SPECIFICATION LIST
JODI BARKER: WETLAND RESERVE PROGRAM
GIBSON COUNTY, TENNESSEE
March 9, 2015
This specification covers the restoration work on the Jodi Barker WRP easement located in Gibson County, Tennessee.
SPECIFICATION
NUMBER DESCRIPTION
CONSTRUCTION SPECIFICATIONS
2 Clearing and Grubbing
3 Structure Removal
6 Seeding, Sprigging, and Mulching
7 Construction Surveys
8 Mobilization and Demobilization
10 Water for Construction
11 Removal of Water
21 Excavation
23 Earthfill
26 Topsoiling
32 Structure Concrete
51 Corrugated Metal Pipe
61 Rock Riprap
83 Timber Fabrication and Installation
95 Geotextile
(210-VI-NEH, May 2001) (2-1)
Construction Specification 2—Clearing and Grubbing
1. Scope The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.
2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.
Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
Any cut, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk. All roots 1-inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other operations shall be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.
3. Marking The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about 6 feet above the ground surface.
4. Clearing and grubbing All trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.
5. Disposal All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the drawings or in a manner specified in Section 7. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from disposal at locations away from the project site.
6. Measurement and payment Method 1—For items of work for which specific units prices are established in the contract, the cleared and grubbed area is measured to the nearest 0.1 acre. Payment for clearing and grubbing is made for the total area within the designated limits at the contract unit price. Such payment will
(210-VI-NEH, May 2001) (2-2) constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 2—For items of work for which specific unit prices are established in the contract, the length of the cleared and grubbed area is measured to the nearest full station (100 feet) along the line designated on the drawing or identified in the specifications. Payment for clearing and grubbing is made for the total length within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 3—For items of work for which specific unit prices are established in the contract, each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet are measured before removal. The size of each tree and snag is determined by measuring its trunk at breast height above the natural ground surface. The size of each log is determined by measuring the butt and by measuring its length from butt to tip.
The size of each stump is measured at the top. Diameter is determined by dividing the measured circumference by 3.14.
Payment for clearing and grubbing of each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet or larger is made at the contract unit price for its size designation as determined by the following schedule:
Measured diameter Size designation
(in) (in)
4 to 8 6
8 to 12 10
12 to 24 18
24 to 36 30
36 to 60 48
Over 60 60
The sum of such payments shall constitute full compensation for clearing and grubbing (including the clearing and grubbing of smaller trees, stumps, snags, logs, brush, shrubs, and roots), applicable permits and associated fees, and rubbish removal. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 4—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in Section 7.
NRCS - Tennessee (2-3) Jodi Barker WRP Wetland Reserve Program February 28, 2015
7. Items of work and construction details
Items of work to be performed in conformance with this specification and the construction details are:
a. Bid Item 4, Field 2: Clearing and Grubbing.
(1) This item includes all work described herein that is required to lower the existing levee in the locations shown on the drawings in field 2 on the Jodi Barker WRP easement. The work shall consist of removing and disposing of the trees, brush, stumps, roots, snags, logs, shrubs, leaves, and vines in the area where the levee will be breached. All materials greater than one (1) inch in diameter shall be removed from the Clearing and Grubbing area where underlying material is to be used for earthfill. Clearing and grubbing shall be completed prior to excavation and/or placing of spoil or fill material.
(2) The Contractor shall clear and grub areas only within the work limit lines where necessary to perform the required work. The work limit lines will be marked in the field by COR or his/her representative. Care shall be taken not to damage any tree that is not designated for removal. Any vegetation and trees that are damaged that are outside of the work limit lines shall be removed and disposed of only if concurred by the COR and in a manner that is acceptable to the COR.
(3) In Section 5, Disposal, cleared and grubbed material shall be disposed of by burning. All precautions necessary to prevent the burning of areas adjacent to the work area shall be used. When conditions exist, such as high winds, extremely dry conditions, or climatic conditions that create heavy concentrations of smoke, burning will not be allowed. All burning shall be performed in conformance with all existing state and local laws. Burning will be allowed on the project sites at locations specified on the drawings or as approved in the field by the COR or his/her representative. Burn locations shall be chosen to protect existing vegetation, the environment, property, and the public. The Contractor shall keep sufficient labor and equipment in the immediate vicinity of his open burning operations that are capable of quickly containing and extinguishing any wildfires that may occur. The Contractor shall continuously watch all open burning operations until all fires have burned out or have been extinguished by water or covered by soil.
All excavation and earthfill related to the disposal of all debris remaining after the fire has been extinguished shall be considered incidental to and subsidiary to clearing and grubbing.
(4) Open burning (see definition of “open burning” below) shall conform to the following conditions:
A. Appropriate permits shall be obtained before burning. Burn permits are normally required from the TN Division of Forestry from Oct 15 through May 15. Additional permit requirements may be imposed as conditions warrant.
NRCS - Tennessee (2-4) Jodi Barker WRP
B. Open burning locations shall be greater than two hundred feet (200’) from a building.
C. The guidance in the brochure “Safe Debris Burning” from the Tennessee Division of Forestry shall be followed.
D. Only wood waste (see definition of “wood waste below”) shall be burned.
Non-woody materials such as the following shall not be burned - tires and rubber products; vinyl siding and shingles; asphalt shingles and other asphalt roofing materials and demolition debris; building material; construction debris and mobile homes; plywood, oriented strand board and treated wood, including railroad ties; asbestos-containing materials, aerosol cans and food cans, copper wire and electrical wires, plastics and other synthetic materials;
paper products, cardboard and newspaper; household trash; leaves, branches and trees not grown on-site.
E. Priming materials used to facilitate such burning shall be limited to #1 or #2 grade fuel oils.
F. A traffic hazard shall not be caused by the air products generated by the fire.
G. No fire shall be ignited while any air pollution emergency episode is in effect in the area of the burn.
H. Compliance with all the requirements from any agency’s permit and with all other applicable requirements, ordinances, or restrictions is the Contractor’s responsibility and is mandatory.
I. Any debris and/or ashes left from burning operations shall be disposed of by burying at locations within the work limit line as approved by the COR. All residue materials shall be buried at least two (2) feet below natural ground in a location that will NOT be under any structure or under any structural earthfill. Earthfill for disposal pits shall be compacted in a maximum of 12 inch lifts with two passes of the earthmoving equipment over the entire fill area to a height 6 inches above surrounding natural ground. All disturbed areas shall be smoothed, transitioned into natural ground, and left in a condition so that the areas can easily be traversed by motorized farm seeding equipment and sloped to drain toward the adjacent ground. .
J. The Contractor is solely liable and responsible for any and all damages and costs resulting from the burning operation and any resulting wildfire.
K. A fire-proof zone shall be created around all burn piles of the width recommended by the TN Division of Forestry, but not less than 20 feet, before burning is commenced.
“Open burning” is defined as the burning of any matter under such conditions that products of combustion are emitted directly into the open atmosphere without passing directly through a stack. Open burning includes, but is not limited to, fires located or burning in a pile on the ground, a barrel, a fire pit, or other semi-enclosure.
“Wood Waste” is defined for this contract as any product which has not lost its basic character as wood, such as bark, sawdust, chips and chemically untreated lumber whose “disposition” by open burning is to solely get rid of or destroy.
Plant life of an herbaceous nature, such as leaves, whether attached, fallen, and/or collected, evergreen needles, and grasses, will be allowed to be burned.
NRCS - Tennessee (2-5) Jodi Barker WRP
Additionally, manufactured lumber products, such as plywood, fiberboard, particleboard, and paneling, are not considered “wood waste”. Painted or artificially stained wood is not considered “wood waste”.
(5) In Section 6, Measurement and Payment, Method 1 will apply.
b. Bid Item 12, Field 4: Clearing and Grubbing.
levee in the locations shown on the drawings in field 4 on the Jodi Barker WRP easement. The work shall consist of removing and disposing of the trees, brush, stumps, roots, snags, logs, shrubs, leaves, and vines in the area where the levee will be breached. All materials greater than one (1) inch in diameter shall be removed from the Clearing and Grubbing area where underlying material is to be the field by COR or his/her representative. Care shall be taken not to damage any tree that is not designated for removal. Any vegetation and trees that are work area shall be used. When conditions exist, such as high winds, extremely dry conditions, or climatic conditions that create heavy concentrations of smoke, burning will not be allowed. All burning shall be performed in conformance with all existing state and local laws. Burning will be allowed on the project sites at locations specified on the drawings or as approved in the field by the COR or his/her representative. Burn locations shall be chosen to protect existing vegetation, the environment, property, and the public. The Contractor shall keep sufficient labor and equipment in the immediate vicinity of his open burning operations that are capable of quickly containing and extinguishing any wildfires that may occur. The Contractor shall continuously watch all open burning
NRCS - Tennessee (2-6) Jodi Barker WRP
B. Open burning locations shall be greater than two hundred feet (200’) from a building.
C. The guidance in the brochure “Safe Debris Burning” from the Tennessee
Division of Forestry shall be followed.
D. Only wood waste (see definition of “wood waste below”) shall be burned.
Non-woody materials such as the following shall not be burned - tires and rubber products; vinyl siding and shingles; asphalt shingles and other asphalt roofing materials and demolition debris; building material; construction debris and mobile homes; plywood, oriented strand board and treated wood, including railroad ties; asbestos-containing materials, aerosol cans and food cans, copper wire and electrical wires, plastics and other synthetic materials;
paper products, cardboard and newspaper; household trash; leaves, branches and trees not grown on-site.
E. Priming materials used to facilitate such burning shall be limited to #1 or #2 grade fuel oils.
F. A traffic hazard shall not be caused by the air products generated by the fire.
G. No fire shall be ignited while any air pollution emergency episode is in effect in the area of the burn.
H. Compliance with all the requirements from any agency’s permit and with all other applicable requirements, ordinances, or restrictions is the Contractor’s responsibility and is mandatory.
I. Any debris and/or ashes left from burning operations shall be disposed of by burying at locations within the work limit line as approved by the COR. All residue materials shall be buried at least two (2) feet below natural ground in a location that will NOT be under any structure or under any structural earthfill. Earthfill for disposal pits shall be compacted in a maximum of 12 inch lifts with two passes of the earthmoving equipment over the entire fill area to a height 6 inches above surrounding natural ground. All disturbed areas shall be smoothed, transitioned into natural ground, and left in a condition so that the areas can easily be traversed by motorized farm seeding equipment and sloped to drain toward the adjacent ground. .
J. The Contractor is solely liable and responsible for any and all damages and costs resulting from the burning operation and any resulting wildfire.
K. A fire-proof zone shall be created around all burn piles of the width without passing directly through a stack. Open burning includes, but is not lumber whose “disposition” by open burning is to solely get rid of or destroy.
NRCS - Tennessee (2-7) Jodi Barker WRP
Additionally, manufactured lumber products, such as plywood, fiberboard,
c. Bid Item 15, Field 6: Clearing and Grubbing.
levee in the locations shown on the drawings in field 6 on the Jodi Barker WRP easement. The work shall consist of removing and disposing of the trees, brush, stumps, roots, snags, logs, shrubs, leaves, and vines in the area where the levee will be breached. All materials greater than one (1) inch in diameter shall be removed from the Clearing and Grubbing area where underlying material is to be the field by COR or his/her representative. Care shall be taken not to damage any tree that is not designated for removal. Any vegetation and trees that are work area shall be used. When conditions exist, such as high winds, extremely dry conditions, or climatic conditions that create heavy concentrations of smoke, burning will not be allowed. All burning shall be performed in conformance with all existing state and local laws. Burning will be allowed on the project sites at locations specified on the drawings or as approved in the field by the COR or his/her representative. Burn locations shall be chosen to protect existing vegetation, the environment, property, and the public. The Contractor shall keep sufficient labor and equipment in the immediate vicinity of his open burning operations that are capable of quickly containing and extinguishing any wildfires that may occur. The Contractor shall continuously watch all open burning
NRCS - Tennessee (2-8) Jodi Barker WRP
B. Open burning locations shall be greater than two hundred feet (200’) from a building.
C. The guidance in the brochure “Safe Debris Burning” from the Tennessee Division of Forestry shall be followed.
D. Only wood waste (see definition of “wood waste below”) shall be burned.
Non-woody materials such as the following shall not be burned - tires and rubber products; vinyl siding and shingles; asphalt shingles and other asphalt roofing materials and demolition debris; building material; construction debris and mobile homes; plywood, oriented strand board and treated wood, including railroad ties; asbestos-containing materials, aerosol cans and food cans, copper wire and electrical wires, plastics and other synthetic materials;
paper products, cardboard and newspaper; household trash; leaves, branches and trees not grown on-site.
E. Priming materials used to facilitate such burning shall be limited to #1 or #2 grade fuel oils.
F. A traffic hazard shall not be caused by the air products generated by the fire.
G. No fire shall be ignited while any air pollution emergency episode is in effect in the area of the burn.
H. Compliance with all the requirements from any agency’s permit and with all other applicable requirements, ordinances, or restrictions is the Contractor’s responsibility and is mandatory.
I. Any debris and/or ashes left from burning operations shall be disposed of by burying at locations within the work limit line as approved by the COR. All residue materials shall be buried at least two (2) feet below natural ground in a location that will NOT be under any structure or under any structural earthfill. Earthfill for disposal pits shall be compacted in a maximum of 12 inch lifts with two passes of the earthmoving equipment over the entire fill area to a height 6 inches above surrounding natural ground. All disturbed areas shall be smoothed, transitioned into natural ground, and left in a condition so that the areas can easily be traversed by motorized farm seeding equipment and sloped to drain toward the adjacent ground. .
J. The Contractor is solely liable and responsible for any and all damages and costs resulting from the burning operation and any resulting wildfire.
K. A fire-proof zone shall be created around all burn piles of the width without passing directly through a stack. Open burning includes, but is not
NRCS - Tennessee (2-9) Jodi Barker WRP
Additionally, manufactured lumber products, such as plywood, fiberboard,
d. Bid Item 24, Field 8: Clearing and Grubbing.
levee in the locations shown on the drawings in field 8 on the Jodi Barker WRP easement. The work shall consist of removing and disposing of the trees, brush, stumps, roots, snags, logs, shrubs, leaves, and vines in the area where the levee will be breached. All materials greater than one (1) inch in diameter shall be removed from the Clearing and Grubbing area where underlying material is to be the field by COR or his/her representative. Care shall be taken not to damage any tree that is not designated for removal. Any vegetation and trees that are work area shall be used. When conditions exist, such as high winds, extremely dry conditions, or climatic conditions that create heavy concentrations of smoke, burning will not be allowed. All burning shall be performed in conformance with all existing state and local laws. Burning will be allowed on the project sites at locations specified on the drawings or as approved in the field by the COR or his/her representative. Burn locations shall be chosen to protect existing vegetation, the environment, property, and the public. The Contractor shall keep sufficient labor and equipment in the immediate vicinity of his open burning operations that are capable of quickly containing and extinguishing any wildfires that may occur. The Contractor shall continuously watch all open burning
NRCS - Tennessee (2-10) Jodi Barker WRP warrant.
B. Open burning locations shall be greater than two hundred feet (200’) from a building.
C. The guidance in the brochure “Safe Debris Burning” from the Tennessee Division of Forestry shall be followed.
D. Only wood waste (see definition of “wood waste below”) shall be burned.
Non-woody materials such as the following shall not be burned - tires and rubber products; vinyl siding and shingles; asphalt shingles and other asphalt roofing materials and demolition debris; building material; construction debris and mobile homes; plywood, oriented strand board and treated wood, including railroad ties; asbestos-containing materials, aerosol cans and food cans, copper wire and electrical wires, plastics and other synthetic materials;
paper products, cardboard and newspaper; household trash; leaves, branches and trees not grown on-site.
E. Priming materials used to facilitate such burning shall be limited to #1 or #2 grade fuel oils.
F. A traffic hazard shall not be caused by the air products generated by the fire.
G. No fire shall be ignited while any air pollution emergency episode is in effect in the area of the burn.
H. Compliance with all the requirements from any agency’s permit and with all other applicable requirements, ordinances, or restrictions is the Contractor’s responsibility and is mandatory.
I. Any debris and/or ashes left from burning operations shall be disposed of by burying at locations within the work limit line as approved by the COR. All residue materials shall be buried at least two (2) feet below natural ground in a location that will NOT be under any structure or under any structural earthfill. Earthfill for disposal pits shall be compacted in a maximum of 12 inch lifts with two passes of the earthmoving equipment over the entire fill area to a height 6 inches above surrounding natural ground. All disturbed areas shall be smoothed, transitioned into natural ground, and left in a condition so that the areas can easily be traversed by motorized farm seeding equipment and sloped to drain toward the adjacent ground. .
J. The Contractor is solely liable and responsible for any and all damages and costs resulting from the burning operation and any resulting wildfire.
K. A fire-proof zone shall be created around all burn piles of the width without passing directly through a stack. Open burning includes, but is not
NRCS - Tennessee (2-11) Jodi Barker WRP collected, evergreen needles, and grasses, will be allowed to be burned.
Additionally, manufactured lumber products, such as plywood, fiberboard, NRCS - Tennessee (2-12) Jodi Barker WRP
THIS PAGE INTENTIONALLY LEFT BLANK
(210-VI-NEH, May 2001) 3-1
Construction Specification 3—Structure Removal
The work shall consist of the removal, salvage, and disposal of structures (including fences) from the designated areas.
2. Marking Method 1—Each structure or structure part to be removed will be marked with stakes, flags, paint, or other suitable method.
Method 2—The area boundaries from which structures must be removed will be marked using stakes, flags, paint, or other suitable method. Structures to remain undisturbed or to be salvaged will be designated by special markings.
3. Removal Method 1—All structures designated for removal in the contract shall be removed to the specified extent and depth.
Method 2—Within the areas so marked, all visible and buried structures identified shall be removed to the specified extent and depth.
4. Salvage Structures or structure parts that are designated to be salvaged shall be carefully removed and neatly placed in the specified or approved storage location. Salvaged structures that are capable of being disassembled shall be dismantled into individual members or sections. Such structures shall be neatly and systematically match marked with paint before disassembly. All connectors and other parts shall be marked to indicate their proper location within the structure and shall be fastened to the appropriate structural member or packed in suitable containers.
Material from fences designated to be salvaged shall be placed outside the work area on the property on which the fence was originally located. Fence wire shall be rolled into uniform rolls of suitable size and neatly piled with other salvaged materials. Posts and rails shall be neatly stacked.
5. Disposal of refuse materials Refuse materials resulting from structure removal shall be disposed of in a manner and at locations specified in section 7 of this specification or in an acceptable manner and at locations approved by the contracting officer. Disposal by burning shall be in accordance with local rules and regulations.
6. Measurement and payment Method 1—For items of work for which specific unit prices are established by the contract, payment for the removal of each structure unit, except fences, is made at the contract unit price.
Fences removed or removed and salvaged are measured to the nearest linear foot. Payment for fence removal or removal and salvage is made at the contract unit prices for each type and size of fence.
(210-VI-NEH, May 2001) 3-2
Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the completion of the work.
Method 2—For items of work for which specific lump sum prices are established by the contract, payment for structure removal is made at the contract lump sum price.
Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed as a contract line item number in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they are made subsidiary are identified in section 7 of this specification.
NRCS - Tennessee (3-3) Jodi Barker WRP Wetland Reserve Easement February 28, 2014
a. Bid Item 9, Field 2: Structure Removal, Screw Gate
(1) This item shall consist of the removal of the screw-gate structure that is located in field 2 as located on the drawings.
(2) In Section 2, Marking, Method 1 will apply.
(3) In Section 3, Removal, Method 1 will apply. The screw gate structure shall be completely removed. The Contractor shall take reasonable care to remove the screw gate assembly with minimal damages.
(4) In Section 4, Salvage, the Contractor shall place the removed flap gate within fifty (50) feet from the access point to field 2 from TN State Highway 152 or as otherwise located in the field by the COR.
(5) In Section 6, Measurement and Payment, Method 2 will apply. Any costs incurred for Excavation and Clearing and Grubbing (Construction Specifications 21 and 2, respectively) are to be considered subsidiary to this bid item.
b. Bid Item 20, Field 6: Structure Removal, Screw Gate and pipe
(1) This item shall consist of the removal and disposal of the existing corrugated pipe and screw-gate structure that is located in field 6 as located on the drawings.
(2) In Section 2, Marking, Method 1 will apply.
(3) In Section 3, Removal, Method 1 will apply. The corrugated pipe and screw gate structure shall be completely removed. The Contractor shall take reasonable care to remove the pipe and screw gate assembly with minimal damages.
(4) In Section 4, Salvage, the Contractor shall place the removed pipe and flap gate within fifty (50) feet from the access point to field 6 from TN State Highway 152 or as otherwise located in the field by the COR.
(5) In Section 6, Measurement and Payment, Method 2 will apply. Any costs incurred for Excavation and Clearing and Grubbing (Construction Specifications 21 and 2, respectively) are to be considered subsidiary to this bid item.
(210-VI-NEH, May 2001) (6-1)
Construction Specification 6—Seeding, Sprigging, and Mulching
The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
2. Material Seed—All seed shall conform to the current rules and regulations of the state where it is being used and shall be from the latest crop available. It shall meet or exceed the standard for purity and germination listed in Section 7.
Seed shall be labeled in accordance with the state laws and the U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.
Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted.
The percent of noxious weed seed allowable shall be as defined in the current State laws relating to agricultural seeds. Each type of seed shall be delivered in separate sealed containers and fully tagged unless exception is granted in writing by the contracting officer.
Fertilizer—Unless otherwise specified, the fertilizer shall be a commercial grade fertilizer. It shall meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contractor shall furnish a supplier's certification of analysis and weight.
When required by the contract, a representative sample of the fertilizer shall be furnished to the contracting officer for chemical analysis.
Inoculants—The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and shall not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer shall be used except four times the amount shall be used when seed is applied using a hydraulic seeder. Seed shall be sown within 24 hours of treatment and shall not remain in the hydraulic seeder longer than 4 hours.
Lime and other soil amendments—Lime shall consist of standard ground agriculture limestone, or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State Department of Agriculture. Other soil amendments shall meet quality criteria and application requirements specified in Section 7.
Mulch tackifiers—Asphalt emulsion tackifiers shall conform to the requirements of ASTM D 977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Non-asphaltic tackifiers required because of environmental considerations shall be as specified in Section 7.
Straw mulch material—Straw mulch shall consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in Section 7. The mulch material shall be air-
(210-VI-NEH, May 2001) (6-2) dry, reasonably light in color, and shall not be musty, moldy, caked, or otherwise of low quality.
The use of mulch that contains noxious weeds is not permitted. The contractor shall provide a method satisfactory to the contracting officer for determining weight of mulch furnished.
Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh, are other mulching materials that may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer's recommendations for methods of application.
3. Seeding mixtures, sod, sprigs, and dates of planting The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting shall be as shown on the plans or as specified in Section 7.
4. Seedbed preparation and treatment Areas to be treated shall be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed shall be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed shall be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.
If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.
Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations shall be removed or disposed of as specified in Section 7.
Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the contracting officer's technical representative (COTR).
5. Seeding, sprigging, fertilizing, mulching, and stabilizing All seeding or sprigging operations shall be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application shall be as specified in Section 7. Unless otherwise specified, seeding or sprigging shall be accomplished within 2 days after final grading is completed and approved.
Fertilizer, lime, and other soil amendments shall be applied as specified in Section 7. When specified, the fertilizer and soil amendments shall be thoroughly incorporated into the soil immediately following surface application.
The rate, amount, and kind of mulching or mesh shall be as specified in Section 7. Mulches shall be applied uniformly to the designated areas. They shall be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material shall be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it shall have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it shall be operated on the contour. Hand methods shall be used where equipment cannot safely operate to perform the work required.
(210-VI-NEH, May 2001) (6-3)
The tackifier shall be applied uniformly over the mulch material at the specified rate, or it shall be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials shall be applied smoothly, but loosely on the designated areas. The edges of these materials shall be buried or securely anchored using spikes or staples as specified in Section 7.
The contractor shall maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance shall consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas shall be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas shall be refertilized, reseeded, and remulched before the new application of the mesh or netting.
6. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in Section 7 and the area calculated to the nearest 0.1 acre.
Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.
When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.
Method 2—For items of work for which specific lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump sum price for the item and will constitute full compensation for the completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds. Progress payments will be determined as specified in Section 7.
Payment of the lump sum contract price will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment.
Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the item(s) to which they are made subsidiary are identified in Section 7.
NRCS - Tennessee (6-4) Jodi Barker WRP Wetland Reserve Program March 9, 2015
a. Bid Item 10, Field 2: Protective Cover, Vegetation & Mulching
(1) This item consists of seedbed preparation, and application of fertilizer, seed, and mulch to establish permanent vegetation on all disturbed areas in Field 2 of the Jodi Barker WRP Easement. The areas to receive protective cover include, earthfill slopes not covered by structures, excavated slopes, and all other disturbed areas.
This item is not intended to cover vegetation establishment in the bottom of the shallow excavation borrow areas.
(2) Fertilizer shall be applied uniformly at the rate of one thousand (1,000) pounds of 6-
12-12 per acre or equivalent. Fertilizer shall be protected against hardening, caking, or loss of plant food values. Caked or hardened fertilizer shall be replaced or pulverized to its original condition before being used. Fertilizer shall be applied prior to seedbed preparation unless application is made with a hydraulic seeding machine, in which case, application may occur after seedbed preparation.
(3) All seed shall conform to the material requirements contained in the current
Tennessee Seed Law and no “Below Standard” seed will be accepted.
(4) Inoculants shall be required on all legumes and shall conform to the material requirements contained in the current Tennessee Seed Law.
(5) In Section 3, Seeding Mixtures, Sod, Sprigs and Dates of Planting, The following per acre mixture shall be utilized according to the appropriate seeding dates and slopes:
(a) From April 15 through August 1, all disturbed areas (except the bottom of borrow areas) shall be seeded with:
Twenty (20) lbs. Japanese Millet, Echinochloa esculenta Ten (10) lbs. Cave-In-Rock Switchgrass, Panicum virgatum
(b) From August 1 through November 30, all disturbed areas (except the bottom of borrow areas) shall be seeded with:
Fifty (50) lbs. Winter Wheat, Five (5) lbs. Brown Top Millet, Two (2) lbs. Ladino Clover
(6) In Section 5, Seeding, Sprigging, Fertilizing, Mulching, and Stabilizing, immediately after broadcasting seed, the seed shall be partially covered by cultipacker, drag, or other methods approved by the Engineer. The seed covering operation shall not be required if the seed is applied with a hydraulic seeding machine. All seeding methods shall result in an even distribution of seed over the disturbed areas.
NRCS - Tennessee (6-5) Jodi Barker WRP
(7) Mulch shall be small grain straw uniformly applied to the seeded areas at a rate of one and one-half (1½) tons per acre. Mulch may be spread by hand or with a mulch-spreading machine. Mechanical mulch stabilization (such as a mulch crimper), the use of a tackifier, or dozer tracks up and down the slope is required.
(8) In Section 6, Measurement and Payment, Method 1 will apply.
b. Bid Item 11, Field 2: Seeding and Mulching, Erosion Control Blanket double-netted erosion control blanket mulch to establish permanent vegetation on disturbed slope areas within Field 2 of the Jodi Barker WRP Easement. The areas to receive protective cover shall include areas as shown on the drawings or otherwise staked in the field by the COR or his/her representative. The specific erosion control blanket and pins to be used on the site must be approved by the Contracting Officer in writing prior to installation.
(2) Fertilizer shall be applied uniformly at the rate of one thousand (1,000) pounds of
6-12-12 per acre or equivalent. Fertilizer shall be protected against hardening, caking, or loss of plant food values. Caked or hardened fertilizer shall be replaced or pulverized to its original condition before being used. Fertilizer shall be applied
Tennessee Seed Law. No “Below Standard” seed will be accepted.
(5) In Section 3, Seeding Mixtures, Sod, Sprigs and Dates of Planting, The following per acre mixture shall be utilized according to the appropriate seeding dates and slopes:
NRCS - Tennessee (6-6) Jodi Barker WRP
(6) In Section 5, Seeding, Sprigging, Fertilizing, Mulching, and Stabilizing, immediately after broadcasting seed, the seed shall be partially covered by cultipacker, drag, or other methods approved by the Engineer. The seed covering operation will not be required if the seed is applied with a hydraulic seeding machine. All seeding methods shall result in an even distribution of seed over the disturbed areas.
On sloped areas too steep or confined for normal farm equipment operation, the entire area shall be tracked with equipment operating up and down the earthen slope in such a manner that the indented cleat portion of the tread marks are approximately on the contour of the slope and cover the entire sloped surface. If too steep for tracking by equipment, the Contractor shall choose to treat the entire area with a hydraulic seeding machine or by hand.
(7) The erosion control blanket shall have a required functional longevity of greater than 6 months to less than 12 months.
(8) The matrix filler for the erosion control blanket shall be 100 percent straw fiber at a rate of not less than 0.50 lbs./sq. yd.
(9) The netting for the erosion control blanket shall be light weight photodegradable polypropylene net with a mesh size no larger than 0.50 inches x 0.50 inches.
(10) Installation and anchoring of the erosion control blanket shall be as follows:
Roll installation shall proceed from downstream to upstream. Begin at the top of the slope by anchoring the blanket in a 6” deep by 6” wide trench with approximately 12” of blanket extended beyond the up-slope portion of the trench.
Backfill and compact the trench only after pinning blanket in the trench. Apply the seed to the prepared seed bed and fold remaining blanket back over filled trench.
Secure the blanket with a row of pins spaced a maximum 20” apart across the width of the blanket. Next roll the blanket down the slope securing the blanket by placing pins in appropriate locations as recommended by the manufacturer, but at a density of not less than a 1.7 staples per sq. yd for slopes 2:1 (H:V) or flatter. For slopes that are 1:1 (H:V) or steeper, pin density shall be 3.4 per/sq. yd. Overlap blankets a minimum of 8 inches and secure lap with pins on a maximum spacing of 10 inches along the lap. Pin length shall be a minimum of 12 inches. Pin diameter shall be minimum 0.20 inches, with a 1.5 inch diameter minimum washer at the top.
(11) In Section 6, Measurement and Payment, the following will apply: For items of work for which specific unit prices are established in the contract, the area treated will be measured with the slope and the area calculated to the nearest square yard (S.Y.). Payment for treatment will be made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.
NRCS - Tennessee (6-7) Jodi Barker WRP
c. Bid Item 14, Field 4: Protective Cover, Vegetation & Mulching mulch to establish permanent vegetation on all disturbed areas in Field 4 of the Jodi Barker WRP Easement. The areas to receive protective cover include, earthfill slopes not covered by structures, excavated slopes, and all other disturbed areas.
or loss of plant food values. Caked or hardened fertilizer shall be replaced or pulverized to its original condition before being used. Fertilizer shall be applied other methods approved by the Engineer. The seed covering operation shall not be spreading machine. Mechanical mulch stabilization (such as a mulch crimper), the
NRCS - Tennessee (6-8) Jodi Barker WRP
d. Bid Item 21, Field 6: Protective Cover, Vegetation & Mulching mulch to establish permanent vegetation on all disturbed areas in Field 6 of the Jodi Barker WRP Easement. The areas to receive protective cover include, earthfill slopes not covered by structures, excavated slopes, and all other disturbed areas.
or loss of plant food values. Caked or hardened fertilizer shall be replaced or pulverized to its original condition before being used. Fertilizer shall be applied other methods approved by the Engineer. The seed covering operation shall not be spreading machine. Mechanical mulch stabilization (such as a mulch crimper), the
NRCS - Tennessee (6-9) Jodi Barker WRP
e. Bid Item 22, Field 6: Seeding and Mulching, Erosion Control Blanket double-netted erosion control blanket mulch to establish permanent vegetation on disturbed slope areas within Field 6 of the Jodi Barker WRP Easement. The areas to receive protective cover shall include areas as shown on the drawings or otherwise staked in the field by the COR or his/her representative. The specific erosion control blanket and pins to be used on the site must be approved by the Contracting Officer in writing prior to installation.
(2) Fertilizer shall be applied uniformly at the rate of one thousand (1,000) pounds of
6-12-12 per acre or equivalent. Fertilizer shall be protected against hardening, caking, or loss of plant food values. Caked or hardened fertilizer shall be replaced or pulverized to its original condition before being used. Fertilizer shall be applied
Tennessee Seed Law. No “Below Standard” seed will be accepted.
(5) In Section 3, Seeding Mixtures, Sod, Sprigs and Dates of Planting, The following per acre mixture shall be utilized according to the appropriate seeding dates and slopes:
(6) In Section 5, Seeding, Sprigging, Fertilizing, Mulching, and Stabilizing, NRCS - Tennessee (6-10) Jodi Barker WRP immediately after broadcasting seed, the seed shall be partially covered by cultipacker, drag, or other methods approved by the Engineer. The seed covering operation will not be required if the seed is applied with a hydraulic seeding machine. All seeding methods shall result in an even distribution of seed over the disturbed areas.
On sloped areas too steep or confined for normal farm equipment operation, the entire area shall be tracked with equipment operating up and down the earthen slope in such a manner that the indented cleat portion of the tread marks are approximately on the contour of the slope and cover the entire sloped surface. If too steep for tracking by equipment, the Contractor shall choose to treat the entire area with a hydraulic seeding machine or by hand.
(7) The erosion control blanket shall have a required functional longevity of greater than 6 months to less than 12 months.
(8) The matrix filler for the erosion control blanket shall be 100 percent straw fiber at a rate of not less than 0.50 lbs./sq. yd.
(9) The netting for the erosion control blanket shall be light weight photodegradable polypropylene net with a mesh size no larger than 0.50 inches x 0.50 inches.
(10) Installation and anchoring of the erosion control blanket shall be as follows:
Roll installation shall proceed from downstream to upstream. Begin at the top of the slope by anchoring the blanket in a 6” deep by 6” wide trench with approximately 12” of blanket extended beyond the up-slope portion of the trench.
Backfill…