Addendum No.2 - Sanitation Yard Vehicle Scale, VM Contract #1321.pdf
PDF 204 KB Posted
- Attached to
- Scarsdale Sanitation Yard Vehicle Scale
- Solicitation number
- VM Contract #1321
- Issued by
- Westchester County, New York
About this file
This document is an Addendum No. 2 issued by the Village of Scarsdale for the Sanitation Yard Vehicle Scale project, identified as VM Contract #1321. The addendum addresses two key bidder questions regarding a vehicle scale installation at the Scarsdale Sanitation Yard. Specifically, the document provides clarification on the totalizer location for hydraulic tubing calculations and confirms the requirement for Professional Engineer (PE) stamped drawings for the truck scale, which will be reviewed by the Owner's Consulting Engineer.
The addendum indicates that detailed information about the totalizer location can be obtained from the scale manufacturer specified in Section 119313 of the project specifications, with additional details available through product substitution procedures. The bidder is responsible for installing the scale on a concrete foundation provided by others, using dimensions specified in the project bid documents. No specific pricing, funding sources, or contract terms are detailed in this addendum, which appears to be a supplementary document to clarify technical specifications for potential bidders on the vehicle scale project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
February 13, 2025
ADDENDUM No. 2
Sanitation Yard Vehicle Scale
VM Contract #1321
This addendum / clarification, containing one (1) item, shall become a part of the Contract
Bid Documents.
ITEM NO.1 – Bidder Questions
1.) What is the exact location of the totalizer in relation to the truck scale? This information is needed to calculate the amount of hydraulic tubing required.
Answer - This information is available from the scale manufacturer of the specified scale indicated in Specification Section 119313 – Truck Scale Weigh System. If a scale substitution is being proposed, the requested information will be provided as part of the substitution procedures indicated in Specification Section 012500 – Product Substitution Procedures.
2.) Are PE stamped drawings required for the truck scale or foundation?
Answer - PE stamped drawings are required for the truck scale, which will be reviewed by the Owner’s Consulting Engineer. Bidder is responsible for providing and installing a scale on a concrete foundation provided by others in accordance with the concrete foundation dimensions indicated on the project drawings included in the project bid documents.