D._Amendment_6__B1_Schedule.docx

DOCX document 26 KB Posted

Attached to
Malheur N. F. 10 Year Stewardship Project
Solicitation number
AG-04KK-S-13-9000
Issued by

About this file

D. B1 Schedule of Items

View the file

Other files

File Type Posted
Amendment_9Task_Order_1_MD.pdf PDF
Amendment-09.pdf PDF
C._Amendment_8_Task_Order_1_MD.docx DOCX document
B._Amendment_8_Appendix_A.doc DOC document
D._Amendment_8_Appendix_B.docx DOCX document
A._Amendment-08.docx DOCX document
E._July_16__Pre_Proposal_Roster.pdf PDF
b._Amendment_7_Appraisal_calamity-teasum.pdf PDF
a._Amendment-07.pdf PDF
e._Amendment_7_Appraisal_paw-teasum.pdf PDF
d._Amendment_7_Appraisal_md-teasum.pdf PDF
f._Pre_Proposal_July_9__Seneca_Participant_List.pdf PDF
g._July_23rd_public_meeting_announcement.pdf PDF
c._Amendment_7_Appraisal_dairy-teasum.pdf PDF
B._Amendment_6_Appendix_A.doc DOC document
E._Amendment_6_Wage_Determination_Revision_45_1977-0079_sca.txt TXT text file
A._Amendment-06.docx DOCX document
C._Amendment_6_Task_Order_1_MD.docx DOCX document
Amendment-05.pdf PDF
Final_Roster_July_3rd.pdf PDF
H._Appraisal_Calamity_TO_1.txt TXT text file
A._Amendment-04.pdf PDF
F._Appraisal_MD_TO_1.pdf PDF
I._Appraisal_Dairy_TO_1.pdf PDF
D._Cruise_Calamity_TO_1.txt TXT text file
E._Cruise_Dairy_TO_1.txt TXT text file
C._Cruise_PAW_TO_1.txt TXT text file
G._Appraisal_PAW_TO_1.pdf PDF
B._Cruise_MD_TO_1.txt TXT text file
a.Amendment-03.pdf PDF
b.Amendment_3_E._Appendix_C_2_K-F.3___MD.pdf PDF
c.Amendment_3-_I._Appendix_C_5_K-F.3__PAW.pdf PDF
d.June_27th_Pre_Proposal_Roster.pdf PDF
Amendment_2_Appendix_A.doc DOC document
Amendment-02.docx DOCX document
Amendment-01.docx DOCX document
O._Pre_Proposal_Vicinity_Map_1_of_3.pdf PDF
K._Calamity_StewardshipTask_Order_1_map.pdf PDF
Q._Pre_Proposal_Map_3_fo_3.pdf PDF
I._Appendix_C_5_K-F.3__PAW.pdf PDF
N._Task_Order_1_MD_Wage_Determination_77-0079_sca.txt TXT text file
J._MD_Stewardship_Task_Order_1_map.pdf PDF
G._Appendix_C_3_K-F.3__Dairy.pdf PDF
H._Appendix_C_4_K-F.3__Calamity.pdf PDF
M._Paw_Stewardship_Task_Order_1_map.pdf PDF
P.Pre_Proposal_Map_2_of_3.pdf PDF
B2._Task_Order_1_MD.docx DOCX document
R._How_to_Do_Business_With__Government__R6-revised_021513.doc DOC document
C._Appendix_A.doc DOC document
L._Dairy_Stewardship_Task_Order_1_map.pdf PDF
Show 40 more

Latest 50 of 55 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-04KK-S-13-9000, Malheur Forest-Wide Stewardship AMENDMENT 6 07/15/2013

PART I – THE SCHEDULE

SECTION B – SERVICES AND PRICES

SCHEDULE OF ITEMS

B.1 SCHEDULE OF SERVICE ITEMS:

Contractor Name

ITEM NO.
DESCRIPTION

WORK ACTIVITIES

UNIT
TOTAL ESTIMATED

QUANTITY

UNIT PRICE
TOTAL

MANDATORY SERVICES

This is the work that is currently available. Additional work will be added via task order as NEPA is completed. The following line items will be used for award purposes and when determining price reasonableness on future task orders. Stewardship credits may be accrued for these work items.

SEE ATTACHED TASK ORDER.

SS

OPTION ITEMS TO BE PERFORMED

This is just a sample of work activities since we will not know what work will be performed until the Forest Service completes NEPA for the additional work areas. The following line items will be used to determine price reasonableness for award purposes. Actual work to be ordered will be negotiated using detailed cost breakdown data. Stewardship credits may be accrued for these work items.

SERVICE WORK Subject to Service Contract Act Wages

1
a) Pre-commercial thinning of stands with 250-1000 tpa to a spacing of 20X20 (Range 0-25000 acres)

LABOR INTENSIVE

Acre
12000

b) Pre-commercial thinning of stands with 1001-2000 tpa to a spacing of 20X20 (Range 0-25000 acres)

LABOR INTENSIVE

Acre

12000

1
c) Pre-commercial thinning of stands with 2001-6000 tpa to a spacing of 20X20 (Range 0-15000 acres)

LABOR INTENSIVE

Acre

2
Mechanical Fuels Reduction:

a) Mechanical Piling or Removal (Range 0-50000)

b) Mastication (Range 0-5000) Acre Acre 25000

3
Hand Piling (Range 0-1000 acres)

LABOR INTENSIVE

Acre
500
4
Machine Fireline Construction (Range 0-5 miles) 3’ to 8’ wide to mineral soil and clear ladder fuels to 10’ interior.
Mile
2
5
Hand Fireline Construction (Range 0-5) 18” wide to mineral soil and clear ladder fuels to 10’ interior.

LABOR INTENSIVE

Mile
2
6
Leave Tree Marking (contractor supplied paint), (Range 0-20,000 acres)
Acre
10,000
7
Pile Burning, (0-60,000 acres) hand piles and grapple piles.
Acres
30,000
8
Weed Spraying, (0-500 acres)
Acres
250
9
Road Maintenance – Vegetation removal, Grade and shape road to remove gullying and erosion, and movement of sediment from road surface and ditches into nearby streams. (Range 0-1000 miles)
Mile
1000
10
Road Obliteration – Close roads by filling and re-contouring the excavated road bed. Pull out culverts and stabilize stream crossing sites. (Range 0-200 miles)
Mile
2
11
Road Decommissioning – Close roads with slash, rocks and/or earthen berms. Pull out culverts and stabilize unstable fill slopes and stream crossing sites. (Range 0-200 miles)
Mile
5
12
Road De-Compacting Rip roads to not less than 16 inches deep and 12 feet wide. (Range 0-200 miles)
Mile
2
13
Road Entrance Closures – Close road entrances with slash, rocks and/or earthen berms. (Range 0-200 roads)
Each
5
14
Culvertcatch basin and ditch-line clean-out to facilitate water flow for fish passage, and to prevent road failure due to water back-up. (Range 0-3000 each)
Each
15

CONSTRUCTION

Subject To Davis-Bacon Wages

15
Fish Passage Culverts (Range 0-20 each)
Each
10
16
Aspen Fencing, Exclosure (Range 0-5 miles) 4 strand wire fence around small aspen stands.
Mile
2
17
Riparian Fencing, (0-10 miles) 4 strand wire.
Mile
5
18
Road Construction (Range 0-25 miles)
Mile
12
Total All Service Items
$