Detailed Acceptance Test Plan for (Application) – (release name/number)

For the Testing and Certification Office

Prepared by: TCO TESTING GROUP’s

Version 1.6

MASTER

Testing and Certification Office

Detailed Acceptance Test Plan Page 2 of 10 Master

Detailed Acceptance Test Plan

VERSION HISTORY

Version Date Summary of Changes Author

Detailed Acceptance Test Plan Page 3 of 10

Table of Contents

1.0 GENERAL INFORMATION

1.1 Summary

PROJECT NAME

PROJECT DESCRIPTION

PROGRAM SPONSOR

PROJECT SCHEDULE

WAIVERS AND RISK ACCEPTANCE

1.2 Project Team Members

PROJECT TEAM

1.3 Environment and Pretest Background

REFERENCES

TEST ENVIRONMENT

TEST DATA USED

SOFTWARE DEPENDENCIES

TOOLS

TABLES UPDATED

FILES CREATED / UPDATED / DELETED (S36/AS400)

2.0 PLAN

2.1 High Level Functional Summary

FUNCTIONAL OUTLINE

2.2 Out of Scope Details

OUT OF SCOPE

3.0 SIGNATURE and ACCEPTANCE

Detailed Acceptance Test Plan Page 4 of 10

1.0 GENERAL INFORMATION

1.1 Summary

PROJECT NAME

Application/Data

Warehouse Acronym Application/Data Warehouse Name

PROJECT DESCRIPTION

Overview

PROGRAM SPONSOR

Organization

PROJECT SCHEDULE

Milestone Planned Start Date Planned Finish Date

Receive Requirement(s)

Complete Detailed Acceptance Test Plan

Perform Requirement Gap Analysis

Write Test Cases

Perform Peer Review

Configure the Application

Execute Test Cases

Stress Testing

Release Software to Production

Close Project

Microsoft Project Schedule Link:

Detailed Acceptance Test Plan Page 5 of 10

WAIVERS AND RISK ACCEPTANCE

Type Waiver Document / Defect Number(s)

Architecture Standards Exceptions

Configuration Exceptions

FSA Style Guide Exceptions

PII Data Exception

Security Exceptions

Section 508 Exceptions

Software/Requirements Exceptions

1.2 Project Team Members

PROJECT TEAM

Division/Role Name

TCO Manager (chief)

Application Tester Lead

Application Tester(s)

Remote Tester(s)

TCO - CMSG Team ug-mokansasc2-cmsg

TCO - CMSG S36/AS400 Member(s) Melvin Hawkins, Christine Jones, Melissa Mayeaux

Development Manager (chief)

Developer Lead

Project Manager

Program Sponsor Manager (chief)

Program Specialist

Other(s)

Project Team Roles and Responsibilities Document Link:

Detailed Acceptance Test Plan Page 6 of 10

1.3 Environment and Pretest Background

REFERENCES

Document Link

Master Acceptance Test

Plan

Requirement(s)

Change Request

System Release

Checklist

Sand Box

Traceability Matrix

TEST ENVIRONMENT

Environment Software Type Application Server(s) Database Type Database Server/DB Name

Detailed Acceptance Test Plan Page 7 of 10

TEST DATA USED

Type TCO Non TCO Group Program Tester

Related System URLs and Notes Link:

SOFTWARE DEPENDENCIES

Type Description

TOOLS

Tool File Location

Detailed Acceptance Test Plan Page 8 of 10

TABLES UPDATED

Move Name Description

FILES CREATED / UPDATED / DELETED (S36/AS400)

File Name New/Upd/Del Description

Detailed Acceptance Test Plan Page 9 of 10

2.0 PLAN

2.1 High Level Functional Summary

FUNCTIONAL OUTLINE

Function(s) (requirement change(s), defect(s), and all functional/business categories to be tested) Description

Approximate

Duration

2.2 Out of Scope Details

OUT OF SCOPE

# Description

Detailed Acceptance Test Plan Page 10 of 10

3.0 SIGNATURE and ACCEPTANCE

Review Type Distributed Date Review Confirmed (How and Date)

Accepted by (No response is acceptance)

Initial Test Plan

Peer Review

Major Revision

Final (pre-production)