AG-0109-C-16-0017
West Glacier Area Enhancements
1 | P a g e
PART I—THE SCHEDULE
SECTION B. SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
Base Bid Item Description Qty Pay Unit Price
A Mobilization and bond premiums for all work, including Additive Items, if awarded.
1 Lump Sum
B Multi-use Trail from existing bike path, including two trail bridges, Skater’s Road crosswalk, and bike racks at West Glacier Trailhead.
1 Lump Sum
C West Glacier SST Trailhead and Toilet, and all related excavation, access paths, stairway and beach area improvements (excluding aggregate path in Option Item 6)
1 Lump Sum
Total Base Bid $ Option Items (ea.)
1 Skater’s Cabin area improvements including asphalt parking lots, aggregate trails connecting to Multi-use Trail, and culverts work
1 Lump Sum
2 Tolch Rock Parking Lot and Tolch Rock Trail Improvements 1 Lump Sum $ 3 Skater’s Cabin area Water valve and meter relocation 1 Lump Sum $ 4 All signs as shown on Sign Plan 1 Lump Sum $ 5 Bollard installation at Arctic Drive 1 Lump Sum $ 6 250’ of 6’ wide aggregate path, along the West Side of West
Glacier Trailhead parking, as shown on Sheet 7; and construction of “View Trail” at West Glacier Trailhead.
1 Lump Sum
Total All Option Items
Grand Total of Base and Options $
Additional Vendor Information Contact Name:
Phone No:
Cell Phone No:
DUNS No:
Email:
2 | P a g e
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 PROJECT DESCRIPTION AND LOCATION
(a) Description:
The Base Item work is the West Glacier Spur Road Area Enhancements, as specified below, and includes mobilization.
Major work items for the Base Bid include construction of a Multi-Use trail from Skater’s Cabin to West Glacier Trailhead, including two trail bridges, a crosswalk where the trail crosses Skater’s Cabin Road, and bike racks at the West Glacier Trailhead. Work also includes improvements at West Glacier Trailhead, including the supply and installation of the West Glacier SST Toilet, as well as all aggregate paths, staircases, beach improvements, and site amenities as shown on the plans, excepting 250’ of 6’ wide aggregate pathway on the west side of the parking lot (as shown in Option Item 6). All aggregate materials used in this part of the project are incidental to the construction of this base bid item and no additional payment will be made for these materials.
Option Item #1 is work located at the Skater’s Cabin area, and includes the construction of one parking lot, the reconstruction of two existing parking lots, aggregate trails along the parking lots, and culverts.
All aggregate materials used in this part of the project are incidental to the construction of this Option Item and no additional payment will be made for these materials.
Option Item #2 is work located at the Tolch Rock Trailhead, and includes the reconstruction of the parking area as well as improvements to the Tolch Rock Trail. All aggregate materials used in this part of the project are incidental to the construction of this Option Item and no additional payment will be made for these materials.
Option Item #3 work consists of the water valve and meter relocation near Skater’s Cabin. All aggregate materials used in this part of the project are incidental to the construction of this Option Item and no additional payment will be made for these materials.
Option Item #4 is the supply and installation of all signs as shown on the Sign Plan.
Option Item #5 is the supply and installation of 2 bollards at Arctic Drive.
Option Item #6 is the construction of 250’ of 6’ wide aggregate path, along the west side of West Glacier Trailhead parking lot.
(b) Location and Facilities: West Glacier Trailhead and Skater’s Cabin are located on the Southwest corner of Mendenhall Lake, on Skater’s Creek Road, and are approximately 13 miles from downtown Juneau. Water and sewer supply the nearby Mendenhall Campground but do not continue into the project area.
(c) Price Range: The Base Bid with all option items is estimated between $500,000 and $1,000,000.
(d) Pre-bid Tour: Yes. See Section L, FAR 52.236-27 Site Visit for details.
(e) Period of Performance: Period of Performance for this requirement is 365 days from date of award.
3 | P a g e
C.2 TECHNICAL SPECIFICATIONS
The following specifications are hereby made part of this solicitation and any resultant contract:
The technical specifications included in Section J.
The Federal Highways Administration Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03 (abbreviated in these specifications as FP-03). An online copy may be viewed at: http://flh.fhwa.dot.gov/resources/pse/specs/fp-03/fp-03usc.pdf
The Forest Service Outdoor Recreation Accessibility Guidelines 2013 (FSORAG). An online copy may be viewed at: http://www.fs.fed.us/recreation/programs/accessibility/FSORAG_2013%20Update.1.pdf
The Architectural Barrier Act (ABA) Standards. An online copy may be viewed at: https://www.access-board.gov/attachments/article/1029/ABAstandards.pdf
C.3 AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
C.4 AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D--PACKAGING AND MARKING
Project Labeling for Official Correspondence
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
Clause Number Title Date 52.246-12 Inspection of Construction AUG 1996
E.2 Inspection and Acceptance (AGAR 452.246-70) (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and http://flh.fhwa.dot.gov/resources/pse/specs/fp-03/fp-03usc.pdf http://www.fs.fed.us/recreation/programs/accessibility/FSORAG_2013%20Update.1.pdf https://www.access-board.gov/attachments/article/1029/ABAstandards.pdf https://www.access-board.gov/attachments/article/1029/ABAstandards.pdf http://www.arnet.gov/far/
4 | P a g e accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at the project site.
E.3 Inspection and Testing Performed By Government
The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Special Project Specifications.
E.4 Conformity with Drawings And Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.
SECTION F--DELIVERIES OR PERFORMANCE
F.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
Clause Number Title Date 52.242-14 Suspension of Work APR 1984
F.2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use within 365 days of the date of award. The time stated for completion shall include final cleanup of the premises.
The trail and new parking area can be worked on at any time (even during the normal “tourist season”). From May-October – the contractor may NOT close the roadway. The roadway could be adjusted to one lane for short periods of time with advance notice and approval of the COR. All work items and schedules shall be coordinated with the COR for safety of visitors and staff.
Required Submittals Prior to Receipt of Notice to Proceed:
Quality Control Plan - Prior to receipt of a notice to proceed, the Contractor shall provide a quality control plan.
This plan shall describe the Contractor’s method for ensuring all work meets the contract requirements. At a minimum, the Quality Control Plan shall outline how the quality of work will be monitored, how the crew will be supervised, and who will perform the quality control functions. Contractor shall provide the Contracting Officer with documentation of quality control inspections.
Safety Plan – Prior to receipt of a notice to proceed, the Contractor shall provide a safety plan. This plan shall describe the company’s policies/plan to comply with OSHA standards and for maintaining a safe and injury/illness
5 | P a g e free workplace. This plan shall also describe the company’s plans for maintaining the safety and security of the public at the worksite location(s).
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be held at a mutually agreed upon location.
G.2 Design ation of Contracting Of f icer’s Repr esentative
The Contracting Officer will designate a Contracting Officer's Representative (COR) at the time of contract award.
The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.
The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract).
On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer.
Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
G.3 Contractor’s Designated Representative
It is required that the Contractor have a designated representative available on the project during the entire project and that the representative be able to speak and understand English. When designating a representative, the Contractor shall furnish a copy of the designation in writing to the Contracting Officer. Such designation shall clearly indicate the name and limitations (if any) of authority of the representative. If the Contractor intends to designate a representative prior to the pre-work meeting, the representative is strongly encouraged to attend that meeting.
G.4 FAR 52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
• The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Visual Condition and Route Surveys.
• Weather conditions: http://www.weather.gov http://www.weather.gov/
6 | P a g e
G.5 Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP)
(a) Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform (IPP). "Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is:
https://www.ipp.gov. The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fms.treas.gov or phone (866) 973-3131.
(b) Final Payment. The final invoice must be accompanied by a release of claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically accepted from the operation of the release. Final payment will not be approved without a properly executed Contract Release, Form 6300-16.
(c) In addition, when submitting the invoice, the Contractor shall submit payrolls, subcontractor payment information and a spreadsheet detailing the payment breakdown in accordance with the Pay Items in the Schedule of Items, Section B.1 (either electronically in IPP, hard copy, or via fax) to the Contracting Officer (see FAR 52.232-5 Payments Under Fixed Price Construction Contracts).
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 AGAR 452.236-73 ARCHAEOLOGICAL OR HISTORIC SITES (FEB. 1988) – See Section I
H. 2 ORDER OF PRECEDENCE - REQUIREMENTS, SPECIFICATIONS, DRAWINGS
Resolve any inconsistencies in the Specifications of this solicitation and any resultant contract by giving precedence in the following order:
a. Section H - Special Contract Requirements
b. Section C – Statement of Work
c. Drawings
1. Drawings, figured dimensions over scaled dimensions
2. Drawings, large scale contract drawings over small scale contract drawings
3. Schedules on contract drawings over any conflicting notations on contract drawings.
4. Shop Drawings - (The term "Shop Drawings", includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the Contractor to explain in detail specific portions of the work required by the contract.)
d. Special Project Specifications.
e. Standard Specifications incorporated by reference
f. Staking on the ground
H. 3 LANDSCAPE PRESERVATION
Confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Unless otherwise agreed to by the CO, retrieve material which falls outside of these limits and either incorporate the material in the work or dispose of the material as directed by the CO.
Schedule and conduct operations to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.). Install silt fencing around areas immediately next to streams and ponds to mitigate suspended sediments when designated on the drawings.
https://www.ipp.gov/
7 | P a g e
Do not discharge pollutants such as raw sewage, and other harmful materials into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Do not allow wash water or waste water from concrete or aggregate operations to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
Collect and return waste motor oils, fuels, lubricants, bitumens and similar hydrocarbons to the supplier. Comply with the requirements of 40 CFR 279, Standards for the Management of Used Oil. Do not discharge hydrocarbon products on the ground, use them for road oiling, or bury them in a landfill.
Do not operate mechanized equipment in live streams without written approval of the Contracting Officer.
There are no known eagle nest trees in the vicinity of the project area, but if such trees are discovered no disturbance will be allowed within 330 feet of the trees and additional mitigation measures may be applied.
Obtain necessary permits for floating camps, floats, shore ramps, and other appurtenances associated with project operations from the following State of Alaska and Federal Agencies:
1. ADNR - Alaska Department of Natural Resources.
2. ADEC - Alaska Department of Environmental Conservation.
3. ADGC – Alaska Department of Governmental Coordination.
4. EPA – US Environmental Protection Agency.
5. DA, COE – US Army Corps of Engineers.
6. USCG – US Coast Guard.
H. 4 USE OF PREMISES
(a) A “watchman” camper may be permitted at the work site. Obtain written approval from the Contracting Officer before opening or operating on National Forest land or lands administered by the Forest Service any camp, quarry, borrow pit, storage area, detour, or bypass site, other than SHOWN ON THE DRAWINGS. A camp is interpreted to include the camp site or trailer parking area of any employee working on the project for the Contractor. Such approval, if granted, will be without charge to the Contractor.
(b) Public recreational camping facilities are available at Mendenhall Campground from May 15-Sept 15. Use of this facility may be allowed as approved by the Gov’t, subject to all existing rules and policies. Exemptions may be made to the length of allowable stay, as approved.
(c) Sanitation Facilities: Provide and maintain the following facilities for the work force at the work site, unless provided otherwise.
1. Meet State of Alaska drinking water regulations 18 AAC 80 regarding potable water supplies for drinking, washing and cooking.
2. Comply with State of Alaska wastewater disposal regulations 18 AAC 72 for domestic sewage.
3. Ensure that the design, operation, and maintenance of all solid waste systems under Forest Service jurisdiction meet all Federal, State, and local requirements. Meet State of Alaska solid waste management regulations (18 AAC 60) and Federal regulations contained in 40 CFR 243, 40 CFR 245, 40 CFR 257, and 40 CFR 258. Remove solid wastes and/or residues and dispose of in approved commercial landfills.
4. Meet the requirements of 40 CFR 112 (Oil Pollution Prevention) for fuel storage. Meet the requirements of 33
CFR 150 and 33 CFR 154 for facilities transferrring oil or hazardous materials in bulk.
(d) Do not begin any camp development, either land based or floating, until a plan for development, occupation, and cleanup is submitted and approved by the Contracting Officer. Include the following information on this plan:
8 | P a g e
1. Location and size of the proposed camp development, including a map.
2. Wastewater system.
3. Number of people who will use the site and proposed dates of occupancy.
4. Power supply system.
5. Water supply system.
6. Building layout, shop area, living quarters.
7. Road and trail layout.
8. Clearing limits and slash disposal locations.
9. Borrow areas.
10. Dock and access location.
11. Equipment and fuel storage area and Spill Prevention Control and Countermeasure (SPCC) plan.
12. Incinerator location and ash disposal plan.
Forest Service will review plan as submitted for completeness and applicability. Proposed modifications of Contractor's plans will be discussed with the Contractor prior to approval. Any modifications agreed upon will be incorporated in a revised set of plans.
H. 5 EMERGENCY CONTROL
(a) Immediately extinguish without expense to the Government all fires on or in the vicinity of the project which are caused by the Contractor's employees, whether set directly or indirectly as a result of construction operations, with or without direction by the Forest Service. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government resulting from fires set or caused by Contractor's employees or resulting from construction operations.
(b) Contractor's Responsibility for Controlling Other Emergencies - When requested by the Contracting Officer, allow the Forest Service to temporarily use employees and equipment for emergency control work. Payment will be made at not less than the current area rate established by the Forest Service.
(c) Fire fighting equipment will be required during the fire season from May 10 to August 31, and during any other period of fire danger designated by the Contracting Officer.
Furnish rust-free fire tools to equip all workers employed in Contractor's operations at each separate work site.
Maintain tools in serviceable condition and keep tools in one or more weather-tight fire tools boxes. Paint fire tools boxes red, mark "tools for Fire Only" with letters at least 3” high, and keep sealed. Post a list of the contents inside each fire tool box so as to be visible when opened.
Kind of Tool No. of People Working in Area 1-4 5-9 10-
16-
Axe, d.b chopping, 32-inch min. handle 1 1 2 3 Shovels, L.H. R.P., No. 0 or larger 1 3 6 7 Pulaski, 32-inch min. handle 2 3 7 10 File, 10-inch mill bastard 1 1 1 2 Pumps, backpack cans, 5-gal filled with water
1 2 2 3
Equip each internal combustion engine with a spark arrester qualified and rated USDA-Forest Service, Standard 5100-1, unless it is:
(a) Equipped with a turbine-driven exhaust supercharger such as the turbocharger. There shall be no exhaust bypass.
(b) A multi-position engine, such as on a chain saw, which is equipped with screen arrester, as described in the Forest Service Spark Arrester guide.
9 | P a g e
A spark arrester, which does not meet the requirements in this guide may be approved upon submission of acceptable proof that the arrester is at least 80 percent efficient in retention, attrition, or destruction of carbon particles. Such arrester may be required to meet higher standards as improvements in design and efficiency are discovered.
(c) A passenger-carrying vehicle or light truck intended primarily for use on roads, and equipped with a factory designed muffler and exhaust system.
(d) A heavy duty truck, such as a dump or log truck, or other vehicle used for commercial hauling, used only on roads and equipped with a factory designed muffler and with a vertical stack exhaust system extending above the cab.
Properly install and constantly maintain in serviceable condition all exhaust equipment described in this Subsection, including spark arresters and mufflers.
Equip each unit of mobile or stationary power equipment, including trucks, with one shovel, and at least one fire extinguisher meeting one of the following specifications:
1. 2-1/2 pound size or larger dry chemical type.
2. 4-pound size or larger carbon dioxide type.
Test or check each extinguisher for proper functioning prior to the beginning of fire precautionary period.
Provide each gasoline power saw with one chemical-pressurized fire extinguisher of not less than 8-ounce capacity by weight. Maintain the extinguisher in good working order at all times.
Do not burn camp refuse, brush, slash, or debris such as that resulting from clearing around camps or on rights-of-way, without the written approval of the Contracting Officer. Submit written requests for burning to the Contracting Officer at least 48 hours in advance of intended burning. The Contracting Officer will approve routine camp refuse disposal incineration in the camp development proposal.
H. 6 CONSTRUCTION STAKES, LINES, AND GRADES
The Government will field stake items as identified in the drawings and specifications.
Perform all construction staking and grade establishment and survey work required to complete the project.
H. 7 GOVERNMENT PROVIDED MATERIALS
(a) Suitable aggregate rock and gravel resulting from excavation, to use as base course and fill, as approved by the
CO.
(b) Boulders are available on site that may be re-used, as approved, in the project as specified on plans. Boulders are also available in a stockpile on the west side of the West Glacier Trailhead parking lot that may be used in the project.
H.8 NOTIFICATION OF WORK SCHEDULE
At the pre-work meeting provide a proposed schedule of work showing dates of major work items. Also incorporated into this contract is FAR 52.236-15, Schedules for Construction Contracts.
H.9 DAMAGE TO STRUCTURES
The Contractor shall be held liable and responsible for any damage caused by his/her personnel or equipment to any existing trails, pavement, culverts, utility lines and related equipment, etc. Repair damaged structures at no
10 | P a g e cost to the Government.
H.10 DISPOSAL SITE
The contractor will remove all waste material from the project area and dispose at an approved location off of National Forest Land.
H.11 TRAFFIC CONTROL
The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
The Contractor shall furnish, erect, maintain, and remove when notified any project identification signs shown on the drawings.
11 | P a g e
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of
Whistleblower Rights (APR 2014) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUL 2013) 52.204-13 System for Award Management Maintenance (JUL 2013) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (AUG 2013) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (JUL 2013) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (OCT 2010) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-8 Utilization of Small Business Concerns (OCT 2014) 52.219-14 Limitations on Subcontracting (NOV 2011) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2014) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) http://www.usda.gov/procurement/policy/agar.html
12 | P a g e
52.222-35 Equal Opportunity for Veterans (JUL 2014) 52.222-36 Affirmative Action for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (JUL 2014) 52.222-40 Notification of Employee Rights under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (FEB 2009) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts (SEP
2013) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-1 Bid Guarantee (SEP 1996) fill in: 20% or $3 million whichever is less 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds – Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (MAY 2014) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR
1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)
Alternate I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984)
Alternate I (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007)
13 | P a g e
52.244-6 Subcontracts for Commercial Items (OCT 2014) 52.245-1 Government Property (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2010) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--Alternate I (SEP
1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
I.2 FAR 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)
(a) Definitions. As used in this clause—
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph
(g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and https://www.acquisition.gov/far/current/html/52_217_221.html#wp1135887
14 | P a g e
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall re-represent its size status in accordance with the size standard in effect at the time of this re-representation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the re-representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its data in SAM, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following re-representation and submit it to the contracting office, along with the contract number and the date on which the re-representation was completed:
The Contractor represents that it is, is not a small business concern under NAICS Code 237310 assigned to contract number AG-0109-S-16-00xx.
I.5 FAR 52.225-9 Buy American -Construction Materials (MAY 2014)
(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means—
(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and http://www.sba.gov/content/table-small-business-size-standards https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/
15 | P a g e any applicable duty (whether or not a duty-free entry certificate is issued); or
(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: none
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) ) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) ) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) ) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the
Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute http://uscode.house.gov/ https://acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123
16 | P a g e applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON
Construction Material Description Unit of Measure Quantity Price (Dollars)*
Item 1:
Foreign construction material Domestic construction material
Item 2:
Foreign construction material
Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
I.6 FAR 52.225-11 Buy American—Construction Materials under Trade Agreements (MAY 2014)
(a) Definitions. As used in this clause— “Caribbean Basin country construction material” means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the
Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508
17 | P a g e
“Cost of components” means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Designated country” means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement country (Armenia, Aruba, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, or United Kingdom);
(2) A Free Trade Agreement country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St.
Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
“Designated country construction…