Attachment 1 - Statement of Work.pdf
PDF 556 KB Posted
- Attached to
- Pilot-Scale Direct-Fired Cement Kiln System
- Solicitation number
- AFQ-2027-00113
- Issued by
-
Department of Energy Office of Science
About this file
This is a Statement of Work (SOW) for the design, build, test, delivery, and commissioning of a pilot-scale direct-fired cement kiln system at the National Laboratory of the Rockies (NLR), a U.S. Department of Energy national laboratory located in Arvada, Colorado.
The subcontractor must design and construct a horizontal rotating cement kiln with an inside diameter of 15 to 24 inches and length of 15 to 30 feet, capable of operating from 600°C to 1600°C and producing up to 100 kg/hr of ASTM C150 or C595 cement clinker. The system includes associated components: a hopper and screw feeder, natural gas-fired kiln with adjustable slope and rotational speed, air-cooled clinker cooler, ball mill for raw material and clinker grinding with air classifier, and environmental controls consisting of a cyclonic dust collector, baghouse, and afterburner. The kiln burner mounting must be removable and swappable to accommodate future hydrogen or direct plasma burners. The subcontractor shall complete design reviews at 50% and 100% design stages, obtain NLR approval before fabrication, conduct a Factory Acceptance Test (FAT) with punch list resolution, deliver equipment to the Flatirons Campus, and perform on-site commissioning including a Site Acceptance Test (SAT) demonstrating eight consecutive hours of operation at 1600°C and clinker production at 100 kg/hr. The subcontractor must also provide operator training for at least 16 hours, a two-year recommended spare parts list, and a 12-month warranty covering parts and labor.
The period of performance is 72 weeks from subcontract execution. Key deliverables include design packages, bill of materials with monthly updates, FAT and SAT reports, operational documentation (manuals, as-built drawings, PLC/HMI source files, and equipment control documents), and a final technical report. The subcontractor must submit deliverables in PDF format with supporting native files and comply with electronic reporting standards, copyright permissions, and model releases for any photographs or images. All data first produced during performance must be provided to NLR as a condition of final payment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OCFO-AS-4133 SOW - Deliverable Based 3/16/2026
The anticipated process flow and desired equipment capabilities include: grinding of the raw materials to the required particle size and homogeneity in a ball mill with an air classifier; screw-driven kiln feed; a natural gas-fired kiln with adjustable temperature, slope, and rotational speed, including drive motors, air feed blowers, a thermal camera, and controls to produce cement clinker;
an air-cooled clinker cooler adjacent to the discharge chute; and finish grinding of the clinker.
Environmental controls shall consist of a cyclonic dust collector followed by a baghouse and an afterburner. Final grinding of the clinker may be performed using the same ball mill used for initial raw material grinding, if the Subcontractor demonstrates that it meets the requirements for both duties.
3. SCOPE OF WORK
To meet the objective, the Subcontractor shall design a system that integrates with NLR’s existing infrastructure, namely the covered pavilion and the on-site AC power and natural gas supply. The kiln, firing hood, and cooler shall sit on a single level at grade, with stairs to an elevated platform for supplying feed.
The Subcontractor shall design, build, test, deliver, and commission the system. NLR will hold a high-level design review with the Subcontractor, a bill of materials review, a final design review, and a factory acceptance review ahead of system delivery and commissioning by the Subcontractor.
The Subcontractor shall provide final operational documentation for the system.
The following lists the features of the direct-fired horizontal rotating cement kiln and ancillary components. The Technical Specifications document gives the detailed requirements for each item, and the Technical Specifications govern if a summary below differs.
3.1 Cement Kiln. Natural gas-fired rotary kiln, 15-inch to 24-inch inside diameter and 15-feet to
30-feet long, operating from 600 °C to a maximum of 1600 °C, with adjustable slope and rotational speed, a firing hood rated to a maximum temperature of 3000 °C, and a removable, swappable burner mounting for future hydrogen or direct plasma burners. Final clinker production rate of up to 100 kg/hr.
3.2 Cement Kiln Feed. Hopper and screw feeder, supplied from an elevated platform reached by stairs.
3.3 Cement Kiln Controls and Thermal Monitoring. Control system, burner management system, process instrumentation, data acquisition, and a thermal camera.
3.4 Clinker Cooling. Air-cooled clinker cooler adjacent to the kiln discharge chute.
3.5 Raw Feed and Clinker Grinding. Ball mill for initial raw material grinding and final clinker grinding, with an air classifier for the raw material circuit.
3.6 Environmental Controls. Cyclonic dust collector feeding a baghouse, followed by an afterburner and stack.
4. TASKS
4.1 Design
The Subcontractor shall be responsible for identifying all components necessary to integrate, fabricate, and assemble the pilot cement kiln system. This includes the electronic hardware and software modules necessary for the controls interface, for monitoring production, and for safe operation of the equipment. The Subcontractor shall:
• Confirm the site interface data (pavilion dimensions, slab loading, electrical service, natural gas supply pressure and capacity) with NLR at the kickoff meeting.
• Select the kiln inside diameter and length within the ranges in the Technical Specifications and document the design basis, including heat and material balance, residence time, bed depth, burner firing rate, and gas flows.
• Prepare a process flow diagram, piping and instrumentation diagrams (P&IDs), a general arrangement (plan and elevation) drawing, an electrical one-line diagram, a control system architecture and I/O list, a sequence of operations, a utility load list (electrical, natural gas, compressed air), and foundation and platform loading data.
• Prepare a Burner Interface Control Document that defines the burner port size, mounting flange and bolt pattern, maximum burner weight, the removal and installation method, and the utility and control provisions for natural gas, with considerations for future hydrogen and direct plasma burners.
• Perform a hazard analysis (HAZOP or equivalent) covering combustion, high temperature, rotating equipment, dust, and fall hazards, and identify the mitigations built into the design.
• Estimate emissions at the design production rate (particulate matter, NOx, CO, SO2, VOC, CO2) to support NLR’s air permit application.
• Submit a 50% design package for the high-level design review and a 100% design package for the final design review. NLR will provide written comments within ten (10) business days after receipt of each package. The Subcontractor shall respond in writing to every comment within ten (10) business days.
• Not begin fabrication until NLR has approved the 100% design package in writing. NLR may approve the early purchase of long-lead items after the bill of materials review.
4.2 Build/Acquire Equipment
The Subcontractor shall be responsible for procuring all components necessary to integrate, fabricate, and assemble the pilot cement kiln system. This includes the electronic hardware and software modules necessary for the controls interface, for monitoring production, and for safe operation of the equipment. The Subcontractor shall:
• Submit an initial bill of materials listing each major component by manufacturer, model, quantity, specification, and lead time, for NLR’s bill of materials review.
• Update the bill of materials monthly with procurement and fabrication status until delivery.
• Obtain NLR’s written approval before substituting any component that changes a requirement in the Technical Specifications.
• Fabricate the equipment in accordance with the approved 100% design and maintain quality records (material test reports, weld procedures and welder qualifications, refractory lot certificates, and instrument calibration certificates) for NLR review.
4.3 Factory Test/Fit Up of Equipment
The Subcontractor shall pre-assemble and test the equipment at the Subcontractor’s or fabricator’s facility before shipment. The Subcontractor shall:
• Submit a Factory Acceptance Test (FAT) plan to NLR at least thirty (30) calendar days before the FAT. The plan shall list each test, the acceptance criterion, and the test method.
• Fit up the kiln shell, drive, support rollers, slope adjustment, hood, burner mounting, feed system, cooler, mill, classifier, and control panels to verify dimensions and interfaces.
• Demonstrate the kiln rotational speed range, slope range, auxiliary drive operation, feed screw calibration, mill and classifier operation on a surrogate material, control loop and I/O checkout, safety interlocks and burner management system functions, data interface to an
NLR-supplied client, and thermal camera operation.
• Demonstrate removal and reinstallation of the burner assembly using the burner mounting system.
• Host the FAT on-site for NLR witnesses, with a virtual option, and record all deviations on a punch list.
• Correct all punch list items that affect safety or performance before shipment. NLR will give written release to ship.
4.4 Delivery of Equipment
The Subcontractor shall package, ship, insure, and deliver the equipment to NLR’s Flatirons
Campus, 19001 W 119th Ave, Arvada, CO 80007. The Subcontractor shall:
• Give NLR at least fourteen (14) calendar days of notice before each shipment, with a packing list and a transport and rigging plan.
• Inspect the equipment with NLR on arrival and document any shipping damage. The
Subcontractor shall repair or replace damaged items at no additional cost to NLR.
NLR will prepare the foundation or pad to the loads in the approved design and will provide electrical service and natural gas to a point of connection agreed at the kickoff meeting. The Subcontractor shall make all connections downstream of that point.
4.5 Commissioning of Equipment
The Subcontractor shall install, commission, and demonstrate the system on-site at the Flatirons
Campus. The Subcontractor shall:
• Assemble the equipment, complete mechanical, piping, electrical, and ducting connections, and perform pre-startup safety checks, instrument calibration, and loop checks.
• Dry out and cure the refractory using the manufacturer’s heat-up schedule, then perform initial firing, burner tuning, and control loop tuning.
• Perform a Site Acceptance Test (SAT) in which the system, using raw materials approved by
NLR, (a) operates the kiln at 1600 °C for at least eight (8) consecutive hours; (b) produces clinker at 100 kg/hr for at least eight (8) consecutive hours; (c) cools the clinker to the temperature stated in the Technical Specifications; (d) grinds the clinker to less than 50 µm at 100 kg/hr; and (e) operates the cyclone, baghouse, and afterburner throughout. NLR will test the clinker free lime content and the Subcontractor shall meet the limit in the Technical
Specifications.
• Demonstrate removal and reinstallation of the burner assembly at the kiln.
• Train NLR operators and maintenance staff for at least sixteen (16) hours on operation, maintenance, safety, the control system, data interface, and the burner swap procedure.
• Provide a recommended spare parts list for two (2) years of operation and a warranty covering parts and labor for at least twelve (12) months from NLR’s written acceptance.
The system is accepted when NLR signs a written acceptance after a successful SAT.
4.6 Operational Documentation
The Subcontractor shall provide complete operational documentation in electronic form (PDF plus native files). The documentation shall include:
One (1) master electronic version, including graphics.
Deliverable 6.11 (Equipment Delivery) shall be delivered to NLR’s Flatirons Campus, 19001 W 119th
Ave, Arvada, CO 80007, as described in Task 4.4. All other deliverables shall be sent electronically.
7. DELIVERY OF DATA
A copy of all data (as that term is defined in this Subcontract) first produced in the performance of this Subcontract is an additional deliverable of this Subcontract and shall be provided to the technical monitor as a condition of final payment, in accordance with the Subcontract. For all deliverables, make particular note of the requirements provided in the Rights in Data clause of this Subcontract regarding data not first produced in the performance of this Subcontract.
8. ELECTRONIC REPORTING REQUIREMENTS FOR SUBCONTRACT REPORT
DELIVERABLES
It is NLR’s intention to publish subcontract report deliverables containing publicly available information (e.g. non-confidential, non-protected, non-proprietary information) for distribution on the internet.
The subcontractor shall provide the final approved version of report deliverables in accordance with the electronic reporting requirements described below.
The technical monitor may specifically direct the subcontractor to provide reports in one or more of the file format standards provided below:
• The subcontractor shall submit all report deliverables (including status, annual, or final reports) as electronic files in Adobe .pdf format, preferably with all graphics and images embedded within the document.
• All final approved version submissions shall be delivered to NLR via e-mail to the NLR
Technical Monitor.
• If it is not possible to include all of the graphics and images (figures, illustrations, and photographs) in the same file as the text, NLR will accept the text in Adobe .pdf formats and the graphics and images as separate electronic graphic or image files*.
• The accepted standard for page layout and graphics is the Adobe Creative Suite of programs.
• *The acceptable graphic or image file formats are: .eps, .tif, .gif, .jpg, .wmf, .emf, .pct, .png, .bmp, .psd, .ai, .fh, .qif, .fpx, cdr. The preferred resolution for graphics or images is 300 dpi.
Include all fonts used in creating the file.
• For animation, video, or multi-media elements, CD-ROM, DVR and thumb drive are acceptable technical deliverable media.
• For all calculations in support of subcontract reports that are conducted in ASPEN+, an electronic copy of INPUT, REPORT and BACKUP (if Model Manager is used) must be submitted with all reports. Additionally, if costing or sizing calculations are conducted in a spreadsheet [no process calculations (heat and material balances) in spreadsheet format are permitted], a copy of the fully documented MS Excel file shall be supplied.
• A fully executed model release shall be supplied to NLR with all photographs and images, regardless of whether such photographs or images are delivered to NLR electronically or in hard copy. Such model release shall certify that the Alliance for Energy Innovation, LLC, Management and Operating Contractor for the National Laboratory of the Rockies for the
U.S. Department of Energy is granted a non-exclusive, paid-up, irrevocable, worldwide license to publish such photographs in any medium or reproduce such photographs or allow others to do so for United States Government purposes. Model releases are required in all situations in which a reasonable person would respond in the affirmative to the question – could someone, other than the model himself/herself, recognize the person in this photograph or image? All model releases shall be provided to the subcontract associate as a condition of final payment, in accordance with the subcontract. To obtain a Subcontractor
Model Release form, please contact images@NLR.gov
9. ACKNOWLEDGEMENTS IN SUBCONTRACTOR PUBLICATIONS
In any scientific or technical report or article, conference paper, journal article, etc. based on or containing data first produced in the performance of this subcontract and published in academic, technical or professional journals, symposia proceedings or similar works, the subcontractor shall use this acknowledgement stating, “This [article, conference paper, journal article, etc.] was developed based upon funding from the National Laboratory of the Rockies for the U.S. Department of Energy under Contract No. DE-AC36-08GO28308.”
10. COPYRIGHT PERMISSION/AUTHORIZATIONS
The subcontractor is responsible for obtaining copyright permission and/or authorization for all information and/or data, as applicable, that is incorporated into all final technical reports. Electronic copies of these copyright permissions and/or authorizations shall be provided to the at the email address provided below. The subcontractor shall also provide a written certification to the Technical
Monitor as to such permissions and/or authorizations as a condition of final payment. The subcontractor’s (including all lower tier subcontractors, as applicable) certification shall specify that “I have obtained all necessary and legally required copyright permissions and/or authorizations for any and all information, data, graphs, images, etc., as applicable, that is incorporated into the final
Technical Report titled __________________________, delivered under this Subcontract
No.__________. Copies of these permissions and/or authorizations are attached.”