ADDENDUM TWO.pdf
PDF 212 KB Posted
- Solicitation number
- B26003505
- Issued by
- Kauai County, Hawaii
About this file
Summary
This is Addendum Two to an Invitation for Bids issued by the State of Hawaii Department of Health Adult Mental Health Division for the removal, disposal, supply, and installation of new HVAC systems at the Kauai Friendship House located at 4-1751 Kuhio Highway, Kapaa, Hawaii 96746, under IFB No. 420-1-26. The scope of work includes removal of existing HVAC equipment and installation of new energy-efficient split AC systems comprising two Fujitsu AOUA72RLBV outdoor condenser units (72,000 BTU each) with six 4-way mounted air handlers for the Kitchen/Dining Area, and one Fujitsu AOUA98RLBV outdoor condenser unit (96,000 BTU) with seven 4-way ceiling-mounted air handlers for the Conference/Communication Area. All work must comply with EPA, OSHA, and applicable Federal, State, and Local Agency regulations, including appropriate weather proofing of all exterior components and complete replacement of all piping, electrical disconnects, and refrigerant lines. The original offer submittal deadline of July 31, 2026, is amended to August 7, 2026, at 4:00 p.m. Hawaii Standard Time. A mandatory site inspection was required prior to bid submission. The preferred contract start date is September 1, 2026, with a completion date of October 31, 2026.
Bidders must maintain an island-based business location on Kauai at the time of bidding and throughout the contract and warranty periods. The all-inclusive offer price must cover labor, materials, equipment, freight, delivery, applicable taxes, and all other costs. Award will be made to the responsive, responsible offeror submitting the lowest price. Contractors must comply with Hawaii Revised Statutes Section 103-55 prevailing wage requirements for contracts exceeding $25,000 and provide proof of compliance with Hawaii's General Excise Tax Law, Employment Security Law, Workers' Compensation Law, Temporary Disability Insurance, and Prepaid Health Care Act. The contractor must carry Commercial General Liability insurance with minimum limits of $1 million per occurrence and $2 million aggregate, plus Basic Motor Vehicle Insurance of $1 million per occurrence. A one-year workmanship warranty and one-year maintenance agreement are required. Questions regarding the solicitation must be submitted in writing and mailed by registered or certified mail return receipt requested prior to the offer deadline. Protests based on solicitation content must be submitted in writing and mailed by registered or certified mail return receipt requested prior to the offer deadline. Protests following award must be submitted within five working days after posting of the award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB HVAC Systems.pdf | ||
| ADDENDUM ONE.pdf | ||
| AG-008 103D General Conditions (1.10.23).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
State of Hawaii Department of Health
Adult Mental Health Division
Addendum Two
July 29, 2026 to
Invitation for Bids
Remove, Dispose, Supply, and Install New HVAC Systems at the Kauai Friendship House
IFB No. 420-1-26
IFB Release Date
June 26, 2026
July 29, 2026
ADDENDUM TWO
to
Invitation for Bids Remove, Dispose, Supply, and Install New HVAC Systems at the Kauai Friendship House IFB No. 420-1-26
The State of Hawaii’s Department of Health, Adult Mental Health Division, is issuing Addendum Two to IFB No. 460-1-26, Remove, Dispose, Supply, and Install
New HVAC Systems at the Kauai Friendship House for the purposes of:
Amending the IFB.
The Offer submittal deadline:
is amended.
The Offer submittal deadline is changed to 4:00 p.m. HST on August 7, 2026.
Attached is (are):
Amendments to the IFB.
31. PROTEST.
A protest based upon the content of the solicitation shall be submitted in writing and mailed by “registered” or “certified” mail return receipt requested prior to the date set for receipt of offers to the Procurement Officer Amy Yamaguchi, AMHD, P.O. Box 3378, Honolulu, Hawaii 96801.
Any protest pursuant to HRS §103D-701 and HAR §3-126-3 must be submitted in writing and mailed by “registered” or “certified” mail return receipt requested within five (5) working days after the posting of the award to the Procurement Officer Amy Yamaguchi, AMHD, P.O. Box 3378, Honolulu, Hawaii 96801.
The Questions and Answers are attached hereto as an amendment just in case the Questions and Answers were not posted in the solicitation.
If you have any questions, contact the IFB Issuing Officer via email:
IFB Issuing Officer Steven Osa Contract Specialist Telephone: 808 733-8386 Email: steven.osa@doh.hawaii.gov mailto:steven.osa@doh.hawaii.gov
1. The HVAC installation shall include appropriate weather proofing of all exterior components. Offeror shall include weather proofing recommendations in its Offer.
Does this specification call for Microguard Coating for exterior, fans, and coils?
The IFB requires the installation to include appropriate weather proofing of all exterior components but does not specify a brand of protective coating. The term appropriate used in this context means specialized weather proofing systems made for HVAC applications. Please include in your bid appropriate weather proofing.
2. Does "complete removal" include the complete replacement of all piping, covers, electrical disconnects?
Yes, the complete removal of the existing HVAC system includes everything including the complete replacement of all piping, covers, and electrical disconnects.
3. Could you confirm whether PSX700 & Blygold is required as weather proofing as coating by a 3rd party company?
The IFB requires the installation to include appropriate weather proofing of all exterior components but does not specify a brand of protective coating. The term appropriate used in this context means specialized weather proofing systems made for HVAC applications. Please include in your bid appropriate weather proofing.
4. Aloha, can you please advise if you want all new refrigerant lines or for us to utilize existing lines? If we reuse the existing, a change order might be needed if we find lines that are compromised.
The complete removal of the existing HVAC system includes everything including all the refrigerant lines and replacing them with new refrigerant lines.
5. To show sufficient experience, shall all bidders show history of at least six (6) successful VRF installation jobs?
There is no minimum requirement for the submission list for successful installation jobs. The IFB requires a list of companies as references for whom the vendor has provided services specified herein. The State reserves the right to contact any reference to inquire about the vendor’s past performance.
6. Will bidders be required to submit Fujitsu Airstage piping diagram to ensure proper pipe sizing?
The vendor bid should include an installation diagram to support the overall installation and costs of the project. In regard to ensuring that the proper pipe sizes are used, the vendor shall use its knowledge and expertise to use the proper pipe sizes for this project.
7. Could you provide electrical plans to ensure wiring is sized properly for the new equipment?
Unfortunately, the AMHD does not have any electrical plans available. The Kauai Friendship House building drawings from the previous HVAC installation included as Addendum One to this IFB is the only relevant document that AMHD has in its possession. The mandatory vendor site visit should have helped in answering any questions.
8. Will a witness test of each system holding at 500 microns or lower for four (4) hours to ensure a leak-free system be required?
The IFB requires that an operational test must be performed after the installation completion to ensure proper operation of the HVAC systems. There are no specifications regarding the operational test itself. The vendor shall conduct its standard operational test after the installation is completed and confirm that the HVAC system is operating properly which shall be sufficient to satisfy the operational test requirement in the IFB.
9. Is certified payroll required, to ensure all wages are competitive?
Certification of payroll is not required. Please complete, sign, date, and submit the Wage Certificate for Service Contracts which is included in the IFB.
10. Will submission of a list of subcontractors suffice for "prior written approval" of subcontractors?
Please submit a list of subcontractors that will be used on this project.
Subcontractors are subject to State contracting requirements.
| IFB No. 420-1-26 |
| Remove, Dispose, Supply, and Install New HVAC Systems |
| at the Kauai Friendship House |
| The State of Hawaii’s Department of Health, Adult Mental Health Division, |
| is issuing Addendum Two to IFB No. 460-1-26, Remove, Dispose, Supply, and Install New HVAC Systems at the Kauai Friendship House for the purposes of: |