C_PROJECT_TO_Safety_Harbor.doc

DOC document 151 KB Posted

Attached to
ROAD, TRAIL, AND FISHERIES CONSTRUCTION, RECONSTRUCTION, AND MAINTENANCE PROJECTS
Solicitation number
AG-05GG-S-08-0021
Issued by

About this file

Task Order C - Safety Harbor Trail Pipeline

View the file

Other files

File Type Posted
A_PROJECT_TO_Tillicum_Mad_River..doc DOC document
B_Drain_Dip.pdf PDF
C_Project_Map.pdf PDF
D_Work_Access_Map.JPG JPG image
A_Drainage_Construction_Details.pdf PDF
D_Drain_Dip.pdf PDF
B_ROAD_STRUCTURE_DETAILS Model —
A_Drain_Dip.pdf PDF
D_Location_and_Area_Map.JPG JPG image
A_Road_Structure_Details.pdf PDF
C_Vicinity_Map.pdf PDF
D_PROJECT_TO_Echo_Trail_Construction.doc DOC document
B_Questionaire.doc DOC document
DBWage_Determination.rtf RTF text file
B_Project_TO_Chiwawa_River.doc DOC document
B_Chiwawa.Work.list.doc DOC document
RFP_AG-05GG-S-08-0021.doc DOC document
DBWage_Determination.rtf RTF text file
C_915_1_Existing_Trail_Restoration.pdf PDF
A_Rd5800_Rd5700_Reconditioning Existing Roadway.doc DOC document
B_Vicinity_Map.pdf PDF
B_Drainage_Construction_Details.pdf PDF
D_954_1_Trail_Obliteration.pdf PDF
D_Work_Site_Map.JPG JPG image
D_Drainage_Construction_Details.pdf PDF
DBWage_Determination.rtf RTF text file
B_Specification_Listing.doc DOC document
RFP_Sample Task Order Form..doc DOC document
RFP_SF24_Bid Bond.pdf PDF
B_851-2_Hazard_Removal_Illustration.pdf PDF
A_851-1_Hazard_Removal_Illustration.pdf PDF
B_801-1_Illustration_of_Road_Structure_Terms.pdf PDF
D_912_1_Typical_Trail_Cross_Sections.pdf PDF
A_801-1_Illustration_of_Road_Structure_Terms.pdf PDF
A_vicinity.map.pdf PDF
A_Specification List.doc DOC document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project C – Safety Harbor Trail Pipeline

INDIVIDUAL PROJECT TASK ORDER

Contract Number
Individual Project Task Order Number

This Individual Project Task Order is issued under contract number:

AG-5GG-C-08-______

AG-05GG-D-08-_____

ISSUING OFFICE: (Forest Service Unit Name)
Task Order Date

Okanogan - Wenatchee National Forest

Acquisition Section, 215 Melody Lane Wenatchee, WA. 98801

Financial obligations and payments shall be processed via the Issuing Office.

PROJECT:

PROJECT NAME: PROJECT C - Safety Harbor Trail Pipeline Chelan Ranger District, OKA-WEN National Forest Itemized payment items, quantities, prices and detailed project requirements are attached

Proposal Request Date:
Proposal Response Date/Time (close of business unless otherwise shown):

A BID GUARANTEE is required for all offers exceeding $100,000.00.

OFFER:

Offeror Name (same as on contract)
Offered by (Name, Title, Phone):
Offered Amounts attached in Section B.
Authorized Signature:

Date:

This is a firm offer for 30 calendar days from the Response Date/Time. The offer agrees to furnish any required bonds and to perform the work at the prices offered.

AWARD:

ITEMS ACCEPTED:

TOTAL

AMOUNT: $

Task Order Number and Award Date shown at top.

Ordered by (Name, Title, Phone):
Authorized Signature

Task Order Contracting Officer

SECTION B – BID SCHEDULE

(Detailed List of Payment Items, Quantities, Units, Unit Prices and Amounts)

B-1 BID SCHEDULE

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

Clearing

Actual Quantity
0.02
2
Excavation
Lump Sum
1
3
Tread & Berm
Linear Foot
1035
4
Mobilization
Lump Sum
1

TOTAL PRICE

B-2 NOTE:

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.

Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.

* Denotes Contract Quantity

SECTION C

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C.1 DESCRIPTION OF WORK

This project involves reconstruction of trail in the upper Safety Harbor Creek Area. The trail is located on a road template with slumps, large boulders, and a restrictive width for equipment of eight feet. Work includes removal and disposal of old irrigation pipeline and associated metal, developing access for construction, installing earthen and rock berms, drainage work, and reconditioning the template to a trail tread.

The purpose of this project is to remove a section of decaying irrigation pipe that is under a 1,035 foot segment of the Safety Harbor Creek trail, a motorized trail in the Sawtooth Backcountry of the Chelan Ranger District. The trail is used by motorbikers, horse riders, mountain bikers, and hikers.

Motorcycle use is the primary use identified in the trail management objective. A 24" diameter pipe made of creosote-treated wood wrapped with metal rings was part of the aquaduct that supplied irrigation water for the Manson and Chelan orchards until it was damaged by wildfires in 1970.

C.2 PROJECT LOCATION

Safety Harbor Creek Trail #1261 is located on the the North shore of Lake Chelan. T.30 N. R.20 E. Sec. 28. Access is off of the Grade Creek Road #8200 via spur Road #155. Distance from Chelan WA. is approximatelly 40 miles.

FOREST SERVICE STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES (AGAR 452.236-78) (NOV 1996) The Forest Service Standard Specifications for Construction and Maintenance of Trails, September 1996 are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.

(End of Clause) Forest Service Standard Specifications for Construction and Maintenance of Trails (EM-7720-103 may be obtained by contacting:

Superintendent of Documents

U.S. Government Printing Office

Washington, D.C. 20402

OR PHONE Seattle

Government Printing Office

Seattle, Washington

(425) 553-4270 ASTM Standards

American Society for Testing and Materials

1916 Race Street

Philadelphia, PA. 19103

(215) 199-5462

AASHTO

American Association of State Highway and Transportation Officials

341 National Press Building

Washington, D.C. 20024 NOTE: The Wenatchee National Forest has no copies of the above for public distribution.

TECHNICAL SPECIFICATIONS

906.03F1 April 18, 2002

906.03 Units of Measurement

Delete this subsection and add the following:

“Forest Service Specifications for Construction and Maintenance of Trails (September 1996) are based on Modern Metric units of measurement. The dimensions and units of measure SHOWN ON THE DRAWINGS for this contract utilize U.S. Standard English units of measure. The SPECIAL PROJECT SPECIFICATIONS developed for this contract, utilize dual units of both Modern Metric and U.S. Standard English units of measure. All measurements referenced in the August 1996 Forest Service Standard Specifications (EM-7720-100) shall be converted to U.S. Standard English units of measure. Appendix A – Engineering Conversion Factors and Appendix B – SI (Modern Metric) Conversion Factors, are included on pages 612 – 614 of the Standard Specification Appendices to assist with any required conversions.

Where references are made to a Metric technical specification, such as ASTM or AASHTO, use the equivalent U.S. Standard English technical specification can be used for purposes of material certifications.

Work required by the contract will be paid based on the PAY UNIT (U.S. Standard English measure) as DESIGNATED IN THE SCHEDULE OF ITEMS.

Under each Specification Section with PAY ITEMS of work DESIGNATED IN THE SCHDULE OF ITEMS for measurement and payment under this contract, the last subsection “Payment - Basis”, shall have the following format:

Pay Item - Numbering system and work description to remain the same.

Pay Unit - Pay unit(s) DESIGNATED IN THE SCHEDULE OF ITEMS have been changed from metric to the corresponding unit of U.S. Standard English measure.

Payment will be by units defined and determined according to U.S. Standard English measure and by the following:

(a) Cubic Yard in Place. Measure solid volumes by the average end area method as follows:

(1) Measure cross sections of the original ground and use with design or staked templates, or take other comparable measurements to determine the end area. Do not measure work outside of the established lines or slopes.

(2) If any portion of the work is acceptable, but is not completed to the established lines and slopes, re-measure cross sections or comparable measurements of that portion of the work. Deduct any quantity outside the designated or staked limits. Use these measurements to calculate new end areas.

(3) Compute the quantity using the average end areas multiplied by the horizontal distance along a centerline or reference line between the end areas. Deduct any quantity outside the designed or staked limits.

Where it is impractical to measure material by the average end area method, other approved methods involving three-dimensional measurements may be used.

(b) Cubic Yard in the Hauling Vehicle. Measure the cubic yard volume in the hauling vehicle using three-dimensional measurements at the point of delivery. Use vehicles bearing a legible identification mark with the body shaped so the actual contents may be readily and accurately determined. Before use, mutually agree in writing upon the volume of material to be hauled by each vehicle. Vehicles carrying less than the agreed volume may be rejected or accepted at the reduced volume.

Level selected loads. If leveling reveals that the vehicle was hauling less than the approved volume, reduce the quantity of all material received since the last leveled load by the same ratio as the ratio of the current leveled load volume to the agreed volume. Payment will not be made for material in excess of the agreed volume.

Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purpose if the conversion factors are mutually agreed to in writing.

Compute measurement using measurements of material in the hauling vehicles at the point of delivery. Load vehicles to at least their water-level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

(c) Cubic Yard Mile. A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one(1) mile.

(d) Hour. Measurement will be for the actual number of hours ordered and performed by the Contractor.

(e) Each. One complete unit, which may consist of one or more parts.

(f) Lump Sum. Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.

(g) MFBM. One thousand feet board measure based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminate timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

(h) Gallon. The quantity may be measured by any of the following methods:

a. Measured volume container.

b. Metered volume. Use an approved metering system.

c. Commercially packaged volumes.

(i) Station. One hundred linear feet measured horizontally.

(j) Station Yard. A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one station.

(k) Square Yard. Measure on a plane parallel to the surface being measure or horizontal.

(l) Thousand Gallons Mile. A combination of linear and volumetric measurement meaning the movement of 1,000 gallons of material one (1) mile.

(m) Ton. Short ton consisting of 2,000 pounds. Use net certified scale weights based on certified volumes.

(n) Ton Mile. A combination of linear and weight measurement meaning the movement of one (1) ton of material one (1) mile.”

SECTION F – PERFORMANCE TIME

F-5

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK / ALTERNATE I

The following performance time requirements shall apply to this project:

60 Calendar Days with desired start work date of July 1, 2008

SECTION G – CONTRACT ADMINISTRATION DATA

G-9

GOVERNMENT-FURNISHED PROPERTY (AGAR 452.245-70) (FEB 1988)

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.

NONE

G-10

POST AWARD CONFERENCE (AGAR 452.215-73) (FEB 1988)

A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be held at the Headquarters of the Okanogan and Wenatchee National Forests, 215 Melody Lane, Wenatchee, WA.

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H-1

LANDSCAPE PRESERVATION AND HAZARDOUS MATERIALS

Add the following:

(a) The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawn or natural features not designated for treatment. The Contractor shall confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material which falls outside of these limits shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Prevention of Oil Spills. If the Contractor maintains storage facilities for oil or oil products on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or other waters of the United States or any of the individual states. If a spill of petroleum product should occur in water, the Contractor shall take immediate action to clean up or contain the spill, then immediately notify the Engineer and the Oregon Emergency Response System (OERS), telephone 1-800-452-0311 or 1-503-378-4124, and then immediately notify the Contracting Officer.

Contractor shall have a SPILL RESPONSE KIT on the project whenever equipment is operating. The spill kit shall be sufficient to absorb 34 gallons of oil, designed to float on the surface, while absorbing oil and repelling water. The KIT shall meet or exceed the physical properties of “New Pig Products Spill Kit #408”.

Oil absorbing mats are required under all stationary equipment, or equipment being serviced within the Forest Boundary to prevent leaking or spilled petroleum base products from contaminating soil and water resources. Such material will be furnished by Contactor and approved by Contracting Officer.

Servicing of all equipment shall be done only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Equipment shall be furnished on a fully operational basis, of modern design and in good operating condition with no fuel or oil leaks. Repairs and move-in/move-out are the Contractor’s responsibility. All equipment shall be power washed and shall be clean prior to entering Forest Service Land.

(c) No objectionable material shall be allowed to enter any stream, river, lake, or other body of water. Material which falls in these areas shall be retrieved and disposed of, or incorporated in the work as directed by the Contracting Officer, and damage to vegetation or structures outside the project limits shall be repaired as directed by the Contracting Officer.

(d) The Contractor shall not operate equipment or otherwise disturb the natural vegetation and soil beyond the areas flagged on the ground or beyond two feet from edge of walkways, top of cuts, or toe of fills.

(e) The Contractor will make every reasonable attempt to preserve the scenic and natural environment along this construction project.

(f) Prior to the start of construction the Contractor shall submit to the Engineer for approval a schedule and plan for temporary pollution control measures for the following phases of work:

H-2

PROSECUTION OF WORK – WORK HOUR LIMITS – WORK ITEM LIMITS

Add the following:

a) All construction activity shall be limited to two (2) hours after sunrise and two (2) hours before sunset, Monday through Friday, unless other hours are approved in writing by the Contracting Officer. The Contractor shall conduct activities so that interference with the public shall be kept at a minimum.

b) The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.

H-3

SANITATION REQUIREMENTS

Unless substitute measures or equipment are authorized in writing by the Contracting Officer, protection of air and water quality will include the use of approved chemical toilets by all persons engaged in road construction or in removing timber under this contract while they are within the boundaries of the Forest. Such facilities shall be furnished by Contractor in quantities and at locations approved by the Engineer. No habitation or overnight dwelling by employees of Contractor will be permitted on National Forest land without advance written approval from the Contracting Officer.

SECTION J - ATTACHMENTS

Item Number of Pages

1. Individual Project Technical Capability Questionnaire 1 page

(Attached separately)

2. List of Applicable Drawings:

4 drawings

(Attached separately)

Vicinity Map

Project Area

Site Map

915-1 Existing Trail Restoration

3. General Decision Number: WA20080001 5/09/2008 44 pages

(Attached separately)

4. Fire Protection Requirements Forms from basic contract:

· R6-FS-6300-52 applies

· Measure 1 applies

· Measure 2 applies

Bid Bond Form SF-24 applies if offer exceeds $100,000.00 and a Surety Bond is used for the Bid Guarantee.

QUESTIONNAIRE

Project C: Safety Harbor Trail Pipline

1. Capability and Project Schedule -

a) Provide a brief explanation of your capability to accomplish this work. You may include a description of the work you plan to subcontract out.

b) Include a list of equipment you will provide to complete the work (owned or rented).

c) Provide your expected schedule including sequence of work items and approximate time to complete each item.

2. Sequencing ALL work

a) Provide your planned sequencing of all work on this segment of the road.

b) Assume there will be water flowing in the stream. Provide a brief explanation of your water diversion and erosion control practices associated with the work.