This addendum issued by the Georgia World Congress Center Authority (GWCC) on September 1, 2023, modifies the original Request for Proposal (RFP081123EC) for escalator modernization at the facility. The addendum extends the submission deadline to September 13, 2023, at 10:00 a.m. and addresses 19 clarifications and modifications to the original bid specifications and requirements. Key project modifications include acceptance of 3/8" balustrade glass as specified, deletion of new truss isolation based on existing conditions, potential acceptance of 16-gauge decking panels if noise levels remain below 60 dB, and inclusion of bi-directional indicators on all escalators with direction of travel indicators at both top and bottom ends. The project involves the modernization of escalators (B25/B26) that serve the Thomas Murphy Ballroom, and contractors must coordinate work schedules around the facility's event calendar, with working hours to be determined with the selected vendor based on event scheduling in 2024, 2025, and 2026.
The addendum clarifies operational and logistical requirements, including barricading restrictions limited to carpeted areas, a minimum requirement for 4' x 8' Masonite board for barricades, and the GWCC's standard carpet specifications for any replacement work (Shaw manufactured custom pattern). The authority indicated that normal working hours can range from 7:00 a.m. to 5:00 p.m. during both event and non-event days, with consideration for night work and scheduling loud work on non-event days when possible. Submittals must be provided within 60 days of contract award rather than the originally specified 45 days. The addendum requires acknowledgment of these modifications prior to the submission deadline or attachment to the proposal, with a communication restriction in effect prohibiting interested firms from contacting GWCC staff or officials except through formal question submission procedures.
Text of this file
ADDENDUM ONE - AMENDED
GEORGIA WORLD CONGRESS CENTER AUTHORITY
ESCALATOR MODERNIZATION
RFPGWCC081123EC
Addendum Issue Date: September 1, 2023
From: Georgia World Congress Center Authority
Purchasing Office 285 International Boulevard NW Atlanta, Georgia 30313
Addendum 1 is hereby issued to incorporate the following as requirements of the Request for Proposal, RFP081123EC:
The submission date has been extended to September 13, 2023, by 10:00 am.
1. Section 01600, 1.6, G. – Request acceptance to provide 3/8” balustrade glass in lieu of ½”. 3/8” balustrade glass is acceptable.
2. Section 143100, 2.2,C.,1. – Request sound isolation be deleted if the contractor provides noise and vibration levels below 60 dBA. Provided the contractor can demonstrate noise levels below 60 dB, deletion of sound isolation can be considered.
3. Section 143100, 2.3,B.,2.0,d. – Request providing standard step chains with an onboard lubrication system in lieu of the Oiless step chain. Provide the oilless step chain as specified.
4. Section 143100, 2.7,B.,1. – Request deletion of new truss isolation since the trusses are not being removed and there is no access underneath the existing trusses.
Delete new truss isolation for the reasons indicated in the question.
5. Section 143100, 2.9,C.,1. – Request acceptance of 16 gauge decking panels in lieu of 14 gauge. Provided the contractor can demonstrate noise levels below 60 dB, 16-gauge decking panels would be acceptable.
6. Section 00800, 1.13,A – Are we clear to barricaded off the area behind the two escalators on the lower landing? Yes, but only to the limits of the carpeted area.
7. Section 00800, 1.13, A – We will do our best to submit a barricade plan with our bid, but this will not be the final plan if awarded the project. We understand that the details of final logistics will be worked out with the selected contractor. The intent is to see the logistics approach.
8. Section 00800, 1.13, A – Does the GWCC have a standard foam and masonite product that we are required to utilize? Standard 4’ x 8’ Masonite board is our minimum requirement.
9. Section 01900, 1.1,B-7 – Our bid currently doesn’t address the carpet cladding located at the base of the escalators. Is this something you all want to address prior to the bid? The carpet wall base in this area is a manufactured by Shaw. We may not have sufficient attic stock and will work with the selected contractor on procurement if replacement becomes necessary.
10. Section 01900, 1.1, D – Does the GWCC have access matching carpet at this time or know there it can be bought from? The carpet in this area is a custom pattern manufactured by Shaw. We may not have sufficient attic stock and will work with the selected contractor on procurement if carpet replacement becomes necessary.
11. Please define normal working hours for this project while scheduled events are taking place and when scheduled events are not taking place. Normal working hours during events can be 7am to 5pm. Additional hours may be available if needed. Non-event days would be the same. Night work can also be considered.
12. Please define working hours for loud work while scheduled events are taking place and when scheduled events are not taking place. Best efforts should be made to schedule loud work on non-event days or at night. These escalators serve the Thomas Murphy Ballroom which often hosts evening/night events so specific scheduling will need to be worked out with the selected firm.
13. Please provide a schedule of known events which this B25/B26 escalator work will impact in year 2024. A copy of the 2024 Event Schedule current as of June 15, 2023 is attached. Note that this schedule is subject to change. Events which will use the Thomas Murphy Ballroom are highlighted in red in the “Anchor Facility” column.
14. Please provide section 01030, Alternates. It is listed in the bid quotation form item
1.8 with an alternate for Escalator Monitoring System, but we do not see the section included in the bid documents. Ignore the reference to Section 01030, Alternates.
As it pertains to the monitoring system, the specifications call for a port in the controller 2.6 D 8-9 and what it must do. This port is required to accommodate future installation of a monitoring system.
15. Submittals – Request provide submission of approvals within 90 days of award of the contract in lieu of 45 days. (Submittals, 1.1, A.) 60 days
16. Please define normal working hours for this project while scheduled events are taking place and when scheduled events are not taking place. Working hours will be determined with the selected vendor since the timing of the work beginning is not known at this time and we cannot determine how specific working hours may be impacted by the event schedule until that is more specifically known.
17. Please define working hours for loud work while scheduled events are taking place and when scheduled events are not taking place. Working hours will be determined with the selected vendor since the timing of the work beginning is not known at this time and we cannot determine how specific working hours may be impacted by the event schedule until that is more specifically known.
18. Please provide a schedule of known events which for the B Building which will impact the escalator work will impact in year 2024, 2025 and 2026. See attached PDF.
19. During the pre-bid meeting, it was noted that an addendum would be issued to include bi-direction indicators on all the escalators in the project. This RFI is to memorialize that conversation. Correct, escalators are to be reversible with direction of travel indicators located on both ends (top and bottom)
This addendum will be a part of RFPGWCC081123EC and modifies the original proposal documents dated August 11, 2023 as noted.
NOTE: A signed acknowledgement of this addendum should be received by this office prior to the due date or should be attached to your proposal. A signature on this addendum does not constitute your signature on the original proposal document.
Authorized Signature: ___________________________________ Date: ___________ (Blue ink)
Name (Typed or Printed) ____________________________________
Other files
| File | Type | Posted |
|---|---|---|
| Event Schedule | — | |
| Sign In Sheet | — | |
| RFP | — | |
| Award Information | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .