This is an Addendum document outlining pay items for the City of DeBary's Bill Keller Park Infield Renovations project in Florida. The addendum specifies detailed specifications for two critical construction pay items related to the renovation of two youth baseball infields at Bill Keller Park. Pay Item 18-11 covers the complete removal and reconstruction of one full-size 18-foot diameter pitcher's mound using Pro Mound Packing Clay or equivalent material, topped with Pro's Choice Pro Red premium top dressing material spread to a half-inch thickness, lightly watered and tamped into place. This pay item includes verification and adjustment of mound grades, installation of a new 24-inch four-sided pitching rubber supplied by the City, and removal of approximately four feet of Bermuda sod around the mound's perimeter to ensure proper finish grade and water runoff. Pay Item 18-12 addresses the supply and installation of Crimson Stone Warning Track Material or approved equivalent, requiring the contractor to move materials into place, match existing slopes with finish material, remove all residual materials, and restore the site to its original condition.

The project must be completed with sod stabilized by August 23, 2018, when fall ball commences, with equipment mobilization beginning July 2, 2018. The addendum emphasizes the contractor's responsibility for material procurement, site preparation, and precise installation according to specified standards. All residual materials generated during construction activities must be removed and the work area restored to baseline conditions upon completion of each pay item.

View the file

Other files

File Type Posted
05-18_bid_tab.pdf PDF
Addendum_05-18_Bid_Form.xlsx XLSX spreadsheet
Addendum_05-18__1__4-17-18.docx DOCX document
BID_05-18.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pay Item No. 18-11 Pitchers Mound Construction – Pay Item 18-11 shall include full payment for the completed construction of (1) full size 18’ diameter pitcher’s mound.

The existing pitcher’s mound is to be completely removed and re-built. This mound shall be constructed using Pro Mound Packing Clay (or equivalent) over the entire surface of the mound. After mound construction is completed a Pro’s Choice - Pro Red premium top dressing material (or equivalent) is to be spread evenly over the top ¼” of the mound, lightly watered and then lightly tamped into place. Mound grades should be verified and adjusted accordingly prior to completion. A new 24” 4 sided pitching rubber supplied by the City will also be installed by contractor. In addition the awarded contractor will be required to remove approximately 4’ of Bermuda sod on the outside perimeter of the mound to ensure adequate finish grade and water runoff.

See Modifying the Pitcher’s Mound illustration provided with packet

Pay Item No. 18-12 Crimson Stone Warning Track Material – Pay Item 18-12 shall include full payment for supplying and installing Crimson Stone Warning track finish material (or approved equivalent).

Contractor will be required to supply and install Crimson Stone Warning track finish material. This entails moving materials into place and matching existing slopes with finish material.

All residual materials are to be removed and the site is to be stored back to its original condition.