This document is a Technical Specifications file for a Pilot-Scale Direct-Fired Cement Kiln System being procured by the National Laboratory of the Rockies (NLR) for installation at the Flatirons Campus.
The system must produce ASTM C150 and ASTM C595 cement at pilot scale, achieving up to 100 kg/hr of clinker through four to ten annual weeklong campaigns. Key equipment requirements include a direct-fired horizontal rotary kiln with 15-24 inch internal diameter and 15-30 foot length, capable of 1,600°C maximum operating temperature controllable from 600-1,600°C, with adjustable slope (1-5 degrees) and rotational speed (0.5-5 rpm). The system must include a natural gas burner with 10:1 turndown, flexible mounting to accommodate future hydrogen or plasma burners, an air-cooled clinker cooler reducing clinker to ≤100°C, a ball mill grinding raw materials at 200 kg/hr and finished clinker to <50 µm at 100 kg/hr, and comprehensive environmental controls (cyclonic collector, baghouse, afterburner). The control system requires an industrial PLC with touchscreen HMI, unlocked source code, 1 Hz data logging with 90-day on-board storage in CSV format, OPC UA and Modbus TCP interfaces, and NFPA 86 compliant safety management. The system must include a high-temperature infrared thermal camera (600-1,800°C range, ±1% accuracy, 30 Hz minimum frame rate) with separate visible-light camera, radiometric data export capability, and future spectral filter for alternative burners.
The subcontractor must deliver the complete integrated system within 52 weeks of award with commissioning complete by 58 weeks, with key milestones including 50% design at 12 weeks, 100% design at 24 weeks, and factory acceptance at 46 weeks. The system will be installed in an existing covered pavilion at the Flatirons Campus on a single level at grade with stairs to an elevated feed platform. All electrical equipment must be NRTL-listed, comply with NFPA 70, 79, 86, and 54, and use 480V 3-phase 60Hz power. The subcontractor must provide predicted emissions data (PM, NOx, CO, SO₂, VOC, CO₂), equipment datasheets for the Colorado air permit, and address hazards including combustion, high-temperature, rotating equipment, dust, falls, and future hydrogen exposure.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Statement of Work.pdf | ||
| Attachment 3 - Sample Subcontract Schedule - Firm Fixed Price.pdf | ||
| Attachment 4 - Proposed Payment Schedule.xlsx | XLSX spreadsheet | |
| NLR Request For Proposal No. AFQ-2027-00113.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OCFO-AS-4164 Technical Specifications 12/18/2025
3.1.1 Design basis. The Subcontractor shall document the heat and material balance, bed depth, and residence time. The kiln shall allow residence time to be adjusted over a range that includes 30 to 60 minutes at the design feed rate.
3.1.2 Production rate. The kiln shall produce clinker at a sustained 100 kg/hr (design maximum) and shall run stably at turndown to 25 kg/hr.
3.1.3 Shell and drive. The kiln shall be a refractory-lined steel shell on riding rings and support rollers, with thrust rollers to control axial movement and end seals that limit air in-leakage.
The main drive shall be driven by a variable frequency drive (VFD) and shall provide a speed range of at least 0.5 to 5 rpm. An auxiliary drive shall keep the kiln rotating slowly during cool-down or loss of main power.
3.1.4 Slope. The slope shall be adjustable over at least 1 to 5 degrees from horizontal, with position indication and a locking feature. Adjustment shall be possible between production campaigns. The Subcontractor shall state whether adjustment while hot and rotating is included or offered as an option.
3.1.5 Refractory. The lining shall be rated for continuous service at 1,600 °C and shall be chemically compatible with Portland cement clinker in the burning zone. The refractory should be high-alumina brick (60-75%+ alumina) or magnesia-based. The Subcontractor shall supply the manufacturer’s dry-out and heat-up schedule.
3.1.6 Hood. The stationary firing hood shall be refractory lined and rated for a maximum temperature of 3,000 °C. It shall include the burner port, a clinker discharge opening to the cooler, an access door, a view port for the thermal camera, and a pressure relief.
3.1.7 Initial burner. The initial natural gas burner shall use ambient combustion air from a blower, with spark ignition and flame supervision, a turndown of at least 10:1, adjustable flame shape, and oxygen trim. The Subcontractor shall size the burner to meet the 100 kg/hr clinker rate at 1,600 °C including heat losses and shall report the rated firing rate.
3.1.8 Flexible burner mounting. The burner shall be mounted on a standard mounting plate and retractable carriage or rail so it can be withdrawn and replaced without disassembling the hood or modifying the kiln. The mounting shall allow a hydrogen burner or direct plasma burner to be installed later. The Subcontractor shall provide a Burner Interface
Control Document stating the port size, flange and bolt pattern, maximum burner weight and moment, and the removal method. The burner station shall include capped spare connections for fuel gas, combustion air, cooling medium, high-current power, and control wiring, and spare PLC I/O. Burner-specific control logic shall be modular so it can be replaced without changing the kiln drive and general interlocks. The materials and layout shall not prevent later hydrogen service.
3.1.9 Access and sampling. The kiln shall have inspection ports and a safe means of taking clinker samples at the discharge during operation.
3.1.10 Layout. The kiln, hood, burner, and cooler discharge shall sit on a single level at grade.
Feed shall be supplied from an elevated platform reached by stairs with landings and guardrails (not ladders).
3.2 Cement Kiln Feed
The kiln shall be fed using a screw feeder and hopper that supply raw meal to the kiln feed end at a controlled, repeatable rate.
3.2.1 Feed rate. The feeder shall be variable speed and shall deliver raw meal from 0 to at least
170 kg/hr, to support 100 kg/hr of clinker.
3.2.2 Accuracy. The feeder shall be gravimetric (loss-in-weight) with an accuracy of ±2% of setpoint, and shall log the feed rate and total mass.
3.2.3 Hopper. The hopper shall hold at least 0.75 m³, with a dust-tight lid, high and low level sensors, and an anti-bridging device suited to fine, cohesive powders.
3.2.4 Loading. The feed platform and stairs shall be sized for two people and for loading with bulk bags using a hoist or davit, and shall meet OSHA requirements for stairs, guardrails, and live load.
3.2.5 Feed tube. The feed tube into the kiln shall be rated for the kiln back-end gas temperature and shall limit air in-leakage. The feed system shall be vented to the dust collection system.
3.2.6 Feed material. The feed system shall handle ground raw meal with a bulk density of 0.8 to
1.4 g/cm³.
3.3 Cement Kiln Controls and Thermal Monitoring
3.3.1 Control system. The system shall use an industrial PLC with a touchscreen HMI at the local panel and an operator workstation. The Subcontractor shall deliver unlocked source code, and the system shall not depend on proprietary licenses that restrict NLR from modifying the program.
3.3.2 Control functions. The controls shall command and monitor kiln speed, slope position, feed rate, burner firing rate and air-fuel ratio, induced draft fan speed and draft setpoint, cooler air, baghouse cleaning, afterburner temperature, and the mill. The controls shall include automatic start-up (with a rate-limited refractory heat-up ramp), shutdown, and manual modes.
3.3.3 Safety. The burner management systems for the kiln burner and the afterburner shall meet
NFPA 86, with purge, flame supervision, and safety shutoff valves. The system shall include emergency stops and interlocks for loss of kiln rotation, loss of combustion air, high and low gas pressure, flame failure, loss of draft, high baghouse inlet temperature, high shell temperature, and mill overload, each driving to a defined safe state. The
Subcontractor shall provide a cause-and-effect matrix.
3.3.4 Data and interfaces. The system shall log all measurements, setpoints, and alarms at 1
Hz or faster, store at least 90 days on board, and export in CSV. The system shall expose all tags through OPC UA and Modbus TCP over Ethernet. A key-enabled external control mode shall allow an NLR-approved external controller to write setpoints; the safety functions shall remain independent and shall not be overridable from that interface. The control network shall be separated from the NLR network, with no direct internet connection and no vendor remote access without NLR approval.
Process instrumentation
3.3.5 Temperature. Infrared shell temperature measurement at not fewer than five axial locations on the kiln; gas temperature at the kiln feed end, hood, cooler outlet, cooler exhaust, baghouse inlet, and afterburner; and clinker temperature at the cooler outlet.
3.3.6 Pressure and flow. Draft at the hood and kiln feed end; baghouse differential pressure;
natural gas flow (with totalizer, accuracy ±1% of reading) for the kiln burner and the afterburner; combustion air flow; and total exhaust flow.
development kit or API so NLR can read raw radiometric frames for model verification and control research. There shall be no recurring license fees.
3.3.12 Housing and protection. The camera shall be in a stainless steel, IP66 (NEMA 4X) air-cooled housing with a replaceable sapphire or fused silica window that has an anti-reflective coating for the selected band. The housing shall include an air purge using filtered, dry instrument air. The camera shall be on a fail-safe retraction mechanism or shutter that withdraws on loss of purge or cooling air, or on high housing temperature, and shall send an alarm to the PLC. No process water shall be required.
3.3.13 Mounting. The camera shall be rigidly mounted on the stationary hood, isolated from kiln vibration, with adjustable aiming of at least ±10 degrees in pan and tilt. The mount and sight line shall be independent of the burner mounting, so the camera is unaffected when the burner is removed or replaced. The camera shall be serviceable from the platform or floor without removing the burner.
3.3.14 Future burners. The Subcontractor shall supply a second interchangeable spectral filter, selected for use with hydrogen and direct plasma burners, whose flame and arc emissions differ from natural gas flames, and shall state the camera settings changes needed.
3.3.15 Calibration and verification. The camera shall be delivered with a calibration certificate traceable to NIST, with a blackbody calibration at not fewer than three temperatures across the range, and a recommended recalibration interval of no more than 12 months. Long-term drift shall not exceed 1% of reading per year. During the factory acceptance test, the
Subcontractor shall verify the camera against a blackbody source at not fewer than two temperatures. During the site acceptance test, the Subcontractor shall compare the camera reading against a hood gas thermocouple and record the result.
3.3.16 Visible-light camera. A separate visible-light video camera shall view the flame and the clinker discharge, with recording stored alongside the thermal images.
3.4 Clinker Cooling
3.4.1 Cooler. An air-cooled clinker cooler shall sit adjacent to the discharge chute and receive all clinker by gravity through a chute rated for clinker at up to 1,450 °C. The Subcontractor shall propose the cooler type (for example grate, rotary, or planetary).
3.4.2 Performance. At 100 kg/hr, the cooler shall reduce clinker to no more than 100 °C at the outlet. Cooling air flow shall be variable with a VFD fan, so the clinker cooling rate can be varied for research.
3.4.3 Clinker size. The cooler shall handle clinker nodules up to 25 mm and fines and dust.
3.4.4 Exhaust. Cooler exhaust shall be ducted to the environmental control train. Using cooler exhaust as preheated combustion air shall be offered as a separately priced option; the base design uses ambient air.
3.4.5 Instrumentation and discharge. The cooler shall measure clinker outlet temperature, cooling air flow and temperature, and exhaust temperature. The discharge shall be dust-tight and interface with 55-gallon drums or 1 cubic yard bulk bags, with a sample port. NLR will transfer cooled clinker to the mill in containers unless the Subcontractor includes an enclosed conveyor.
3.5 Raw Feed and Clinker Grinding
Ability to grind raw material at 200 kg/hr and to grind finished clinker to less than 50 µm at 100 kg/hr.
3.5.1 Ball mill. One ball mill shall be used for initial raw material grinding and for final clinker grinding. If the Subcontractor demonstrates that one mill cannot meet both duties, the
Subcontractor may propose two mills with justification and cost.
3.5.2 Raw grinding. The ball mill, with an air classifier, shall grind raw materials at 200 kg/hr to a raw meal with no more than 12% retained on a 90 µm sieve and no more than 2% retained on a 212 µm sieve.
3.5.3 Air classifier. A dynamic air classifier shall be installed in closed circuit with the mill for the raw material circuit, with an adjustable cut point and oversize returned to the mill.
3.5.4 Clinker grinding. The ball mill shall grind clinker at 100 kg/hr to a d90 of less than 50 µm by laser diffraction, and shall be capable of a Blaine fineness (ASTM C204) of at least 400 m²/kg.
3.5.5 Feed materials. The mill shall process limestone, clay or shale, sand, iron source, and alternative raw materials with a Bond work index up to 18 kWh per short ton. NLR will supply raw materials pre-crushed to no more than 12 mm and clinker nodules up to 25 mm.
3.5.6 Mill design. The mill shall have wear-resistant liners, an initial grinding media charge with a graded media list, a VFD drive, discharge temperature measurement, an air sweep or ventilation, power measurement, and sampling ports.
3.5.7 Additive feeder. A metering feeder shall add calcium sulfate or limestone during finish grinding at an adjustable 0 to 15% by mass.
3.5.8 Changeover. The mill, classifier, and transfer lines shall have clean-out access, and the
Subcontractor shall provide a cleaning procedure that limits cross-contamination.
Changeover between raw and clinker duty shall not take more than one 8-hour shift.
3.5.9 Dust and noise. The mill, classifier, and transfer points shall be sealed and vented to the dust collection system, and noise shall not exceed 85 dBA at 1 m.
3.6 Environmental Controls
3.6.1 Train. Kiln exhaust shall pass through gas conditioning, a cyclonic dust collector, a baghouse, and an afterburner, with an induced draft fan and stack. Cooler exhaust shall join the train ahead of the cyclone. Mill, classifier, and feed vents shall connect to the baghouse or a dedicated vent filter.
3.6.2 Gas conditioning. The system shall cool the gas to a temperature safe for the filter media, using dilution air or a heat exchanger, with an emergency dilution damper on high inlet temperature.
3.6.3 Cyclone. The cyclonic dust collector shall have sealed discharge into drums, with the option to return dust to the kiln feed.
3.6.4 Baghouse. The baghouse shall be a pulse-jet type with high-temperature filter media compatible with the gas composition and acid dew point, insulated or heat-traced hoppers with rotary airlocks, and automatic cleaning. Outlet particulate shall not exceed 0.005 gr/dscf (grains of particular matter per dry standard cubic foot of exhaust air).
3.6.5 Afterburner. A natural gas-fired afterburner downstream of the baghouse shall destroy at least 98% of CO and VOCs, at a minimum of 760 °C with at least 0.5 s residence time, with its own NFPA 86 burner management system integrated with the PLC.
3.6.6 Induced draft fan. The fan shall be VFD-controlled to hold kiln draft at a slight negative pressure and shall be sized for the design flow plus 25% margin.
3.6.7 Stack and sampling. The stack shall have sampling ports and a platform for EPA
Methods 1 through 4 (40 CFR Part 60, Appendix A) and ports for future continuous emissions monitors. The Subcontractor shall recommend the stack height.
3.6.8 Emissions data. The Subcontractor shall provide predicted emissions at the design rate
(PM, NOₓ, CO, SO₂, VOC, CO₂) and equipment data sheets to support NLR’s Colorado air permit. NLR is responsible for the permit application.
TECHNICAL OR SAFETY REQUIREMENTS
Technical and safety requirements
• NRTL compliance: All electrical equipment and control panels shall be NRTL listed (for example UL 508A for panels) or shall receive an NRTL field evaluation before commissioning. The system shall comply with NFPA 70, NFPA 79, NFPA 86, and NFPA 54, as applicable. NLR Research Equipment Standards may be applied instead; to customize them, NLR will email
• Guarding and hazards: Rotating equipment shall be guarded and accessible surfaces shall be no hotter than 60 °C or shall be guarded. Lockout/tagout energy isolation points shall be provided. The design shall address respirable dust and silica exposure, CO, noise, and fall hazards.
• Utilities: The system shall use 480 V, 3-phase, 60 Hz AC power from NLR’s on-site service, with the Subcontractor providing any transformers for other voltages. NLR will confirm available service capacity and natural gas pressure and capacity at the kickoff meeting. The
Subcontractor shall provide any gas booster or regulator and a self-contained compressed air system (compressor and dryer) unless NLR confirms plant air is available. No process water shall be required.
Space requirements / limitations
• Covered/uncovered: Covered. The system will be installed in the existing covered pavilion at the Flatirons Campus.
• New space: No new space is needed. The Subcontractor shall give weights, dimensions, and loads for the foundation in the 50% design package. NLR will confirm pavilion dimensions and slab loading at the kickoff meeting.
• NLR Site Ops assistance: Yes. NLR Site Ops will support electrical service, natural gas connection to the agreed point of connection, and foundation or pad preparation. The
Subcontractor shall give the electrical, natural gas, and civil requirements in the 50% design package.
• Advanced computing resources: No. The system needs an Ethernet connection for research data acquisition as described in 3.3.4.
TIMELINE
• Key milestones after award: kickoff within 30 calendar days; 50% design at 12 weeks;
initial bill of materials at 16 weeks; 100% design at 24 weeks; factory acceptance at 46 weeks.
• Delivery needed by: 52 weeks after subcontract award, with commissioning complete within
58 weeks after award. Lead time is an evaluation factor.
TM RESOURCES
• ES&H POC – required safety/electronic specs:
• New hazards: Yes. This project introduces combustion, high-temperature, rotating equipment, dust, fall, and (for the future burner) hydrogen hazards. NLR will ensure they are mitigated through the Subcontractor’s hazard analysis and NLR ES&H review before operation.
• ROD/ROMs:
• Directorate’s Engineering Team:
File details come from the government source that posted it. Updated .