AMENDMENT 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT_1.pdf | ||
| Allegheny_NF_AOP_Sta_215+65_Design_Package.pdf | ||
| AG-24H8-S-17-0017.pdf | ||
| Allegheny_AOP_Supplemental_Specs_03022017.pdf | ||
| v=3.pdf | ||
| GovtProvidedTechnicalProposalForms.rtf | RTF text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 2: AG-24H8-S-17-0017
FR262 STA 215+65 AOP Culvert Replacement
SOLICITATION: AG-24H8-S-17-0017
The below information and attachments are hereby incorporated into this solicitation:
Q&A:
1. QUESTION: Could you please clarify what all is required to be submitted by the contractors to the USFS on 5/1/2017 @ 1:00pm for consideration on this project? Please provide a complete list of what should be included with the pricing submission.
RESPONSE: This information is included in the solicitation. Reference the solicitation
2. QUESTION: Item# 25101, PennDOT Class 5 Rip Rap. Is there a certain spec for this, or is it PennDOT R-5 Rock?
RESPONSE: PennDOT Class 5 Rip Rap is the same as PennDOT R-5.
3. QUESTION: Item# 553A02 – Are the footings required to be precast, or can they be cast in place?
RESPONSE: The footings shall be precast. Note: “These culverts were designed based on specifications utilizing Big R Bridge culverts. Another culvert supplier can be used subject to changing details per manufactures recommendations.”
4. QUESTION: Temporary Traffic Control – There is a note on sheet 2 of 12 that states contractor is to maintain traffic on the existing road during construction of the culvert. It was my understanding that the road was to be closed during construction of the culvert. Please clarify.
RESPONSE: Section C.6.o: Traffic Control. Contractor shall submit a Traffic Control and Signage Plan for review and approval, 10 days prior to the start of operations.
Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). Traffic control signs shall be placed in areas with adequate turnaround space for a public truck pulling a fifth wheel trailer. Contractor shall not be paid directly for this item, rather it will be considered incidental to the other items of work listed in the Schedule of Items. The existing bridge shall be closed to all public traffic throughout the full duration of work onsite.
Also refer to Section 156 – Public Traffic on page 26 of 76.
5. QUESTION: If the road is to be closed, what are the required road closure signs? Where should they be located? There are no road closure signs specified on the detour plan.
RESPONSE: Section C.6.o: Traffic Control. Contractor shall submit a Traffic Control and Signage Plan for review and approval, 10 days prior to the start of operations.
Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). Traffic control signs shall be placed in areas with adequate turnaround space for a public truck pulling a fifth wheel trailer. Contractor shall not be paid directly for this item, rather it will be considered incidental to the other items of work listed in the Schedule of Items. The existing bridge shall be closed to all public traffic throughout the full duration of work onsite.
Also refer to Section 156 – Public Traffic on page 26 of 76.
6. QUESTION: Dewatering – If I am reading the dewatering requirements right, the plan you have is just a guideline for dewatering. We can make our own dewatering plan and submit it to you? So we could choose to pump around and/or construct an open channel for the water to flow through? We are not required to place a bypass pipe?
RESPONSE: Section C.6.d: Dewatering Plan. Due to the proximity of water, the Contractor shall submit a Dewatering Plan, for the purpose of protecting the abutment foundations. The Contractor is solely responsible for the development and execution of their dewatering plan.
The Contractor’s Dewatering Plan will be reviewed and approved according to the contract documents and protecting the resource.
Also see the “Requirements” notes on Sheet 12 of 12 including “This sheet illustrates the general dewatering requirements and possible methods and equipment, and is not considered adequate or complete for this project”.
7. QUESTION: I do not see an item for the 6” aggregate base course under the asphalt binder pavement. Is this included in an item or incidental to other items of work?
RESPONSE: Bid Item 32401 Crushed Aggregate Base, PennDOT 3/4" minus gradation, Compaction D includes this work.