Chickamin Barge Dry-Dock
1. SCOPE
This contract is for Barge Hull and On-Board System Inspections, modifications, and repairs. Work items include:
a. Move barge from mooring to dry dock facility and return to mooring following work.
b. Exterior hull work – pressure wash and inspect for damage and report findings.
c. Fuel tanks –
· fill,
· test fuel
· treat for multiple year storage and use.
d. Bilge work –
· pressure wash inside hull and inspect for damage.
· Evaluate and report findings for dry exhaust piping IAW ABYC standard P-1.
· Evaluate and replace non-compliant fuel oil hoses on generators.
e. Electric work –
· Mount and wire in government supplied Water Treatment Control Panel (WTCP).
· Remove multiple existing float switches and install multiple new float switch assemblies.
· Remove multiple existing plumbing and install multiple new float switch assembly.
· Cut in and install new proximity switches.
· Install 120 Volt, 20 amp circuit to Water Treatment Control panel.
· Rewire Distribution pump control.
· Remove overload, reconnect starter relay, loop control coil to WTCP.
· Remove old control panel and all unused cabling.
· Rewire existing motor starter for filtration pump.
· Control circuit for starter shall be looped to WTCP.
· Connect twist lock connector body Hubbell HBL2353/HB60CM32 to shipboard cable for connection to valve assembly.
· Remove old gray water pump, starter, and associated equipment.
· Terminate cable from WTCP in DC control panel (DCCP) in aft hold.
· Install inlet valve assembly.
· Place existing ROMEX into junction boat for future light.
· Coordinate with ceiling. Inlet valve assembly cut into new ceiling tile existing junction box for smoke detector.
· Evaluate electrical system for sensitive ground detection system which provides continuous indication of circuit status to ground.
f. Deck Inside building –
· rehab/pressure wash, loose scale, fine powder rust treatment tank. Spot paint treatment tank. Weld deck fitting. Disinfect treatment tank and flush entire system. Deck penetration for water inlet fitting – structural steel platform, exterior.
Plumbing –
· Connect treatment and distribution tanks.
· Replumb piping in foreward bulkhead.
· Replace flexible coupling with rigid connection.
· Deck fitting unit – install check valves for backflow prevention.
· Install preliminary filter housing on untreated water line.
· Install drain valves, to flush filters and collect water samples.
· Relocate RO product line upstream of chlorine injections point.
· Install raw water tank bypass.
· Install treated water connection to distribution tanks.
· Install true union ball valves on either side of new equipment and at new tees.
· Install unions between new valves and filter housing.
Roof specialties –
· Reconfigure downspouts to discharge overboard.
Electrical –
· Water system automation and miscellaneous electrical work.
Miscellaneous carpentry –
· Ceiling repair, water infiltration repair, damaged siding repair.
· Replace in kind 27 damaged/missing 2X4 drop in tiles.
· Reattach 12” X 12” ceiling squares.
· Replace missing ceiling.
· Find repair source of water infiltration.
· Fix damaged siding around battery box exhaust vent.
· Install fuel shut off valves before and after fuel filter on Toyo stove.
· Inspect Fire Extinguishers and assure eight are mounted as described in specifications.
· Service and certify two On-Board Life rafts.
g. Deck outside building –
· Pressure wash and inspect for damage.
· Prepare and paint deck non-skid areas
· Prepare and paint all deck appurtenances,
· Inspect and service boom,
· Inspect and service deck winches and cabling,
· Inspect and service capstans,
· Fabricate waterproof (oil skin) winch covers and tie down straps.
h. OPTION ITEMS:
· Remove unused Water piping and fittings.
· Welding shut unneeded penetrations on forward bulkhead.
· Install 81 gallon pressure tank and associated pressure gauges.
· Replace chlorinator.
· Install pulse meter (must be done if chlorinator is replaced).
· Replace chlorine solution tank (10 gallons).
· Replace filter housings.
· Replace all piping, downstream of preliminary filter, elbows, and tees.
· Install true union ball valve on either side of new equipment.
· Remove finishing filter.
· R.O. System – condition assessment and remediation contract preparation. (Evaluate and report findings.)
· Produce isometric drawing of entire water system