Software Release to Production
Document Name: TCO-SYS-002-Software Release-Flowchart
Purpose: Complete and Submit a Software Release Instruction Form for Processing
DRAFT 05/10/2011
CMSG reviews the SRIF
Software Release to
Production
Lead Tester to prepare Software Release
Information Form in accordance to instructions –
TCO-SYS-002-Software Release-INST.
Click to use the latest copy of the SRIF.
Locate software and/or data and secure:
S:\TCO-Shared\Test_Area is where the files are kept
S:\TCO-Shared\Test_To_PROD is where CMSG copies the files for IPUSO to retrieve
STOP
If Siteminder / eAuth interface, submit to IPUSO 2 weeks prior to release date.
Initial Web
Release
Updates to existing webs
New Existing
Notify CMSG two working days before release date.
Database
Changes?
No
For DB changes, CMSG submits an
RFA and a WRTS request to the
DBMO group
Yes
E-mail the completed Web Software Release
Information Form (SRIF) to CMSG mokansasc2-cmsg@one.usda.gov
Is SRIF Correct
No
Yes
CMSG sends request to Tester to VERIFY LISTING:
Verification
Successful?
NO
CMSG creates RFA (Request for Action) and submits to
IPUSO for implementation.
Yes
Database
Changes?
For DB changes, IPUSO passes
RFA to
DBMO
CMSG collects RFA numbers and notifies lead tester to review (Reply to all in original e-mail)
Completion of RFA Implementation:
1) IPUSO will update the TCO Target to Production
SharePoint Calendar.
2) All interested parties refer to the TCO Target to
Production SharePoint Calendar for production status
No
Yes
Lead tester reviews RFA to verify:
1. Date to production
2. SME / POC information is correct
3. Any pre-requisites are included
4. Monitoring and healthcheck url’s are correct
5. Correct System Release Checklst has been included.
(Lead Tester reviews RFAs. If corrections are needed, work with development or other contacts if necessary, then notify CMSG of updates needed).
TCO testers works with CMSG to understand verification issue and re-submit
SRIF if necessary.
Lead Tester sends Confirmation e-mail to CMSG.
Lead Tester verify the file(s) listed in the test to production listing is the same as the file CMSG originally controlled and loaded in the cert environment (file(s), size, or date / time)
NOTE - If more than one kc-287 is being used, then the file listing CMSG sends for review will contain the latest move of each file that has to be loaded in production.
Return to
Master
Flow
24-hour notification required if after hours work required https://fsa.sc.egov.usda.gov/mgr/itsd/otc/TCO/Shared%20Documents/Forms/AllItems.aspx https://fsa.sc.egov.usda.gov/mgr/itsd/otc/TCO/Shared%20Documents/SOP%20Work%20Folder/MASTER%20SOP%20MOCK%20UP/Master%20SOP.htm
08/25/2010 1.0 Document for Review Glenn Olvera
06/07/2011 1.0 New Flow Template Keith Rose
08/04/2010 1.0 Document layout - DRAFT Glenn Olvera
Date Version Comments Author
Version Control Summary
TCO-SYS-KC287-TEST-001Version 1.0 04/22/2010
| TCO-SYS-002-Software Release-FlowChart.vsd |
| Software Release |
| Version Control |
File details come from the government source that posted it. Updated .