This is an addendum to construction drawings for the Administration Building Lobby Renovation project by Fraser Public Schools, issued on March 4, 2020. The project encompasses comprehensive renovation of the lobby and stair areas, including installation of new luxury vinyl tile (LVT) flooring with vinyl cove base throughout the lobby, new gypsum board wall surfaces with full-height painting, and painting of existing 12x12 acoustic tile ceilings. The scope includes installation of two new 3-foot by 7-foot flush wood solid core doors with hardware (closers, hinges, classroom locksets with lever handles, wall stops, and kick plates), one door with laminated glass sidelite and the other with SG4 security glass sidelite. Additional work includes new rubber vinyl cove base, stair treads, risers, nosings, and landing surfaces on existing stairs from the first floor to lower level; a new surface-mounted LED light fixture with two lamps to be connected to existing circuits; new SG4 security glass with specified dimensions and voice holes in a new HM window frame; and new wood casing around door frames stained to match. Owner-supplied items include new acrylic signage, extension of electrical outlet and switch boxes, installation of a police emergency button connected to the district security system, removal and reinstallation of an existing wall-mounted security camera, and verification of paint colors and electrical quantities.

The addendum provides detailed specifications and numbered work items with corresponding reference notations on the architectural drawings (referenced as Drawing No. A-1.3 for painting extent and Detail No.1/A-1.4 for window specifications). Field verification is required prior to ordering new door and window frames to ensure proper opening dimensions. The document establishes construction standards for materials, finishes, and installation methods, with owner responsibilities clearly delineated for certain tasks including electrical work modifications, security system connections, and fixture installation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BJS

BJS

03-03-2020

A-1.2

Fraser Public Schools Administration Building Lobby Renovation

OFFICE

STAIR

HALLWAY

OFFICE

LOBBY

NEW WORK NOTES:

1. New LVT floor tile and new 4" vinyl cove base in entire room.

2. New 3-0x7-0 flush wood solid core door (stain) in new HM frame (paint) with 1/4" laminated glass sidelite. Verify frame opening in field prior to ordering new frame. Hardware to be: closer, hinges, Classroom Lockset with lever handle, wall stop and kick plate.

3. New vinyl reducer strip at LVT/carpet edge.

4. Apply new 3/8" gypsum board over all wall surfaces full ht. then Paint all walls in room full ht.

5. Paint existing 12x12 acoustic tile ceiling.

6. Fill in hole in ceiling tile prior to painting.

7. Owner to provide & install New 1x4 surface mounted, 2 lamp, LED light fixture, connect to existing circuits and switching.

8. Existing supply air diffuser to remain. (Clean and Paint)

9. New acrylic signage surface mounted to exterior wall. (By owner)

10. Paint existing frames and walls full ht to match adjacent color. Verify color with owner.

11. New Rubber 4" vinyl cove base, stair treads, risers, nosings and landing surface on all existing stairs from first floor to lower level.

12. New 3-0x7-0 flush wood solid core door (stain) in new HM frame (paint) with SG4 security glass in sidelite. Verify frame opening in field prior to ordering new frame. Hardware to be: closer, hinges, Classroom Lockset with lever handle, wall stop and kick plate.

13. New SG4 security glass with 2"x14" slot on bottom and 1/2" dia. voice holes in 8" dia. circular pattern in new HM window frame (paint). Frame size to be +/- 34"Wx33"H (V.I.F.) See Detail No.1/A-1.4

14. Cut new base to stop/start each side of existing plastic corner guard for new base work.

15. Cut new flooring around existing floor register.

16. Owner to Extend existing light switch boxes and receptacle boxes as required to be flush with new wall surface. Verify quantities and sizes in room.

17. Existing wall mounted security camera to be removed and reinstalled by Owner.

18. Owner to install New Police Emergency button on wall. Connect to existing District security system.

19. Patch walls after frame removal and paint to match existing colors.

20. Provide new wood casing on both side and all around new HM frame. Stain to match new doors.

201865

See Drawing No.A-1.3 for extent of painting