Administration Building Lobby Renovation Addendum No. 1 Drawings_March 4, 2020.pdf
PDF 493 KB Posted
- Attached to
- Administration Building Lobby Renovation
- Solicitation number
- RFP FRA 200000001149 3
- Issued by
- Macomb County, Michigan
About this file
This is an Addendum No. 1 to the Administration Building Lobby Renovation project for Fraser Public Schools, containing demolition notes and architectural drawings dated March 4, 2020. The project scope includes removal of existing interior finishes and fixtures in the lobby and hallway areas to prepare for renovation work. Specific demolition items include removal of an existing wood door with hardware, HM frame, and wire glass; surface-mounted light fixtures (with circuits and switching to be reused); sliding glass panels and wood trim; 12x12 vinyl tile flooring and 4-inch cove base; rubber stair treads, risers, and cove base on all stairs and landing from the first floor to lower level; metal threshold; and vinyl reducer strip at carpet edge. The existing floor register and light circuits are noted to remain and be reused for new installation.
The addendum provides architectural drawings and detailed demolition notes to guide contractor work, with notations indicating the document was prepared on March 3, 2020. No pricing, bidding timeline, due dates, or contract terms are specified in this addendum document, as it functions solely as a supplemental drawing and demolition specification attachment to the primary contract documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEMOLITION NOTES:
A. Remove existing wood door, hardware, HM frame and wire glass complete.
B. Existing surface mounted light fixture to be removed by owner. Circuits and switching to be reused for new lights.
C. Remove sliding glass panels and wood trim.
D. Remove existing 12x12 vinyl tile floor and 4" cove base in entire room.
E. Remove existing rubber stair treads and risers and 4" cove base complete on all stairs and landing from first floor to lower level.
F. Remove existing metal threshold .
G. Existing floor register to remain.
H. Remove existing 12x12 vinyl tile on landing.
J. Remove vinyl reducer strip at carpet edge.
A
B
C
A
D
D
A
BJS
BJS
03-03-2020
A-1.1
Fraser Public Schools Administration Building Lobby Renovation
LOBBY
HALLWAY
OFFICE
OFFICE
STAIR
E
201865
F
H
G
E
J
J
ADDENDUM NO. ONE
File details come from the government source that posted it. Updated .