AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. /3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
008 2/23/2012
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
SW IDAHO-NEVADA ACQUISTION CENTER
1249 S VINNELL WAY STE 200
BOISE, ID 83709-1663
CONTRACTING OFFICER - USDA ,USFS, SWINAC
c/o SPRING MTNS. NATIONAL REC. AREA
4701 N. TORREY PINES DRIVE
LAS VEGAS, NV 89130
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
AG-0261-S-12-0004
9B. DATED (SEE ITEM 11)
11/22/2011
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Project Title: Desert View Overlook Rehabilitation
Purpose of Amendment: 1) To answer FINAL questions posed by vendors. No further questions will be accepted.
Receipt of Offers: The date, time, and receipt of proposals remains unchanged - Tuesday, February 28, 2012, 3:00 PM PST. The place for receipt of offers remains the same.
Acknowledgment: See Block 11 above regarding how to acknowledge this amendment. The acknowledgement must be received at the place designated for receipt of offers (see Block 19 of the Solicitation, Offer, and Award, Standard Form 1442).
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Margaret S. Schafer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 008 AG-0261-S-12-0004 – Desert View Overlook
1. Answers to Final Questions posed by Vendors:
Q1) In the Anchor to Soldier Pile detail it shows the anchor extending through the beam web as if the beam is in two pieces. In the geocomposite drainage detail it shows the tieback anchor in the center of the beam flange. The schematic soldier pile
& precast lagging detail shows the anchor being installed to the right of the flange.
Please confirm which of these details are correct.
Answer: The anchor will be installed toward the right side of the H-Pile
Q2) If the beams are to be notched in any way for the anchor installation, how is the epoxy coating to be applied for the cut areas since the epoxy coating will have to be done off site prior to beam delivery?
Answer: The beams will be notched and a coating will be applied to the cut areas in the field.
Q3) Can these notches be cut in the field? Can epoxy coating be applied in the field?
If so, what is the recommended epoxy coating?
Answer: Yes, the notches in the beams can be cut in the field. Yes an epoxy coating should be applied to the cut areas in the field. Please provide preferred epoxy coating in the submittals for approval.