This Addendum No. 1, issued April 17, 2018, modifies the original contract documents for the City of DeBary's Bill Keller Park Infield Renovation Project for Fields 1 and 3 (Bid #05-18). The project involves complete renovation of two youth baseball infields currently used by Babe Ruth for the 46/60 and 50/70 divisions. Scope of work includes stripping infields to base grade, re-working irrigation zones, performing laser grading for clay and turf areas, incorporating new clay with conditioner, constructing a new pitcher's mound with associated equipment, and installing new sod with final rolling of clay and turf areas. Equipment mobilization is scheduled for July 2, 2018, with project completion required by August 23, 2018, prior to the start of fall ball season. Bidders were required to acknowledge receipt of this addendum and submit bids by 2:00 P.M. on April 24, 2018, using the same sealed bid process as the original documents.
The projected project cost is $121,000. This addendum removes three bonding requirements that were specified in the original contract documents: Bid Bond, Performance Bond, and Payment Bond requirements are eliminated. All prospective bidders are responsible for independently verifying site conditions, including surface and subsurface characteristics, with guidance provided in Article 3, Section 2 under General Conditions regarding Unforeseen Physical Conditions. Bidders must quantify and factor all necessary materials in their proposals to achieve the finished product as outlined in the project specifications, as the quantities identified on the bid form may not account for all required materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 05-18_bid_tab.pdf | ||
| Addendum_Pay_Items.docx | DOCX document | |
| Addendum_05-18_Bid_Form.xlsx | XLSX spreadsheet | |
| BID_05-18.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 1 April 17, 2018
BID DOCUMENTS
FOR
BILL KELLER PARK INFIELD RENOVATION PROJECT
FIELDS 1&3
CITY OF DEBARY BID # 05-18
TO: PROSPECTIVE BIDDERS AND OTHER CONCERNED PARTIES
This Addendum #1 to the plans, specifications and contract documents for the City of DeBary, “BILL KELLER PARK INFIELD RENOVATION PROJECT FOR FIELDS 1&3 is hereby declared a part of the original Contract Documents dated March 31, 2018. This addendum shall be incorporated within the Contract Documents and shall have the same force and effect as if part of the original documents, and in the case of conflict, this Addendum No. 1 shall govern. Bidders shall state in their proposal that this Addendum No. 1 has been taken into consideration in their bids.
In the event that a bidding contractor has already submitted their sealed bid, acknowledgement of this addendum is required by returning the additional Bid Form following the same requirements as the original bid documents (sealed and clearly marked with Bid # 05-18) and received by the required submittal deadline of 2:00 P.M. on 4-24-18.
This Addendum consists of a total of 2 pages plus the following attachment items:
Additional Information
1. Addendum Specifications (1 page)
1. Addendum Pay Items (1 page)
CHANGES TO SPECIFICATIONS
1. Requirement for a Bid Bond is removed in all places within the contract documents
1. Requirement for a Performance Bond is removed in all places within the contract documents
1. Requirements for a Payment Bond is removed in all places within the contract documents
1. What is the projected project cost? The projected project cost is $121,000
1. The contract states “that all prospective bidders should inform itself to all conditions related to the project” with all aspects of the site to include surface and sub surface. The contract attempts to alleviate concerns regarding this. See Article 3, Section 2 under General Conditions Unforeseen Physical Conditions.
1. How accurate are the quantities identified on the “Bid Form” regarding materials? All prospective bidders should quantify and factor all necessary materials to obtain a finished product as outlined in the Project Specifications.
Tom VanDeHey City of DeBary Parks Superintendent 386-804-9195
END OF ADDENDUM NO. 1