NRCS May 2010 WV Deckers Creek Acid Mine Drainage Treatment Project Laurel Run Sites 1&2 Page 1 of 1
Laurel Run Sites 1 & 2
Deckers Creek Acid Mine Drainage Treatment Project
Construction and Material Specification List
No. Date Title
CONSTRUCTION SPECIFICATIONS
2 5/01 Clearing & Grubbing 3 5/01 Structure Removal 5 1/09 Pollution Control 6 5/01 Seeding, Sprigging, and Mulching 7 1/09 Construction Surveys 8 5/01 Mobilization & Demobilization
11 5/01 Removal of Water 21 5/01 Excavation 23 1/09 Earthfill 24 5/01 Drainfill 44 1/09 Corrugated Polyethylene Pipe 61 1/09 Rock Riprap 94 5/01 Contractor Quality Control 95 5/01 Geotextile
405 2/10 Silt Fence 424 4/10 Crushed Aggregate Paving
MATERIAL SPECIFICATIONS
521 5/01 Aggregates for Drainfill and Filters 523 11/05 Rock for Riprap 548 1/09 Corrugated Polyethylene Pipe 592 1/09 Geotextile
(210-VI-NEH, May 2001) 2-1
Construction Specification 2
Clearing and Grubbing
1. Scope
The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.
2. Protection of Existing Vegetation
Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.
Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.
Any cut, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk. All roots 1-inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other operations shall be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.
3. Marking
The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about
6 feet above the ground surface.
4. Clearing and Grubbing
All trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.
(210-VI-NEH, May 2001) 2-2
5. Disposal
All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the drawings or in a manner specified in section 7. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from disposal at locations away from the project site.
6. Measurement and Payment
Method 1—For items of work for which specific units prices are established in the contract, the cleared and grubbed area is measured to the nearest 0.1 acre. Payment for clearing and grubbing is made for the total area within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 2—For items of work for which specific unit prices are established in the contract, the length of the cleared and grubbed area is measured to the nearest full station (100 feet) along the line designated on the drawing or identified in the specifications. Payment for clearing and grubbing is made for the total length within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 3—For items of work for which specific unit prices are established in the contract, each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of
10 feet are measured before removal. The size of each tree and snag is determined by measuring its trunk at breast height above the natural ground surface. The size of each log is determined by measuring the butt and by measuring its length from butt to tip. The size of each stump is measured at the top. Diameter is determined by dividing the measured circumference by 3.14.
Payment for clearing and grubbing of each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet or larger is made at the contract unit price for its size designation as determined by the following schedule:
Measured diameter Size designation
(in) (in)
4 to 8 6
8 to 12 10
12 to 24 18
24 to 36 30
36 to 60 48
Over 60 60
(210-VI-NEH, May 2001) 2-3
The sum of such payments shall constitute full compensation for clearing and grubbing (including the clearing and grubbing of smaller trees, stumps, snags, logs, brush, shrubs, and roots), applicable permits and associated fees, and rubbish removal. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
Method 4—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 7.
NRCS February 2010
Laurel Run Sites 1&2 2-4
7. Items of Work and Construction Details
The items of work and construction details to be performed in conformance with this specification are:
Bid Item 1, Clearing and Grubbing
(1) This item shall consist of all equipment, tools, and labor necessary to clear and grub all work areas in conformance with this specification and as shown on the plans, except that grubbing of roots is not required in the Disposal Areas designated on the plans.
(2) The work of clearing and grubbing shall include the removal and proper disposal of all trash, garbage, abandoned appliances, and any miscellaneous structural debris within the areas to be cleared and grubbed. Structural material that is to remain on-site or not be disturbed will be designated prior to construction.
(3) All trees cleared and greater than 3-inches in diameter at the base shall be salvaged and stockpiled on site at locations coordinated with the landowner and approved by the COTR. The
Contractor shall remove and dispose of tree-top portions of the salvaged trees, tree-tops being branch sections less than 3-inches in diameter.
(4) Disposal of woody debris may be by burning or removal from the site. The Contractor is responsible for obtaining any necessary burning permits. All non-woody debris shall be disposed off-site. The Contractor shall select off-site disposal locations for approval by the
Contracting Officer.
(5) Explosives are prohibited.
(6) The Contractor shall exercise discretion to minimize soil disturbed by clearing and grubbing.
Clear and grub only as necessary to complete the work shown on the plans.
(7) Method 4 of Section 6 shall apply. Partial payments of the lump sum bid price may be made as the work proceeds and supported by invoices presented by the Contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.
(210-VI-NEH, May 2001) 3-1
Construction Specification 3
Structure Removal
The work shall consist of the removal, salvage, and disposal of structures (including fences) from the designated areas.
2. Marking
Method 1—Each structure or structure part to be removed will be marked with stakes, flags, paint, or other suitable method.
Method 2—The area boundaries from which structures must be removed will be marked using stakes, flags, paint, or other suitable method. Structures to remain undisturbed or to be salvaged will be designated by special markings.
3. Removal
Method 1—All structures designated for removal in the contract shall be removed to the specified extent and depth.
Method 2—Within the areas so marked, all visible and buried structures identified shall be removed to the specified extent and depth.
4. Salvage
Structures or structure parts that are designated to be salvaged shall be carefully removed and neatly placed in the specified or approved storage location. Salvaged structures that are capable of being disassembled shall be dismantled into individual members or sections. Such structures shall be neatly and systematically match marked with paint before disassembly. All connectors and other parts shall be marked to indicate their proper location within the structure and shall be fastened to the appropriate structural member or packed in suitable containers.
Material from fences designated to be salvaged shall be placed outside the work area on the property on which the fence was originally located. Fence wire shall be rolled into uniform rolls of suitable size and neatly piled with other salvaged materials. Posts and rails shall be neatly stacked.
5. Disposal of Refuse Materials
Refuse materials resulting from structure removal shall be disposed of in a manner and at locations specified in section 7 of this specification or in an acceptable manner and at locations approved by the contracting officer.
Disposal by burning shall be in accordance with local rules and regulations.
(210-VI-NEH, May 2001) 3-2
Method 1—For items of work for which specific unit prices are established by the contract, payment for the removal of each structure unit, except fences, is made at the contract unit price. Fences removed or removed and salvaged are measured to the nearest linear foot. Payment for fence removal or removal and salvage is made at the contract unit prices for each type and size of fence.
Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the completion of the work.
Method 2—For items of work for which specific lump sum prices are established by the contract, payment for structure removal is made at the contract lump sum price.
Such payment will constitute full compensation for all labor, equipment, tools, applicable permits and associated fees for burning and disposal of refuse, and all other items necessary and incidental to the completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed as a contract line item number in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and items to which they are made subsidiary are identified in section 7 of this specification.
Laurel Run Sites 1&2 3-3
Items of work to be performed in conformance with this specification and construction details are:
Subsidiary Item, Structure Removal
(1) This item shall consist of all equipment, tools, and labor necessary to remove the existing culvert for the installation of Culvert C10.
(2) Method 1 of Section 2 shall apply.
(3) Method 1 of Section 3 shall apply.
(4) The existing culvert shall be disposed off-site. The Contractor shall select off-site disposal locations for approval by the Contracting Officer.
(5) No separate payment will be made for this item. Compensation will be included in the respective payments for:
Bid Item 11, Culvert, 18-Inch HDPE Pipe, Construction Specification (CS) 44.
Chapter 2 National Standard Construction Specifications Part 642 National Engineering Handbook
(210-VI-NEH, January 2009) 5-1
Construction Specification 5
Pollution Control
The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.
2. Material
All material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.
3. Erosion and Sediment Control Measures and Works
The measures and works shall include, but are not limited to, the following:
Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.
Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.
Mulching—Mulching to provide temporary protection of the soil surface from erosion.
Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.
Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.
Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Sediment filters—Straw bale filters or geotextile sediment fences trap sediment from areas of limited runoff.
(210-VI-NEH, January 2009) 5-2
Sediment filters shall be properly anchored to prevent erosion under or around them. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures.
These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.
4. Chemical Pollution
The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to dispose of chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction activities. At the completion of the construction work, sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.
Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.
5. Air Pollution
The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.
Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.
All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.
(210-VI-NEH, January 2009) 5-3
6. Maintenance, Removal, and Restoration
All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.
7. Measurement and Payment
Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.
Laurel Run Sites 1&2 5-4
8. Items of Work and Construction Details
Items of work to be performed in conformance with this specification and construction details are:
Bid Item 2, Pollution Control
(1) This item shall consist of the materials, supplies, equipment, tools, and labor necessary to install and maintain the pollution control measures described in this section; to remove and dispose of any temporary pollution control measures; and the construction management necessary to construct and maintain all required temporary and permanent features in a sequence that minimizes soil erosion and sedimentation of streams such that full compliance with local, state, and federal pollution, erosion, and sediment control statues, the general terms of this specification, the plans, and the pollution control requirements of this contract are achieved.
(2) Payment for this item includes
(a) construction and maintenance of the Stabilized Construction Entrance
(b) construction of new access road from the Stabilized Construction Entrance to the existing access road
(c) stone paving and maintenance of existing access road to the limits of the Construction
Staging Area and preparation and maintenance of the Construction Staging Area
(d) the stone paving of the existing access road at Culvert C10
(e) installation of Temporary Runoff Diversions and Rock Check Dams.
(3) The Sediment filters paragraph of Section 3 does not apply.
(a) Straw and hay bales are prohibited for use as a pollution control measure.
(b) Geotextile silt fences trap sediment from areas of limited runoff. Silt fences shall be properly anchored to prevent erosion under or around them. Silt fences are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.
(4) The Contractor is responsible for obtaining an Air Quality Permit from the West Virginia Department of Environmental Protection.
(5) The Contractor shall prepare a Groundwater Protection Plan (GPP) as required by the West Virginia
Department of Environmental Protection. The Contractor shall maintain the document on-site and meet the requirements of the GPP throughout construction.
Laurel Run Sites 1&2 5-5
(6) Silt Fence installations are paid by Bid Item 15, Silt Fence, Construction Specification 405.
(7) All permanent and temporary pollution control measures shall be maintained throughout the construction period. As a minimum, all pollution control measures shall be inspected every seven days and immediately following rainfall in excess of one-half inch in 24 hours, or six-inches of snowmelt in 24 hours. All damaged measures shall be repaired or replaced immediately. Maintenance work includes the removal and disposal of sediment from all pollution control measures.
(8) The minimum construction sequencing required for pollution control shall include the following in the sequence shown:
(a) construction of Stabilized Construction Entrance,
(b) preparation of staging area,
(c) installation of pollution control measures prior to clearing and grubbing operations in areas tributary to those pollution control measures,
(d) construct design features from downstream to upstream, completing a downstream feature prior to excavating for an upstream feature,
(e) removal and disposal of sediment accumulations in permanent constructed measures immediately prior to demobilization.
(9) Temporary seeding shall be installed on all disturbed areas not having vegetative cover for more than
3 days.
(a) lime shall be applied at the rate of 3 tons per acre,
(b) 10-20-20 fertilizer shall be applied at the rate of 400 pounds per acre,
(c) lime and fertilizer for temporary seeding shall be incorporated into the soil by mechanical methods, areas inaccessible or unsafe for mechanical equipment may have lime and fertilizer broadcast onto the earth surface,
(d) apply annual ryegrass at the rate of 60 pounds per acre for temporary seeding,
(e) mulch shall be applied at the rate of 2 tons per acre, only small-grain straw is permitted.
(10) Method 3 of Section 7 shall apply.
(11) Items of work subsidiary to this bid item are:
Excavation, Access Road, Unclassified, Construction Specification (CS) 21;
Geotextile, Access Road, CS 95;
Crushed Aggregate Paving, C33 Size 1, CS 424;
Crushed Aggregate Paving, 1½ Inch Crusher Run, CS 424.
(210-VI-NEH, May 2001) 6-1
Construction Specification 6
Seeding, Sprigging, and Mulching
The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.
Seed—All seed shall conform to the current rules and regulations of the state where it is being used and shall be from the latest crop available. It shall meet or exceed the standard for purity and germination listed in section 7.
Seed shall be labeled in accordance with the state laws and the U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.
Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable shall be as defined in the current State laws relating to agricultural seeds. Each type of seed shall be delivered in separate sealed containers and fully tagged unless exception is granted in writing by the contracting officer.
Fertilizer—Unless otherwise specified, the fertilizer shall be a commercial grade fertilizer. It shall meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contractor shall furnish a supplier's certification of analysis and weight. When required by the contract, a representative sample of the fertilizer shall be furnished to the contracting officer for chemical analysis.
Inoculants—The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and shall not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer shall be used except four times the amount shall be used when seed is applied using a hydraulic seeder. Seed shall be sown within 24 hours of treatment and shall not remain in the hydraulic seeder longer than 4 hours.
Lime and other soil amendments—Lime shall consist of standard ground agriculture limestone, or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State Department of Agriculture. Other soil amendments shall meet quality criteria and application
(210-VI-NEH, May 2001) 6-2 requirements specified in section 7.
Mulch tackifiers—Asphalt emulsion tackifiers shall conform to the requirements of ASTM D 977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting.
Nonasphaltic tackifiers required because of environmental considerations shall be as specified in section 7.
Straw mulch material—Straw mulch shall consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 7. The mulch material shall be air-dry, reasonably light in color, and shall not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor shall provide a method satisfactory to the contracting officer for determining weight of mulch furnished.
Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh, are other mulching materials that may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer's recommendations for methods of application.
3. Seeding Mixtures, Sod, Sprigs, and Dates of Planting
The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting shall be as shown on the plans or as specified in section 7.
4. Seedbed Preparation and Treatment
Areas to be treated shall be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed shall be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed shall be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.
If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.
Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations shall be removed or disposed of as specified in section 7.
Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the contracting officer's technical representative (COTR).
(210-VI-NEH, May 2001) 6-3
5. Seeding, Sprigging, Fertilizing, Mulching, and Stabilizing
All seeding or sprigging operations shall be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application shall be as specified in section 7. Unless otherwise specified, seeding or sprigging shall be accomplished within 2 days after final grading is completed and approved.
Fertilizer, lime, and other soil amendments shall be applied as specified in section 7. When specified, the fertilizer and soil amendments shall be thoroughly incorporated into the soil immediately following surface application.
The rate, amount, and kind of mulching or mesh shall be as specified in section 7. Mulches shall be applied uniformly to the designated areas. They shall be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material shall be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it shall have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it shall be operated on the contour. Hand methods shall be used where equipment cannot safely operate to perform the work required.
The tackifier shall be applied uniformly over the mulch material at the specified rate, or it shall be injected into the mulch material as it is being applied. Mesh or netting stabilizing materials shall be applied smoothly, but loosely on the designated areas. The edges of these materials shall be buried or securely anchored using spikes or staples as specified in section 7.
The contractor shall maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance shall consist of the repair of areas damaged by water erosion, wind, fire, or other causes.
Such areas shall be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas shall be refertilized, reseeded, and remulched before the new application of the mesh or netting.
Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in section 7 and the area calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the
When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of
(210-VI-NEH, May 2001) 6-4 the work.
Method 2—For items of work for which specific lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump sum price for the item and will constitute full compensation for the completion of the work.
Method 3—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds. Progress payments will be determined as specified in section 7. Payment of the lump sum contract price will constitute full compensation for completion of the work.
All Methods—The following provisions apply to all methods of measurement and payment. Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the item(s) to which they are made subsidiary are identified in section 7.
NRCS April 2010
Laurel Run Sites 1&2 6-5
The items of work and construction details to be performed in conformance with this specification are:
Bid Item 3, Seeding and Mulching
(1) This item shall consist of seeding and mulching to permanent cover all disturbed areas within the designated construction limits shown on the plans, excluding areas occupied with rock riprap and below the crest elevations of permanent pools of water.
(2) No permanent seeding shall be done between October 1 and December 1 unless otherwise approved by the Contracting Officer.
(3) The approved lines and grades for permanent seeding at the time of permanent seeding shall be maintained during and after the seeding and mulching operation. Any area that has been damaged or had part or all of the seeding material removed by any means shall be repaired before acceptance will be made. The area to be repaired shall be filled and/or graded as needed to bring it back to neat lines, fertilized, seedbed prepared, and then seeded and mulched at the specified rates.
(4) Lime shall be applied at an application rate of 5 tons per acre.
(5) The following minimum amounts of fertilizer shall be applied per acre prior to seeding:
(a) Nitrogen (N) 100 Lb.
Phosphoric Acid (P2O5) 100 Lb.
Potash (K2O) 100 Lb.
(b) The required application can be achieved by applying fertilizer having an analysis of 10-10-10 at the rate of 1000 pounds per acre or 23 pounds per 1000 square feet.
(6) Seedbed Preparation.
(a) Lime and fertilizer shall be applied prior to final seedbed preparation.
(b) Seeding shall be accomplished immediately after achieving final grade. Seedbed preparation shall only be required on compacted, polished, or freshly cut soil surfaces. Where special seedbed preparation is required, the hardened soil shall be loosened to a depth of 1½ inches; either by equipment or manual methods.
Laurel Run Sites 1&2 6-6
(7) Seed.
(a) Each seed species shall comply with the West Virginia Department of Agriculture’s standards for purity and germination. The seed mixtures and application rates are:
Seed Rate,lb/ac.
Orchard Grass 10 Birdsfoot Trefoil 10 Ladino Clover 5 Red Top 3 Perennial Ryegrass 5
(b) When seeding is performed between April 15-August 1 or December 1-March 1, the specified rates of seed per acre shall be increased by 50 percent.
(8) Mulch material shall be wheat, barley, oat or rye straw only. Mulch shall be applied uniformly over all seeded areas at the specified rate per acre. Application shall be within 24 hours after seeding. A mechanical blower may be used to apply the mulch. Application rates and material requirements shall be in accordance with the following table:
Time Period vs. Mulching Requirements for Revegetation of Construction Sites
Time Period Suitability Mulch Application tons/acre
March 1 – April 15 August 1 – October 1
Best Seeding Periods Small grain straw*
April 15 – August 1 High Risk Period Small grain straw 2.5
October 1 – December 1 Do Not Seed - -
December 1 – March 1 Good Seeding Period Small grain straw 2.5
* Small grain straw shall consist of wheat, oat, or rye straw.
(9) Mulch Tackifier
(a) A non-asphaltic mulch tackifier consisting of a free-flowing silicate powder with hydrophilic polymer additives mixed in water shall be applied according to the manufacturer's recommendation.
Laurel Run Sites 1&2 6-7
(b) The Contractor shall submit in writing to the Contracting Officer a request for approval of the selected mulch tackifying agent. The request by the Contractor shall include sufficient descriptive information (manufacturer's specification) to allow a determination of acceptability and suitability to be made.
(c) In lieu of applying a mulch tackifying agent or asphalt emulsion, mulch may be crimped in place using disk equipment or light crawler-type construction equipment as approved by the Engineer.
(10) Method 1 of Section 6 shall apply.
(210-VI-NEH, January 2009) 7-1
Construction Specification 7
Construction Surveys
The work consists of performing all surveys, measurements, and computations required by this specification.
2. Equipment and Material
Equipment for construction surveys shall be of a quality and condition to provide the required accuracy. The equipment shall be maintained in good working order and in proper adjustment at all times. Records of repairs, calibration tests, accuracy checks, and adjustments shall be maintained and be available for inspection by the engineer. Equipment shall be checked, tested, and adjusted as necessary in conformance with manufacturer's recommendations.
Material is field notebooks, stakes, templates, platforms, equipment, spikes, steel pins, tools, and all other items necessary to perform the work specified.
3. Quality of Work
All work shall follow recognized professional practice and the standards of the industry unless otherwise specified in section 9 of this specification. The work shall be performed to the accuracy and detail appropriate for the type of job. Notes, sketches, and other data shall be complete, recorded neatly, legible, reproducible and organized to facilitate ease in review and allow reproduction of copies for job documentation. Survey equipment that requires little or no manual recording of field data shall have survey information documented as outlined in section 9 of this specification.
All computations shall be mathematically correct and shall include information to identify the bid item, date, and who performed, checked, and approved the computations. Computations shall be legible, complete, and clearly document the source of all information used including assumptions and measurements collected.
If a computer program is used to perform the computations, the contractor shall provide the engineer with the software identification, vendor's name, version number, and other pertinent data before beginning survey activities. Computer generated computations shall show all input data including values assigned and assumptions made.
The elevations of permanent and temporary bench marks shall be determined and recorded to the nearest 0.01 foot. Differential leveling and transit traverses shall be of such precision that the error of vertical closure in feet shall not exceed plus or minus 0.1 times the square root of the traverse distance in miles. Linear measurements
(210-VI-NEH, January 2009) 7-2 shall be accurate to within 1 foot in 5,000 feet, unless otherwise specified in section 9 of this specification. The angular error of closure for transit traverses shall not exceed 1 minute times the square root of the number of angles turned.
The minimum requirements for placing slope stakes shall be at 100-foot stations for tangents, as little as 25 feet for sharp curves, breaks in the original ground surface and at any other intermediate stations necessary to ensure accurate location for construction layout and measurement. Slope stakes and cross sections shall be perpendicular to the centerline. Significant breaks in grade shall be determined for cross sections. Distances shall be measured horizontally and recorded to the nearest 0.1 foot. Side shots for interim construction stakes may be taken with a hand level.
Unless otherwise specified in section 9 of this specification, measurements for stationing and establishing the location of structures shall be made to the nearest 0.1 foot.
Elevations for concrete work, pipes, and mechanical equipment shall be determined and recorded to the nearest
0.01 foot. Elevations for earth work shall be determined and recorded to the nearest 0.1 foot.
4. Primary Control
The baselines and bench marks for primary control, necessary to establish lines and grades needed for construction are shown on the drawings and have been located on the job site.
These baselines and bench marks shall be used as the origin of all surveys, layouts, and measurements to establish construction lines and grades. The contractor shall take all necessary precautions to prevent the loss or damage of primary control points. Any stakes or control points lost or damaged by construction activity will be reestablished by the contractor or at contractor expense.
5. Construction Surveys
Before work starts that requires contractor performed surveys, the contractor shall submit in writing for the engineer's review: the name, qualifications, and experience of the individuals to be assigned to the survey tasks.
Method 1—Contractor performed surveys shall include:
• checking and any supplemental or interim staking
• performing quantity surveys, measurements, and computations for progress payment
• other surveys as described in section 9 of this specification
Method 2—Contractor performed surveys shall consist of all work necessary for:
• establishing line and grade for all work
(210-VI-NEH, January 2009) 7-3
• setting slope stakes for all work
• checking and any supplemental or interim staking
• establishing final grade stakes
• performing quantity surveys, measurements, and computations for progress payment
• other surveys as described in section 9 of this specification
Method 3—Contractor performed surveys shall consist of all work necessary for:
• establishing line and grade for all work
• setting slope stakes for all work
• checking and any supplemental or interim staking
• establishing final grade stakes
• performing quantity surveys, measurements, and computations for progress payments
• performing original (initial) and final surveys for determinations of final quantities
• other surveys as described in section 9 of this specification.
6. Staking
The construction staking required for the item shall be completed before work on any item starts. Construction staking shall be completed as follows or as otherwise specified in section 9 of this specification:
Clearing and grubbing—The boundary of the area(s) to be cleared and grubbed shall be staked or flagged at a maximum interval of 200 feet, closer if needed, to clearly mark the limits of work. When contractor staking is the basis for determining the area for final payment, all boundary stakes will be reviewed by the engineer before start of this work item.
Excavation and Fill—Slope stakes shall be placed at the intersection of the specified slopes and ground line.
Slope stakes and the reference stakes for slopes shall be marked with the stationing, required cut or fill, slope ratio, and horizontal distance from the centerline or other control line. The minimum requirements for placing slope stakes are outlined in section 3, Quality of work.
Structures—Centerline and offset reference line stakes for location, alignment, and elevation shall be placed for all structures.
7. Records
All survey data shall be recorded in fully identified standard hard-bound engineering survey field notebooks with consecutively numbered pages. All field notes and printed data shall include the purpose or description of the work, the date the work was performed, weather data, sketches, and the personnel who performed and checked the work. Electronically generated survey data and computations shall be bound, page numbered, and cross referenced in a bound field notebook containing the index for all survey activities. All work shall follow
(210-VI-NEH, January 2009) 7-4 recognized professional practice.
The construction survey records shall be available at all times during the progress of the work for examination and use by the engineer and when requested, copies shall be made available. The original field notebooks and other records shall be provided to and become the property of the owner before final payment and acceptance of all work.
Complete documentation of computations and supporting data for progress payments shall be submitted to the engineer with each invoice for payment as specified in section 9 of the specification. When the contractor is required to conduct initial and final surveys as outlined in section 5, Construction Surveys, notes shall be provided as soon as possible after completion to the engineer for the purpose of determining final payment quantities.
8. Payment
Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation of correct and accurate invoices by the contractor showing related costs and evidence of the charges of suppliers, subcontractors, and others for supplies furnished and work performed.
Invoices for the total amount of the contract price will not be accepted until all surveys are complete and required documentation has been determined complete. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of all work under the bid item.
Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the contractor's approved construction schedule. Payment of the lump sum contract price will constitute full compensation for completion of all work under this bid item.
All Methods—Payment will not be provided under this item for the purchase price of materials or equipment having a residual value.
Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the item to which they are made subsidiary are identified in section 9 of this specification.
Laurel Run Sites 1&2 7-5
9. Items of Work and Construction Details
The items of work and construction details to be performed in conformance with this specification are:
Subsidiary Item, Construction Surveys
(1) This item shall consist of all materials, supplies, equipment, tools, and labor necessary to provide horizontal and vertical control for all the works of improvement as shown on the plans.
(2) The person responsible for construction surveys shall be a professional surveyor licensed to practice surveying in West Virginia, and shall have 5 years experience in the methods of survey for construction.
(3) Method 2 of Section 5 shall apply.
(4) The Contractor shall provide survey documentation and supporting data for progress payments in the type and format specified by the Contracting Officer’s Technical Representative.
(5) No separate payments will be made for this item. Compensation will be included in the respective
Bid Item 14, Contractor Quality Control, Construction Specification (CS) 94.
(210-VI-NEH, May 2001) 8-1
Construction Specification 8
Mobilization and Demobilization
The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract. Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.
2. Equipment and Material
Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.
Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.
This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.
3. Payment
Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment. Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.
Payment will not be…