AG-24H8-S-17-0017.pdf

PDF 426 KB Posted

Attached to
FR262 STA 215 +65 AOP Culvert Replacement, Allegheny National Forest
Solicitation number
AG-24H8-S-17-0017
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
AMENDMENT_2.pdf PDF
AMENDMENT_1.pdf PDF
Allegheny_NF_AOP_Sta_215+65_Design_Package.pdf PDF
Allegheny_AOP_Supplemental_Specs_03022017.pdf PDF
v=3.pdf PDF
GovtProvidedTechnicalProposalForms.rtf RTF text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

AG-24H8-S-17-0017

North East Acquisition Team 4 Farm Colony Drive Warren PA 16365

The Allegheny National Forest (ANF) intends to award a single contract for this work located within the Forest in McKean County.

The project includes the replacement of two culverts on Longhouse Scenic Drive—a two lane paved highway. Work activities include, but are not limited to: installation of detour and traffic signs, erosion and sedimentation control, control surveys, removal of existing asphalt paving, excavation and trenching, dewatering, removal and replacement of two culverts, installation of AOP stream simulation rock, construction of off road bicycle trail, backfill, asphalt paving and highway line striping. Contractor shall provide all necessary heavy equipment, manpower, transportation and operating supplies and other incidentals to accomplish this work.

The work is located within the ANF in the State of Pennsylvania. Work is expected to start on or about 5 July 2017.

This procurement is set-aside 100% for small business concerns. The NAICS code is 237310 and the Small Business size standard is $36.5 million.

The Magnitude of Construction is: Between $250,000 and $500,000

QUESTIONS SHALL BE SUBMITTED IN WRITING TO THE CONTRACTING OFFICER IDENTIFIED IN BLOCK 9.

Same as Block 7: ATTN Ashley Witmer

Ashley Witmer 814-728-6258 email: ashleyawitmer@fs.fed.us

103/30/2017

05/01/2017

1:00 PM

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

AG-24H8-S-17-0017

FR 262 STA 215+65 AOP Culvert Replacement

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

FR262 STA 215+65 AOP Culvert Replacement

Allegheny National Forest Bradford Ranger District

Warren County

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

PRICE

TOTAL

15101 Mobilization Lump Sum 1

15201 Construction survey and staking, method I, tolerance A Lump Sum 1

15713 Soil Erosion Control, Straw Wattles (“Filter Socks”)

Linear Foot 600

15730 Dewatering and Soil Erosion & Pollution Control Lump Sum 1

20102 Clearing and grubbing Lump Sum 1

20301 Removal of Existing Culverts Each 2

20411 Embankment Construction (Bicycle Trail), Compaction Method D Cubic Yard 290

20416 Waste, Disposal of Unsuitable Material Cubic Yard 450

20801 Structural Excavation Cubic Yard 1,818

20803 Structural Backfill Cubic Yard 1,366

25101 Placed Riprap, Penn DOT Class 5, Machine Placed

Cubic Yards 210

32401 Crushed Aggregate Base, PennDOT 3/4" minus gradation, Compaction D Tons 90

32405 Crushed Aggregate Surfacing, DSA - Limestone Tons 45

40330 Hot-mix Asphalt Concrete Pavement, PennDOT Plant Mix Bituminous, 3-1/2” Thick Binder Course, FB-1

Tons 140

40331 Hot-mix Asphalt Concrete Pavement, PennDOT Plant Mix Bituminous, 1-1/2” Thick Wearing Course, FB-1

Tons 60

553A02 Precast Reinforced Concrete Footings Linear Feet 226

60203 57” span, 38” rise, Aluminized Steel, Type 2, Corrugated Steel Pipe Arch, 10 Gauge, 0.138 inch thickness

Feet 114

60304 14’-0” span, 4’-8” rise, Galvanized Steel Structural Plate Single Radius Arch, 8 Gauge,

0.170 inch thickness

Feet 112

ITEM

NO.

DESCRIPTION

PAY

EST.

QTY.

TOTAL

61710 Guard Rail System, Install new guiderail Linear Feet 600

62503 Seeding, Dry Method Lump Sum 1

62904 Erosion Control Mats, Type 3B, Biodegradable Lump Sum 1

63401 Pavement Markings, Double Solid, Yellow Centerline, Reflectorized

Feet 300

64804 Placed streambed simulation rock, Class 10 design mix, placement method A Tons 180

64869 Placed streambed channel rock, bed class R-7, placement method A; including rock weirs & rock clusters

Tons 110

65005 Temporary Traffic Control Lump Sum 1

Total:

B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.

Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.

Contractor Acceptance Statement: By signing the offer, the Contractor agrees to all terms, conditions, and provisions included in the solicitation and agrees to furnish any awarded items at the price set in the schedule unless otherwise excepted as follows:

Contractor Notes:

1. Contractor must be registered in www.sam.gov in order to submit an offer on this project.

THIS IS A FREE REGISTRATION.

2. There is a pre-bid meeting at the site on 04/03/2017 at 10:00 am EST. Directions to site:

State of Pennsylvania, County of Warren, Allegheny National Forest, Bradford Ranger District; Latitude:

41°48'10.02"N, Longitude 78°55'24.35"W.

The FR 262 Station 215+65 culvert replacement project is located on FR 262 approximately 4 miles from SR 321 near Red Bridge.

Directions to the project site, from the city of Kane, PA: Proceed north on SR 321 approximately 10 miles to FR 262. Turn left onto FR 262. Project site is approximately 4 miles from SR 321. From Warren, PA:

proceed easterly on SR 59 for approximately 12 miles. Turn right onto FR 262. Proceed approximately 7 miles to project site.

3. This is a construction project which has the following bonding requirements:

20% bid bond for offers over $150,000 required with offer submission. 100% performance and payment bonds for offers over $150,000 upon award. See Section I for details.

4. Award will be made to one contractor. You must submit pricing for all items to be considered.

http://www.sam.gov/

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 DESCRIPTION OF WORK

Furnish all labor, equipment, and materials, to accomplish the Work under this contract.

Services consist clearing and grubbing, furnishing and installing one (1) single radius structural plate arch on reinforced concrete footings, one (1) corrugated metal squash arch culvert at a separate tributary, placing streambed simulation materials, removing and disposing of the existing culverts, installation of guide railing, construction of asphalt and aggregate surfaced roadways and trails, structural excavation and backfill, and signage.

The Contractor shall refer to the Schedule of Items, Project Area Map, and referenced Specifications when making estimates for quantities of work.

C.2 PROJECT LOCATION

State of Pennsylvania, County of Warren, Allegheny National Forest, Bradford Ranger District;

Latitude: 41°48'10.02"N, Longitude 78°55'24.35"W.

The FR 262 Station 215+65 culvert replacement project is located on FR 262 approximately 4 miles from SR 321 near Red Bridge.

Directions to the project site, from the city of Kane, PA: Proceed north on SR 321 approximately 10 miles to FR 262. Turn left onto FR 262. Project site is approximately 4 miles from SR 321.

From Warren, PA: proceed easterly on SR 59 for approximately 12 miles. Turn right onto FR

262. Proceed approximately 7 miles to project site.

C.3 CONTRACT TIME

The contract time shall be 180 days. Contract time includes delays for weather, locating and transporting supplies and materials, and final site cleanup.

C.4 PROJECT SITE CLEAN UP

Project site cleanup includes the removal and proper disposal of all project trash, demolition debris, and residue off National Forest Land. Proper waste disposal sites shall be any local commercial landfill.

All spills of petroleum products including leak spots from parked vehicles shall be removed and properly disposed according to all Local, State, and Federal rules, regulations, and laws governing such disposal. Any Fuel Trucks staged on-site must be equipped with spill containment kits and portable berms that meet all state and federal regulations. A Spill Containment Plan must be submitted and approved prior to the start of work. If any fuel or oil are to be stored onsite (regardless of the amount), the Contractor shall prepare, and submit for review and approval, then later for implementation a Spill Prevention and Countermeasures Plan.

The (SPCC) Plan shall meet applicable EPA requirements (40 CFR 112), including required certification by a Registered Professional Engineer. Contractor is responsible for all clean-up costs of petroleum product spills within the project vicinity area caused directly or indirectly by their employees or from their contract operations.

C.5 RESERVED

C.6 SPECIAL CONDITIONS AFFECTING THE WORK

a. Physical Conditions. The indications of physical conditions on the drawings and in the specifications are the result of site investigations and surveys performed by the Government.

b. Existing Structures. The existing culverts are corrugated metal pipes.

c. Excavation Plan. Due to the proximity and/or limitations of existing structures, and the limited work space, the Contractor shall submit a comprehensive excavation plan that outlines the proposed methodology for excavating down to the required depth, and any proposed shoring to protect workers. The Contractor is solely responsible for the development and execution of their Bridge Excavation Plan.

d. Dewatering Plan. Due to the proximity of water, the Contractor shall submit a Dewatering Plan, for the purpose of protecting the abutment foundations. The Contractor is solely responsible for the development and execution of their dewatering plan.

e. Weather. Low temperatures at the project site range from less than 20 ºF from December to February to lows of 50 ºF in June and August. High temperatures range from 30 ºF from December to February, to around 80 ºF in July and August. The annual precipitation at the project site is less than 50 inches per year, including snowfall. Winter snow storms and freezing temperatures will occur during the winter months and will cause the project to be shutdown. Icy conditions on local roads and highways can occur during the fall, winter and spring. Highway curves in shaded areas will remain covered with ice or frost for weeks.

f. Typical Work Hours, Weekends and Holiday Hours. Holiday restrictions from June 30th to July 5th, 2017; and September 1st to September 5th, 2017.

g. Safety, Emergency Communications and Evacuation. Contractor is responsible for the safety of the Contractor’s employees including Subcontractors employees, Government employees associated with the project, and any visitors to the site both Government and private. The Contractor shall submit a Project Safety Plan to the Contracting Officer for review prior to commencement of Work. The project safety plan shall comply with the appropriate Pennsylvania OSHA and Federal OSHA rules and regulations and must include a medical evacuation and emergency communications plan.

h. Staging Areas. The contractor shall provide the necessary site investigation of the project area and any adjacent areas, and propose staging areas for approval by the Contracting Officer.

i. Highway Permits. Contractor is responsible for securing any overload or over width limit permits required for the transport of materials or equipment to the project site. The Contractor is responsible for conducting a thorough reconnaissance of all routes leading to the site.

j. Fuel Storage. The contractor shall propose fuel storage areas for approval by the Contracting Officer. The fuel storage tank shall be set inside a fuel containment basin.

The containment basin shall be large enough to hold 110% of the tanks capacity. Provide spill plan in accordance to the specifications for review and approval by the Contracting Officer.

k. Toilets. No toilet or shower facilities are available on site. Contractor shall provide portable toilet facilities for its employees.

l. Camping. Contractor may request a permit from Bradford Ranger District.

m. Water. Non-potable water for the project construction can be drafted directly out of the unnamed tributaries of the Kinzua Creek (at the project site). Use appropriate procedures to prevent sediment and other debris from entering the creek.

n. Security. Contractor is responsible for the Contractor’s equipment and materials owned or supplied to the site. Lost, damaged, or stolen equipment or materials shall be replaced at the contractor’s expense. All equipment not equipped with a key lock system shall be secured in such a manner as to make it inoperable to the average person at the end of each working day. All hand tools and other equipment shall be secured at the end of each working day. The contractor shall be responsible for signing, limiting public access, and safety of the public and/or government employees at the site. All refuse shall be properly stored or removed from the site at the end of each day.

o. Traffic Control. Contractor shall submit a Traffic Control and Signage Plan for review and approval, 10 days prior to the start of operations. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD).

Traffic control signs shall be placed in areas with adequate turnaround space for a public truck pulling a fifth wheel trailer. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items. The existing bridge shall be closed to all public traffic throughout the full duration of work onsite.

p. Burning Permits. Contractor is subject to all rules and regulations governing the on-site burning of slash and other debris. Contractor shall obtain a burning permit from the jurisdiction having control over burning. The Contractor shall comply with Fire Plan for Construction and Service Contracts included in the Contract.

q. Protection of Resources. Contractor shall thoroughly clean all equipment prior to delivery to the project site, to remove weeds, seeds, mud, grease and oil buildup from all equipment surfaces. Contractor shall schedule an equipment inspection with the COR 36 hours prior to mobilization. Spills of petroleum products and other hazardous substances shall be reported, contained, and removed in accordance with all applicable rules, regulations and laws. Contractor shall submit a project spill response plan at the pre-work meeting for review by the Contracting Officer.

C.7 SITE VISIT CONFERENCE OR TOURS

The pre-proposal conference will be held on April 3rd, 2017, at 10:00 am, at the project site. The Contractor acknowledges that they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

C.8 EQUIPMENT CLEANING & NOXIOUS WEED-FREE CERTIFICATION

Unless the entire project area is already infected with noxious weeds, the contractor shall ensure that prior to moving from one on forest location to another part of the project area all off-road equipment, which last operated in areas known by Forest Service to be infected with noxious weeds, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds.

Contractor shall certify in writing to the CO that off-road equipment is free of noxious weeds prior to each start-up of operations and for subsequent moves of equipment to other project areas.

Measures taken to ensure that off-road equipment is free of noxious weeds will be identified.

“Off-road equipment” includes all equipment operating off of paved roadways. A Current list of noxious weeds of concern to Forest Service is available at the Forest Supervisor’s office, and can be obtained by the contractor upon request. Contractor shall clean off-road equipment prior to moving between project areas with known infestations with noxious weeds and other project areas, if any, which are free of such weeds. Contractor shall employ whatever cleaning methods are necessary to ensure that off-road equipment is free of noxious weeds. Equipment shall be considered free of soil, seeds, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools is not required.

The Contractor shall notify Forest Service at least 24 hours prior to beginning of work in area designated as a noxious weed area, unless otherwise approved by CO. Notification shall include the location of the equipment’s most recent operations. If the prior location of the off-road equipment cannot be identified, Forest Service may assume that it was infested with noxious weed seeds. Upon request of Forest Service, Contractor must arrange with CO for Forest Service to inspect each piece of off-road equipment prior to it being placed into service. If

Contractor desires to clean off-road equipment on National forest land, such as at the end of a project or prior to moving to a new unit that is free from noxious weeds, Contractor and Forest Service CO shall agree on methods of cleaning, locations for the cleaning, and control of off-site impacts, if any. New infestations of noxious weeds, of concern to Forest Service and identified by either Contractor or Forest Service, within the project area or on the haul route, shall be promptly reported to the other party.

C.9 BARRICADES, WARNING SIGNS, AND OTHER DEVICES

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform to Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

The Contractor shall furnish, erect, maintain, and remove when notified, four project information signs. Sign details and installation shall conform to the (MUTCD) standards for temporary signs on a rural highway. A sign plan shall be submitted to the CO for approval prior to fabrication or installation of the signs. Specific locations shall be designated by the COR prior to installation.

All signs shall be installed prior to commencing on-site work.

Trenches and other hazards will be signed and flagged in such a way that the public will be aware of the hazard.

C.10 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND

BRIDGES ON FEDERAL HIGHWAY PROJECTS

The Standard Specifications for this project are contained within the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S. Customary Units.

Copies of this document are available on-line only at the Federal Highway Administration web site at https://flh.fhwa.dot.gov/resources/specs/ in either Microsoft Word .doc or Adobe Acrobat .pdf format.

https://flh.fhwa.dot.gov/resources/specs/

Special Project Specifications and Supplemental Project Specifications are included in full text as an attachment in Section J of the contract and amend, supplement, or replace the FP-14 Standard Specifications. All specifications not included in the specification listing, but referenced by listed specifications are applicable.

NOTE: Offerors are cautioned to carefully review these Standard and Supplemental Project

Specifications prior to submission of proposals. All specifications in the “Standard

Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14 U.S.

Customary Units are binding on the parties signing the contract.

C.11 PENNDOT STANDARD SPECIFICATIONS

Certain products reference the State of Pennsylvania Department of Transportation (PennDOT) standard specifications. Copies of this document are available online at the PennDOT website at http://www.dot.state.pa.us/public/PubsForms/Publications/Pub_408/408_2016/408_2016_2/40 8_2016_2.pdf. Refer to the Schedule of Items for a list of products required to comply with PennDOT specifications.

C.12 RESERVED

The Magnitude of Construction is: Between $250,000 and $500,000.

AGAR 452.211-72 Statement Of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

Sustainable Acquisitions http://www.dot.state.pa.us/public/PubsForms/Publications/Pub_408/408_2016/408_2016_2/408_2016_2.pdf http://www.dot.state.pa.us/public/PubsForms/Publications/Pub_408/408_2016/408_2016_2/408_2016_2.pdf

The Contractor shall comply with FAR Part 23 Sustainable Acquisition Policy and all associated laws, rules, regulations, and executive orders referenced therein. Contracts that include the supply of products and for the acquisition of services (including construction) that include the supply of products, require that the products provided are—

(1) Energy-efficient (ENERGY STAR® or Federal Energy Management Program (FEMP)-designated); (applicable if FAR Clause 52.223-15 is included)

(2) Water-efficient; (applicable if FAR Clause 52.223-15 is included)

(3) Biobased; (applicable if FAR Clause 52.223-2 is included)

(4) Environmentally preferable (e.g., EPEAT®-registered, or non-toxic or less toxic alternatives); (applicable if FAR Clause 52.223-13,14, or 16 are included)

(5) Non-ozone depleting; (applicable if FAR clause 52.223-11,12,20, or 21 are included), and/or

(6) Made with recovered materials (EPA-Designated products) (applicable if FAR clause 52.223-9 or 17 is included).

(b) The required products in the contract actions for services include products that are—

(1) Delivered to the Government during performance;

(2) Acquired by the contractor for use in performing services at a Federally-controlled facility; or

(3) Furnished by the contractor for use by the Government.

Sustainable products identified for this solicitation:

The following is a list of sustainable products that that may be used i n t h e performance of this contract. The list is not all inclusive; the Contractor shall research for available products.

C1.1.1 Energy-efficient and Water-efficient Products ENERGY STAR® at http://www.energystar.gov/; and FEMP at http://www1.eere.energy.gov/femp/procurement/eep_requirements.html www.epa.gov/watersense Roofing Products, low flow toilets, faucets, appliances

Biobased Products: (requires reporting at www.sam.gov by 10/31 each year) http://www.biopreferred.gov a Diesel Fuel Additives

(1) Any substance, other than one composed solely of carbon and/or hydrogen, that is intentionally added to diesel fuel (including any added to a motor vehicle's fuel system) and that is not intentionally removed prior to sale or use.

(2) Neat biodiesel, also referred to as B100, when used as an additive. Diesel fuel additive does not mean neat biodiesel when used as a fuel or blended biodiesel fuel (e.g., B20). 90% - Minimum Biobased Content.

b Hydraulic Fluids - Mobile Equipment http://www.energystar.gov/ http://www1.eere.energy.gov/femp/procurement/eep_requirements.html http://www.epa.gov/watersense http://www.sam.gov/ http://www.biopreferred.gov/

Hydraulic fluids formulated for general use in nonstationary equipment, such as tractors, end loaders, or backhoes. 44% - Minimum Biobased Content.

c Penetrating Lubricants Products formulated to provide light lubrication and corrosion resistance in close tolerant internal and external applications including frozen nuts and bolts, power tools, gears, valves, chains, and cables. 68% - Minimum Biobased Content.

d Greases - Truck Lubricants composed of oils thickened to a semisolid or solid consistency using soaps, polymers or other solids, or other thickeners. Lubricants that are designed for use on the fifth wheel of tractor trailer trucks onto which the semi-trailer rests and pivots. 71% - Minimum Biobased Content.

e Gear Lubricants Products, such as greases or oils, that are designed to reduce friction when applied to a toothed machine part (such as a wheel or cylinder) that meshes with another toothed part to transmit motion or to change speed or direction. 58% - Minimum Biobased Content.

f Fuel Conditioners Products formulated to improve the performance and efficiency of engines by providing benefits such as removing accumulated deposits, increasing lubricity, removing moisture, increasing the cetane number, and/or preventing microbial growths within the fuel system. 64% - Minimum Biobased Content.

g Erosion Control Woven or non-woven fiber materials manufactured for use on construction, demolition, or other sites to prevent wind or water erosion of loose earth surfaces, which may be combined with seed and/or fertilizer to promote growth. 77% - Minimum Biobased Content.

h 2-Cycle Engine Oils Lubricants designed for use in 2-cycle engines to provide lubrication, decreased spark plug fouling, reduced deposit formation, and/or reduced engine wear. 34% - Minimum Biobased Content.

C1.1.3 Environmentally Preferable Products:

www.epa.gov/epeat.

None

C1.1.4 Non-ozone Depleting Products:

http://www.epa.gov/snap

None http://www.epa.gov/epeat http://www.epa.gov/snap

C1.1.5 EPA Designated Products:

https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program

Plastic trash bags, printer ribbons, toner cartridges, print & writing papers, Traffic Barricades, Traffic Cones, Engine Coolants, Rebuilt Vehicular Parts, Re-refined lubricating oils, retread tires, manual grade strapping, signage, sorbents.

SAFETY AND HEALTH

2.1.1 SUMMARY

A. References: In addition to publications referenced in the Contract and FAR 52.236-13, the following Code of Federal Regulations (CFR) publications designate and define hazardous materials and conditions, and establish procedures for handling these materials and conditions.

1. 29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards.

2. 29 CFR, Part 1926: OSHA Construction Industry Standards.

3. 40 CFR, Part 61: National Emission Standards for Hazardous Air Pollutants.

4. 40 CFR, Part 261: Environmental Protection Agency (EPA) Characteristics of

Hazardous Waste.

5. 40 CFR, Part 761, EPA Polychlorinated Biphenyls (PCBs), Manufacturing, Processing, Distribution in Commerce and Use Prohibitions.

B. Acquisition of Publications: Referenced CFR publications may be purchased from the

Superintendent of Documents, U.S. Government Printing Office, Washington, D.C. 20402.

2.1.2 SAFETY MEETING

A. Prior to commencing construction, representatives of the Contractor, including the Superintendent, shall meet with the Government to review the Contract's safety and health requirements.

B. The Contractor's safety and health program shall be reviewed, and implementation of safety and health provisions pertinent to the Work shall be discussed.

2.1.3 COMPLIANCE WITH REGULATIONS

A. Contractor Responsibility: The Contractor shall assume full responsibility and liability for compliance with all applicable codes, standards and regulations pertaining to the health and safety of personnel during execution of the Work. The Contractor shall have written safety and health programs in compliance with 29 CFR Parts 1910 and 1926.

2.1.4 SUBMITTALS

https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program

A. Safety and Health Programs: The Contractor shall submit, for approval, copies of the project safety and health programs, as applicable to the work scope, or required as a result of the safety meeting, including but not necessarily limited to the following:

1. Occupational Noise Exposure.

2. Fall Protection.

3. Personnel Protective Equipment.

4. Control of Hazardous Energy.

5. Electrical Safety Related Work Practices.

6. Lead.

7. Respirator Protection.

8. Confined spaces.

9. Heavy Equipment Operation

PART 2 - PRODUCTS

2.2.1 PERSONNEL PROTECTIVE EQUIPMENT

A. Special facilities, devices, equipment and similar items used by the Contractor in execution of the Work shall comply with 29 CFR Part 1910, Subpart I and other applicable regulations.

PART 3 - EXECUTION

2.3.1 EMERGENCY SUSPENSION OF WORK

A. In accordance with FAR 52.236-13, when the Contractor is notified by the Government, of noncompliance with safety or health provisions of the Contract, the Contractor shall immediately, correct the unsafe or unhealthy condition. In accordance with FAR 52.236-13 if the Contractor fails to comply promptly, all or part of the Work will be stopped by Government notice. The Contractor shall not be allowed any extension of time or compensation for damages in connection with a work stoppage for unsafe or unhealthy conditions.

2.3.2 PROTECTION OF PERSONNEL

A. The Contractor shall take all necessary precautions to prevent injury to the public, occupants, or damage to property of others.

2.3.3 ENVIRONMENTAL PROTECTION

A. Dispose of solid, liquid and gaseous contaminants in accordance with local codes, laws, ordinances and regulations.

B. Comply with applicable federal, state and local noise control laws, ordinances and regulations, including but not limited to 29 CFR 1910.95 and 29 CFR 1926.52.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) (APR 1984)

The Contractor shall be required to (a) commence work under this contract within _10__calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than __180 calendar days after NTP. The time stated for completion shall include final cleanup of the premises.

SECTION G--CONTRACT ADMINISTRATION DATA

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

AGAR 452.215-73 Post Award Conference (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within ___14___ days after the date of contract award. The conference will be held at __a location on the Allegheny National Forest. The location will be determined after award.

G.1 DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The contracting Officer will designate a Contracting Officer's Representative (COR) at the time of award.

The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

On all matters that pertain to the contract terms the contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the contracting officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal for a contract claim.

G.2 GOVERNMENT-FURNISHED PROPERTY

RESERVED

G.3 INVOICING

The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). All invoices are to be submitted online via the electronic Invoice Processing Platform. This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm.

Your company must register at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish an account in order to submit an invoice on this project.

G. 4. ORDERING PROCEDURES

RESERVED

G.5 FINAL PAYMENT - RELEASE OF CLAIMS

The Government shall pay the final amount due the Contractor under this contract after—

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed invoice; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.

RELEASE OF CLAIMS

To be submitted with final invoice

Contract Number:

For and in consideration of payment and pursuant to the terms of the contract cited above, the government of the United States, its officers, agents, and employees are hereby released and discharged from all liabilities, demands, obligations, and claims arising under or by virtue of said contract.

Signature: ________________________________

Printed Name: ________________________________

Title: ________________________________

Company: ________________________________

Date: ________________________________

G.6 INCIDENTAL PAYMENT ITEMS

The intent of the contract is to provide for the complete performance of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

G.7 CONTRACTOR CERTIFICATION

Contractor will submit certification with every progress invoice

CONTRACTOR CERTIFICATION

Page of Unit (Region, Forest, District) Project: Contract No.

Name of Contractor: Invoice No. Invoice Date:

I hereby certify, to the best of my knowledge and belief, that--

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) Payments to subcontractors and suppliers have been made, and timely payments will be made for the work activities covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments/credits does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor's performance.

(Name)

(Title)

(Date)

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 EQUIPMENT CLEANING

REFERENCE SECTION C.8

H.2 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

H.3 UTILITY SERVICES

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil/

52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform

Employees of Whistleblower Rights (APR 2014) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(JAN 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY

2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT

2016) 52.204-13 System for Award Management Maintenance (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records -- Negotiation (AUG 2016) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (NOV 2016) 52.219-14 Limitations on Subcontracting (JAN 2017) 52.219-28 Post Award Small Business Program Rerepresentation (JUL 2013) 52.222-3 Convict Labor (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2014) 52.222-6 Construction Wage Rate Requirement (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000

(MAY 2014)

52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC

2010) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2017) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction

Contracts (SEP 2013) 52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (Jan 1997) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air

Conditioners (JUN 2016) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction

Contracts (MAY 2008) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG

2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997)

52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds—Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL

2013) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate I (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (JAN 2017) 52.246-21 Warranty of Construction (MAR 1994)

Alternate I (APR 1984) 52.248-3 Value Engineering – Construction (OCT 2015) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--

Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts

(NOV 1996)

The Contract Price includes the total amount for premiums that the Contractor attributes to the furnishing of performance and payment bonds required by the contract. Reimbursement for bond premiums under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not cover any amount therefor not included in the contract price.

(End of clause)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) Neither the Contractor nor any subcontractor performing under this contract shall use paints containing more then 0.06 of 1 percent lead by weight (calculated as lead metal) in the total nonvolatile content of the paint, or the equivalent measure of lead in the dried film of paint already applied, or both.

(End of clause)

452.236-72 Use of Premises (NOV 1996)

(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.

(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.

(End of clause)

452.236-73 Archeological or Historic Sites (FEB 1988) If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.

(End of clause)

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.

(End of clause)

452.236-76 Samples and Certificates (FEB 1988) When required by the specifications or the Contracting Officer, samples, certificates, and test data shall be submitted after award of the contract, prepaid, in time for proper action by the Contracting Officer or his/her designated representative. Certificates and test data shall be submitted in triplicate to show compliance with materials and construction specified in the contract performance requirements.

Samples shall be submitted in duplicate by the Contractor, except as otherwise specified, to show compliance with the contract requirements. Materials or equipment for which samples, certifications or test data are required shall not be used in the work until approved in writing by the Contracting Officer.

(End of clause)

452.236-77 Emergency Response (NOV 1996)

(a) Contractor's Responsibility for Fire Fighting. (1) The Contractor, under the provisions of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION,…

This is the start of the file's text. The full file is on GovTribe.