E. Quality_Control.pdf
PDF 27 KB Posted
- Attached to
- Ditch Creek and Ollokot Campground Well Drilling
- Solicitation number
- AG-04M3-S-09-0050
About this file
E. Quality Control
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_1_change_setaside.rtf | RTF text file | |
| M. sf25a_Payment_Bond.pdf | ||
| B. AG-04M3-S-09-0050.rtf | RTF text file | |
| J. ollokot campground well drawings.pdf | ||
| I. DITCH TITLE SHEET | — | |
| H. Daily well drilling shift record.pdf | ||
| L. sf25_Performance_Bond.pdf | ||
| C. Measuremnt and Payment.pdf | ||
| D. Submittal_Procedures.pdf | ||
| Return_This_Copy.rtf | RTF text file | |
| F. Product_Storage_Handling.pdf | ||
| N. sf25b_Continuation_Sheet.pdf | ||
| G. Water_Supply_Well.pdf | ||
| K. Contract SITE PLAN DITCH CREEK.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
06/2009 Ditch Creek GS and Ollokot CG Wells 01450 - 1/1
Quality Control
SECTION 01450
QUALITY CONTROL
PART 1 � GENERAL
1.01 SUMMARY
A. Provide certification that the quality and quantity of construction conforms to the drawings, specifications, and requirements of the contract.
PART 2 � PRODUCTS
Not Used
PART 3 � EXECUTION
3.01 CERTIFICATION & MEASUREMENTS
A. Offsite-Produced Materials: Furnish certificates executed by the manufacturer supplier, or vendor, stipulating that all materials produced off site that are incorporated into the work meet the applicable requirements stated in the specifications. Make each certificate apply to a single commodity or invoice. Certify all incidental purchases needed to remedy minor shortages of material.
B. Quantity Measurements: Make all measurements for computation of quantities for all work items, except those specified for payment by design quantity or lump sum. Compute the quantities for periodic progress payments; the CO will compute the quantities for the final payment based on measurements taken. All Contractor measurements are subject to verification. Submit all field notes, calculation sheets, and other data used to determine quantities, and certify in writing as to the accuracy of the measurements and computations submitted
END OF SECTION