Allegheny_AOP_Supplemental_Specs_03022017.pdf
PDF 353 KB Posted
- Solicitation number
- AG-24H8-S-17-0017
About this file
Supplemental Specs
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT_2.pdf | ||
| AMENDMENT_1.pdf | ||
| Allegheny_NF_AOP_Sta_215+65_Design_Package.pdf | ||
| AG-24H8-S-17-0017.pdf | ||
| v=3.pdf | ||
| GovtProvidedTechnicalProposalForms.rtf | RTF text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
152 - Construction Survey and Staking
152.04 General
152.05 Survey and Staking Requirements…………………………………………………….17
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations
Table 152-2 Cross section and slope stake tolerances
153 - Contractor Quality Control………………………………………………………………...22
153.07 Project Submittals
155 - Schedules for Construction Contracts
155 Delete
156 - Public Traffic………………………………………………………………………………25
156.03 Accommodating Traffic During Work
156.08 Traffic and Safety Supervisor
157 - Soil Erosion Control
157.02 Materials
157.03 General
157.08 Water Crossings
171 - Weed and Disease Prevention
201 - Clearing and Grubbing
201.02 Material:
201.01 Description
201.04 Clearing. (c)
203 - Removal of Structures and Obstructions
203.01 Description
203.04 Removing Material
203.05 Disposing of Material
204 - Excavation and Embankment
204.05 Conserved Topsoil
204.06 Roadway Excavation
204.09 Preparing Foundation for Embankment Construction
204.10 Embankment Construction
204.11 Compaction
204.13 Sloping, Shaping, and Finishing
204.13 Sloping, Shaping, and Finishing
Table 204-2 Construction tolerances
204.14 Disposal of Unsuitable or Excess Material
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements
208 - Structure Excavation and Backfill for Selected Major Structures
208.03 General
208.08 Foundation Preparation
208.12 Measurement
251 - Riprap
251.03 General
324 - Minor Aggregate, Commercial Source
552 - Structural Concrete
552.02 Material
552.03 Composition (Concrete Mix Design)
Table 552-1 Composition of Concrete………………………………………………………...45
Table 552-2 Minimum Air Content for Air Entrained Concrete
Table 552-3a Required Average Compressive Strength
552.08 Delivery
552.09 Quality Control of Mix
552.11 Handling and Placing Concrete
552.12 Construction Joints
552.18 Loads on New Concrete Structures
Table 552-3b Required Average Compressive Strength
553A - Precast Concrete Structures
554 - Reinforcing Steel
603 - Structural Plate Structures
603.03 General
603.04 Erecting
617 - Guiderail
625 - Turf Establishment
625.03 General
625.04 Preparing Seedbed
625.05 Watering
625.06 Fertilizing
625.07 Seeding
629 - Rolled Erosion Control Products and Cellular Confinement Systems…………………….58
629.03 General
648 - Stream Simulation
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
704 - Soil
704.02 Bedding Material
704.02 Bedding Material
705 - Rock
705.02 Riprap Rock
705.07 Streambed Simulation Rock
705.08 Channel Rock
709 - Reinforcing Steel and Wire Rope
714 - Geotextile and Geocomposite Drain Material
Tables 714-1 and 714-4
714.03 Geogrids
Table 714-7—Physical strength requirements for geogrids
725 - Miscellaneous Material
725.40 High Strength NonShrink Grout
725.41 Mortar
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
http://www.nist.gov/
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Stream Course--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Modify the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
152 - Construction Survey and Staking
152.00_nat_us_08_05_2005
Description
152.04(c) Material.
Add the following:
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
Construction Requirements
152.04 General.
Delete the fifth and sixth paragraphs (after 152.04(c) Material Section).
Add the following:
When indicated on the plans, a preliminary survey line has been established on the ground. The project location line is established by offsets from this preliminary line.
Delete second sentence in eleventh paragraph and replace with the following:
Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations
152.05 Survey and Staking Requirements.
(b) Centerline establishment.
Add the following:
Take roadway cross-sections normal to centerline. When the centerline curve radius is less than or equal to 200 feet, take cross-sections at a maximum centerline spacing of 25 feet. When the centerline curve radius is greater than 200 feet, take cross-sections at a maximum centerline spacing of 80 feet.
Reestablish centerline from instrument control points. The maximum spacing between centerline points is 25 feet when the centerline curve radius is less than or equal to 200 feet. When the centerline curve radius is greater than 200 feet, the maximum distance between centerline points is 80 feet.
c) Slope Stakes & References:
Replace section with the following:
Slope stakes and references. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
• Method I—Computed Method. Use the template information shown in the plans or other Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
• Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other Government-provided data.
(e) Clearing and grubbing limits.
Add the following:
Establish clearing limits on each side of the location line by measuring the required horizontal or slope distances shown in the stake notes. Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.
After establishing clearing limits, move the location line stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line
(g) Culverts.
Replace subsection with the following:
Set culvert reference stakes at all culvert locations. Set a culvert reference stake on the centerline of the culvert 10 feet from each end or beyond the clearing limit, whichever is greater. Record the following on culvert reference stakes:
(1) Diameter, actual field measured length, and type of culvert.
(2) The vertical and horizontal distance from the reference stake to the invert at the ends of the culvert.
(3) Station of actual point where culvert intersects centerline.
When required, stake headwall for culverts by setting a hub with a guard stake on each side of the culvert on line with the face of the headwall. Perform this work after clearing is completed.
152.05 (l) Miscellaneous Survey and Staking.
Add the following to the first sentence:
Cattleguards
Drain Dips
Erosion Control Measures
Replace Table 152-1 with the following two tables:
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.
Precision Class
Minimum Position Closure Angular Accuracy (±)
L-Line Tangent Control Pointsa
Vertical Closureb
A
(Bridges) 1/10,000
2 sets, direct/reverse
10 second rejection limit
N/A
0.02 ft or
0.02ft/1000ftc
B 1/5,000
2 sets, direct/reverse
20 second rejection limit
0.1 ft
0.02 ft or
0.02ft/1000ftc
C 1/1,000 1 set, direct/reverse
1 minute rejection limit
0.2 ft 0.5ft/1000ftc
D 1/300 Foresight and backsight; 15 minute rejection limitc
0.4 ft 1.0ft/1000ftc
E 1/100 Foresight and backsight; 30 minute rejection limitc
0.8 ft 1.0ft/1000ftc
Precision
Class
Minimum Position Closure Angular Accuracy (±)
L-Line Tangent Control Pointsa
Vertical Closureb
a. Accuracy of offset measurement.
b. Determine vertical closures at intervals not to exceed 2000 ft as measured along centerline.
c. Use greater value.
Table 152-2 Cross section and slope stake tolerances.
Item Tolerances
A B C D E
Allowable deviation of cross-section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves
(±)2o (±)3o (±)3o (±)5o (±)5o
Take cross-sections topography measurements so that variations in ground from a straight line connecting the cross-section points will not exceed
0.5 ft 1.0 ft 2.0 ft 2.0 ft 3.0 ft
Horizontal and vertical accuracy for cross-sections, in feet or percentage of horizontal distance measured from traverse line, whichever is greater.
0.1 ft or 0.4%
0.15 ft or 0.6%
0.2 ft or 1.0%
0.2 ft or 1.0%
0.3 ft or 1.0%
Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured from centerline or reference stake, whichever is greater.
Slope reference stakes and slope stakes. 0.1 ft or 0.4%
0.15 ft or 0.6%
0.2 ft or 1.0%
0.2 ft or 1.0%
0.3 ft or 1.0%
Clearing limits 1.0 ft 1.0 ft 1.0 ft 1.5 ft 2.5 ft
153 – Contractor Quality Control
Add the following.
153.07. Project Submittals
At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.
Submittal Log
Log No.
Incidental to Pay Item(s) Description of Submittal
Type of Submittal
Specification No. / Drawings
1 C Safety Plan Plan Section C.6 (g)
2 151 Weed Free Material Source Certification
Material Certification FSSS 105.02(b)
3 151 Hazardous Spill Plan Plan FSSS 107.10 4 151 Contractor Quality Control Plan Plan 153.02 5 156 Traffic Control Plan Plan FSSS 156.03
6 157 Dewatering and Soil Erosion and Sediment Control Plan Plan FSSS 157.03
7 204 Material Moisture/Density Testing Test Results Table 204-1
8 204 Structural Backfill Compaction Testing Test Results 204.11
9 208 Excavation Plan Plan FSSS 208.04
10 208 Material Moisture/Density Testing Test Results Table 208-1
11 208 Structural Backfill Compaction Testing Test Results 208.11, 208.12
12 251 Riprap Material
Certification 251.07
13 324
Crushed Aggregate Gradation:
Road Base and Limestone Surfacing
Material Certification 324.03
14 552 Structural Concrete: Mix Design Mix Design 552.03 15 552 Structural Concrete: Testing Test Results 552.19
16 553A Miscellaneous Material: Grout Material
Certification FSS 725.40
17 553A Miscellaneous Material: Grout Product
Approval FSS 725.40
18 553A Welder Certification Copy of
Certification General Notes Sheet
19 553A Precast Concrete Structures Fabrication Certification FSSS 553.02
20 553A Precast Concrete Structures Shop
Drawings FSSS 553.03
21 553A Precast Concrete Structures:
Testing Test Results FSSS 553.06
22 553A Reinforcing Steel Order List 554.03
23 603 Structural Plate Structures Assembly
Instructions 603.04
24 603 Structural Plate Structures Material
Certification 603.04
25 617 Guide Rail Product
Approval 617
26 625 Seed Mix Material
Certification FSSS 622.02
27 648 Streambed Simulation, Rock Weirs, & Channel Rock
Certification 648.03
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.03 Accommodating Traffic During Work.
Delete the first paragraph and replace with the following:
Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635.
Submit a traffic control plan for acceptance at least 14 days before intended use.
Add the following project specific requirements:
The Contractor will be allowed to close both lanes of Forest Road 262 in the immediate vicinity of the project site to public traffic during the culvert replacement construction work, as specified in the project drawings. Provide detour signage, and road closure barricades, and maintain signage throughout the course of work on the project site.
Develop a construction sign plan identifying the type and location of all advanced warning signs necessary to safely restrict or pass public traffic. The traffic control plan must include provisions to safely accommodate and guide public traffic on the detour road at all hours of the day. Install construction signs conforming to the Manual on Uniform Traffic Control Devices (MUTCD) prior to proceeding with any construction work. Furnish, maintain and remove all barricades and signs required for construction signing.
It is the responsibility of the Contractor to schedule delivery of materials, equipment and all necessary supplies to the site, to ensure that the culvert can be substantially completed within the specified contract time.
The Contractor shall be responsible for providing, installing, maintaining, and removal of warning signs and barricades required for the road closure period in accordance with MUTCD as submitted and approved in the traffic control plan.
Delete the following from the last sentence of the last paragraph:
according to Subsection 106.07(b)
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety
157 - Soil Erosion Control
157.02 Materials
Add the following:
Provide bales, wattles, logs and rolls from a certified noxious weed free source.
157.03 General.
Delete the first two paragraphs and replace with the following:
Submit a Dewatering and Soil Erosion and Sediment Control Plan detailing permanent and temporary control measures to minimize erosion and sedimentation during and after construction in accordance with the plans and storm water permits. Do not modify the type, size, or location of any control or practice without approval. Submit the erosion control plan proposal at least 7 days before operations begin to the CO for approval.
Reflect in the Dewatering and Soil Erosion and Sediment Control Plan special concerns and measures necessary to protect resources and government improvements. Include:
(a) The construction activities and sequence of implementation relating to specific erosion control measures.
(b) The location and type of permanent controls to be implemented during construction.
(c) The location and type of temporary controls to be implemented during construction.
(d) For work in stream channels with running water, a detailed dewatering plan.
(e) For work in stream channels without flowing water describe level of ground and vegetative disturbance and measures to reduce potential sediment delivery.
(f) Description of the monitoring plan.
Add the following to the third paragraph:
Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.
157.08 Water Crossings.
Add the following:
At any channel crossing where there is running water, dewater by rerouting water flow around the site before and during excavation and embankment operations.
171 - Weed and Disease Prevention
171.00_nat_us_03_30_2005
Description
171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment for inspection by the Government, before the equipment is used on National Forest System lands.
171.02 Conform to the following Subsection:
Water 725.01 (c)
171.03 General . Notify the CO in writing at least 15 Days, to schedule an inspection, before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Perform all work at a location designated on the plans or other locations approved in writing.
Provide the CO with an opportunity to monitor the washing and inspection.
171.04 Equipment. Use a high pressure washing system.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment.
Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.
Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
Measurement
171.08 Do not measure weed prevention for payment.
Payment
171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for Section 151-Mobilization.
201 - Clearing and Grubbing
201.00_nat_us_08_05_2009
201.02 Material:
Delete Tree wound dressing material reference.
201.03 General.
Delete the last sentence.
201.04 Clearing.
Delete the last sentence of (d).
01.01_nat_us_02_18_2005
201.01 Description
Replace with the following
This work consists of clearing and grubbing within clearing limits and other designated areas.
201.04_nat_us_02_22_2005
201.04 Clearing. (c)
Delete paragraph (c) and replace with the following:
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. For timber sales, stump heights will meet the requirements of the Timber Sale contract.
201.04 Clearing.
Delete subsection (d) and replace with the following:
(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter, that is within the clearing limits but beyond the roadway and not in a decking area, and that does not interfere with sight distance along the road.
(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.
(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
203 - Removal of Structures and Obstructions
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fifth and sixth paragraphs with the following:
Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation.
Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
203.05_nat_us_02_18_2005
203.05 Disposing of Material.
Add the following:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees.
Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
203.08_nat_us_02_24_2005
203.08 Payment
Add the following:
Disposal of construction slash will be compensated under the designated pay item in Section 201.
204 - Excavation and Embankment
204.05_nat_us_02_18_2005
204.05 Conserved Topsoil
Delete the entire paragraph.
204.06_nat_us_03_02_2005
204.06 Roadway Excavation
Add the following:
Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.
204.09_nat_us_03_02_2005
204.09 Preparing Foundation for Embankment Construction.
Delete subsection (a) and replace it with the following:
(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying.
Compact the ground surface according to Subsection 204.11.
204.10_nat_us_03_02_2005
204.10 Embankment Construction.
Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.
(a) General.
Delete the third paragraph and add the following:
Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.
204.11_nat_us_04_11_2005
204.11 Compaction.
Delete the first paragraph and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d) or (e) no sieve test is required.
Add the following compaction methods:
(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
(e) Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
(a) Sloping.
Add the following:
Slope rounding is not required on tolerance class D though M roads.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until visible displacement ceases.
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
Add Table 204-2—Construction Tolerances:
Table 204-2 Construction tolerances.
Tolerance Class(a)
A B C D E F G H I J K L M Roadbed width (ft)
+0.
+0.
+1.
+1.
+1.
+1.
+1.
+1.
+2.
+2.
+2.
+2.
+2.
Subgrade elevation
(ft)
+0.
+0.
+0.
+0.
+0.
+1.
+1.
+1.
+2.
+3.
+2.
+3.
(c)
Centerline alignment (ft)
+0.
+0.
+0.
+0.
+1.
+1.
`+1.
+1.
+2.
+3.
+3.
+5.
(c)
Slopes, excavation, and embankment (% slope(b)
+3 +5 +5 +5 +5 +5 +10 +10 +10 +10 +20 +20 +20
a. Maximum allowable deviation from construction stakes and drawings.
b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
204.15_nat_us_02_07_2007
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements.
Add the following note to the table:
(3) When compaction methods (d) or (e) are used AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.
208 - Structure Excavation and Backfill for Selected Major Structures
208.04_nat_us_08_05_2009
Construction Requirements
208.03 General.
Add the following to the end of the second sentence of the first paragraph:
"... to the CO a minimum of 5 days prior to beginning excavation work."
Add the following to the end of the third sentence of the first paragraph:
"...to the CO a minimum of 15 days prior to installation."
208.08 Foundation Preparation.
Add the following after the first paragraph:
The foundation elevation is defined as the bottom of footings, for spread footing placement; the bottom of the pile cap, for construction of pile foundations; and the toe of the wall, for construction of retaining walls, except wingwalls at bridges.
Replace all material from any over-excavation below the designated footing elevation with concrete, compacted gravel, or foundation fill at the direction of the CO.
When boulders or irregular, fractured, or seamed bedrock precludes excavation to the designated footing elevation without further loosening of previously solid material, the CO may order removal of such loose material and allow payment for concrete, gravel, or structural backfill that is required to restore foundation material to the designated elevation
208.12 Measurement.
Add the following to the second paragraph:
(g) Material excavated to construct end walls or wing walls which lie outside the excavation limits specified above.
Add the following paragraph:
Foundation over-excavation and the resulting replacement material will not be measured for payment unless the CO determines the over-excavation was unavoidable because of the nature of the material.
251 - Riprap
251.03_nat_us_08_05_2009
251.03 General.
Place riprap under or adjacent to structures before placing prefabricated superstructure units or constructing superstructure falsework unless otherwise approved by the CO.
251.08 Measurement.
Payment for excavation and embankment required for placement of riprap is indirectly included in the pay item for riprap.
324 - Minor Aggregate, Commercial Source
324.00_nat_us_08_28_2008
324.01 This work consists of constructing one or more courses of aggregate on a prepared surface.
Work includes producing aggregate by crushing methods.
324.02 Conform to the following Subsections:
Aggregate 703.06 Water 725.01
324.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.
Request approval of the roadbed in writing before placing aggregate.
Develop, haul, and apply water in accordance to Section 170.
Develop, haul, and apply water in accordance to Section 170.
Submit state approved aggregate gradations for review and approval by the CO.
After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at approved locations.
324.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness. Place the mixture in a maximum compacted layer thickness of 6 inches.
When more than one layer is necessary, compact each layer according to Subsection 324.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
324.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
324.06 Construction Tolerance. If grade finishing stakes are required, finish the surface to within ±0.10 feet from staked line and grade elevation.
If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot straightedge. Defective areas are surface deviations in excess of 1/2 inch in 10 feet between any two contacts of the straightedge with the surface.
Correct all defective areas by loosening the material, adding or removing material, reshaping, and compacting.
Ensure that the compacted thickness is not consistently above or below the specified thickness.
The maximum variation from the compacted specified thickness is ½ inch.
Ensure that the compacted width is not consistently above the specified width. The maximum variation from the specified width will not exceed +12 inches at any point.
324.07 Maintenance. Maintain the aggregate course to the correct line, grade, and cross-section by blading, watering, rolling, or any combination thereof until placement of the next course. Correct all defects according to Subsection 324.06.
324.08 Acceptance. See Table 324-1 for sampling and testing requirements.
Aggregate gradation and surface course plasticity index will be evaluated under Subsection 106.03 and 106.04. Other aggregate quality properties will be evaluated under Subsections 106.02 and
106.03. Placement of aggregate courses will be evaluated under Subsections 106.02 and 106.04.
Preparation of the surface on which the aggregate course is placed will be evaluated under Section 204 or 303 as applicable.
324.09 Measure the Section 324 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
Measure square yard width horizontally to include the top of aggregate width including designed widening. Measure the square yard length horizontally along the centerline of the roadway.
If the measurement for aggregate is by cubic yard using contract quantities then measure aggregate by the cubic yard in-place once compacted, otherwise measurement for aggregate by the cubic yard is measured by the cubic yard in the hauling vehicle.
Measure thickness perpendicular to the grade of the travel-way.
Measure width perpendicular to the centerline.
324.10 The accepted quantities will be paid at the contract price per unit of measurement for the Section 324 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
T ab le
-1
Sa m pl in g an d
T es tin g
R eq ui re m en ts
R ep or tin g T im e
B ef or e us in g in w or k h ou rs
Sp lit pl e
Y es
, w he n re qu es te d
“ “ “ Y es
Po in t o f
Sa m pl in g
So ur ce o f m at er ia l
Fr om w in dr ow o r ro ad be d af te r pr oc es si ng o r fro m a pp ro ve d cr us he r s am pl in g de vi ce pl in g Fr eq ue nc y pe r t yp e so ur ce o f m at er ia l pe r d ay t M et ho ds ec ifi ca tio ns
A
SH
TO
T
A A
SH
TO
T
SH
TO
T
ST
M D
A A
SH
TO
C at eg or y ha ra ct er is tic
LA
a br as io n
(c oa rs e)
So di um su lfa te so un dn es s l os s
(c oa rs e fi ne
D ur ab ili ty in de x
(c oa rs e fi ne
Fr ac tu re d fa ce s
Sa m pl e
T yp of cc ep ta nc e (S ub se ct io n)
M ea su re d an d te st ed fo r c on fo rm an
(1
.0
M ea su re d an d te on fo rm
.0
4) er ia l o r
Pr od uc t
A gg re ga te so ur ce q ua lit y
3.
Su bb as e, B as e, a nd S ur fa co se s ab le
-1
(c on tin ue d) pl in g an d T es tin g R eq ui re m en ts
R ep or tin g T im e
B ef or e us in g w or k
B ef or e pl ac in g ne xt la ye r
(1
M in im um o f 5 p oi nt s p er p ro ct lit pl e
Y es
, w he n re qu es te d
Po t o f
Sa m pl in g
So ur ce o f m at er ia l
In -p la pl in g Fr eq ue nc y pe r t yp e an d so ur ce o f m at er ia l pe r da y
T es t M et ho ds ec ifi ca tio
SH
TO
T
(1
R -1
M ar sh al l
A A
SH
TO
0(1
R -1
M ar sh al l
A A
SH
TO
T o th er a pp ro ve d pr oc ed eg or y ha ra ct er is tic oi st ur e-de ity et ho
D oi st ur e-de ho d E
M oi st ur e-de ho d F
M oi st ur e-de ho
G
In -p la ce d en si ty oi st ur e co nt en t
T yp of cc ep ta nc e (S ub se ct io n) ea su re d an d te on fo rm
.0
4) er ia l o r
Pr od uc t
Su bb as e, B as e, a nd S ur fa
552 - Structural Concrete
552.02_nat_us_06_20_2007
Material
552.02 Add the following:
Anchor bolts 717.01 Dowels 717.17 Epoxy resin adhesives 725.21 High strength non-shrink grout 701.02 Mortar 701.02 Portland cement 701.01 Sealants, fillers, seal, and sleeves 712.01
552.03 Composition (Concrete Mix Design).
Delete Tables 552-1, 2, and 3 and replace with the following:
Table 552-1 Composition of Concrete
Class of Concrete
Minimum Cement Content
(pound per cubic yard)
Maximum W/C Ratio
Slump (1) (inches)
Maximum Nominal Coarse
Aggregate Size (5)
(inches) A 611 0.49 2 to 4 1½
A(AE) 611 0.44 1 to 4 1½ B 517 0.58 2 to 4 2½
B(AE) 517 0.58 2 to 4 2½ C 658 0.49 2 to 4 ¾
C(AE) 658 0.44 1 to 3 ¾ D(AE)(2) 611 0.40 1 to 3 1½ E(AE)(3) 611 0.40 4 to 6 (4) ¾
P (Prestressed) 658 0.44 0 to 4 1
P(AE) 658 0.44 0 to 4 1 Seal 658 0.54 4 to 8 1½
(1) Maximum slump is 8 inches if approved mix design includes a high-range water reducer.
(2) Concrete with a water reducing and retarding admixture conforming to AASHTO M 194, type D.
(3) A latex modified concrete with 0.037 gallons of modifier per pound of cement.
(4) Measure the slump 4 to 5 minutes after the concrete is discharged from the mixer.
(5) Meeting the processing requirements of AASHTO M43, Table 1 – Standard Sizes of Processed Aggregate.
(6) Use Class P (AE) concrete in the entire depth of the top flange of all multi-beam bridge girders. In lieu of this, Class P (AE) concrete may be used for fabrication of the entire girder, and throughout the entire depth of prestressed slabs. In all cases, furnish concrete meeting the 28 day specified minimum concrete strength requirements for the prestressed members as shown on the plans, unless otherwise specified.
Table 552-2 Minimum Air Content for Air Entrained Concrete
Nominal Maximum Aggregate Size (1)
As Delivered Minimum Air
Content (2) (3) (%) 2½ inch 3.5 2 inch 3.5
1½ inch 4.0 1 inch 4.5 ¾ inch 4.5 ½ inch 5.5
(1) Meeting the processing requirements of AASHTO M 43, Table 1 – Standard Sizes of Processed Aggregate.
(2) These air contents apply to the total mix. When testing these concretes, aggregates larger than 1½ inches are removed by handpicking or sieving, and air content is determined on the minus 1½-inch fraction of the mix. Air content of the total mix is computed from the value determined on the minus 1½-inch fraction.
(3) For P(AE) concrete, the as delivered minimum air contents may be reduced 1.0 % and the maximum air content is 6.0 %
Table 552-3a
Required Average Compressive Strength (1)
Specified Compressive Strength (f’c)
(psi)
Required Average Compressive Strength
(f’cr) (psi)
Less than 3000 f’c + 1000 3000 to 5000 f’c + 1200
Over 5000 1.10f’c + 700
(1) Use this table when there is not enough data available to establish a standard deviation
Delete the first paragraph after Table 552-2 and replace with the following:
Submit written concrete mix designs for approval at least 30 calendar days before production.
Add the following under the list of items to be included in the mix design submittal:
(y) Evaluation of potential aggregate reactivity
552.08 Delivery.
(a) Truck mixer/agitator.
Do not exceed 130 total revolutions at mixing speed, including both initial mixing and remixing. Do not exceed 300 total revolutions, including both mixing and agitating speed.
552.09 Quality Control of Mix.
Add the following after the first paragraph:
At least 2 weeks prior to the start of concrete placement operations, arrange a pre-concrete placement conference. Coordinate attendance with the CO and any applicable subcontractors.