CIM-0909-11T-469-0909-01

SCHEDULE OF ITEMS

ATV & Snowmobile Trail Reconstruction

Project Area A Superior National Forest

St. Louis County, Minnesota

12//09 Item No. Description Method

Of Meas.

Pay Unit

Estimate of

Quantity

Unit Price

Amount

Mobilization

L.S.Q.

Lump Sum

201(10) Footnote 1

Clearing & Grubbing Slash Treatment Methods for Brush & Small Trees 6 & 7, and logs 4, Utilization of Timber 2.

C.Q.

Square Yard

1,670

203.03 Removal of Structures and

Obstructions

Cubic

204.10b Footnote 2

Excavation and Embankment Base Aggregate, Type A

1,445

204.12a Footnote 3

(Special Ditch-Johnson Lake)

Linear Foot

204.12b

(V-Ditching)

308(01) Footnote 2 & 6

Minor Crushed Aggregate, Roadway Aggregate

Yard

2,820

503 Grid Paving C.Q. Linear

602(11)

17”x 13”, polymer-coated corrugated steel pipe, 16 ga.

602(12) Footnote 3

French Drain

650a

Road Closure Devices C.Q. Each 0

650b

Parking Bollards C.Q. Each 5

Project Area A (cont.)

703.05a

Screening

1,917

703.05b Footnote 5

Aggregate, Type Surface Course

3,458

Footnote 4

Stockpiled Aggregate, Type Surface Course

1,000

705.02 RipRap Class 1

C.Q.

714(01)

Geotextile C.Q.

1,818

Total =

FOOTNOTES:

1 Clearing is 8’ from centerline.

2 Compacted in-place quantities.

3 Geotextile, Drain Rock and Riprap are included in this pay item.

4 Quantity is as measured in the Stockpile (Stockpile Volume).

5 Quantity is as measured in Loose Volume 6 Quantity includes 240 CY ( Loose Volume) (GFM) @ Long Lake Trail.

GFM = Government furnished material.

Project Area B

Of Meas.

Pay Unit

Estimate of

Quantity

Unit

201(10) Footnote 1

Clearing & Grubbing Slash Treatment Methods for Brush & Small Trees 6 & 7, and logs 4, Utilization of Timber 2.

Footnote 2

Footnote 2

3,400

503 Grid Paving C.Q. Linear

57”x 38”, polymer-coated corrugated steel pipe, 14 ga.

602(12) Footnote 3

French Drain

650a

Road Closure Devices C.Q. Each 4

1,040

Footnote 5

4,520

Footnote 4

Total = $____ ___

FOOTNOTES:

1 Clearing is 10’ from centerline.

2 Compacted in-place quantities.

3 Geotextile, Drain Rock and Riprap are included in this pay item.

4 Quantity is as measured in the Stockpile (Stockpile Volume).

5 Quantity is as measured in Loose Volume

Project Area C

Of Meas.

Pay Unit

Estimate of

Quantity

Unit

Footnote 2

Footnote 2

28”x 30”, polymer-coated corrugated steel pipe, 16 ga.

Footnote 5

Footnote 4

714.01

Geotextile

1,070

714.02

GeoWeb , Swamp Crossing

Total = $____ ___

FOOTNOTES:

2 Compacted in-place quantities.

3 Geotextile, Drain Rock and Riprap are included in this pay item.

4 Quantity is as measured in the Stockpile (Stockpile Volume).

5 Quantity is as measured in Loose Volume