Addendum No. 2 to Invitation to Bid (ITB) 26-23-214657 issued by the Alaska Railroad Corporation provides clarifications and updates to the Bridge 158.7 Replacement project located at Milepost 158.7 near Cottonwood Creek in Wasilla. This addendum addresses a bidder question regarding material quantities for Type A and Type C fill materials by providing corrected quantities that account for fill areas within sheet pile cells and track prism configurations. The revised pay item quantities are 174 tons for Selected Material Type A (Pay Item 203.0006.1) and 237 tons for Selected Material Type C (Pay Item 203.0006.2). The project scope includes complete replacement of an existing timber bridge with a new two-span precast concrete ballast deck bridge on steel pipe piles, sheet pile abutments, reinforced concrete pile caps, bulkhead and riprap installation, track work, and site restoration. The comprehensive bid schedule encompasses 50 pay items in the base bid including clearing and grubbing (2.55 acres), unclassified excavation (337 cubic yards), structural steel piles and sheet piles, concrete work, track work (120 track feet), and two additive alternatives for concrete barriers and temporary railroad crossing. Sealed proposals were originally due June 30, 2026, at 3:00 p.m. at Alaska Railroad Corporation, 327 W. Ship Creek Avenue, Anchorage, AK 99501, with the deadline subsequently extended to July 15, 2026, per Addendum No. 1. A non-mandatory site visit was scheduled for June 23, 2026, at 12:00 p.m. at the Wasilla Section House. Substantial completion is required by January 30, 2027, with final completion by June 30, 2027.

Bidders must submit a bid bond equal to 5 percent of the bid price, along with a construction bid form, contractor responsibility questionnaire, and detailed cost schedule. The apparent low bidder must additionally provide a subcontractor list, quality assurance/quality control plan, and site health and safety plan within five working days of notification. The successful contractor must furnish 100 percent performance and payment bonds and a certificate of insurance prior to contract award. Liquidated damages of $4,900 per calendar day apply for failure to achieve substantial completion by the deadline. The project is jointly funded by the Alaska Railroad Corporation and the Federal Transit Administration, triggering federal contract compliance requirements for projects exceeding $100,000, including a race-neutral Disadvantaged Business Enterprise (DBE) aspiration of 4.0 percent participation during fiscal years 2025-2027. Prevailing wage requirements per the Minimum Rates of Pay for Laborers and Mechanics effective April 1, 2026, apply to all workers. Contractors must register with Avetta for verification and submit weekly certified payrolls within seven days of each pay period. Precast concrete bridge span halves and pile caps are furnished by ARRC from its Anchorage warehouse, with the contractor responsible for transportation, assembly, and installation. All structural steel must be hot-dip galvanized per ASTM A123 at 2.3 ounces per square foot, and prestressed concrete must achieve 6,000 PSI at 28 days. The bridge design complies with Cooper E-80 live loads, 0.25 coefficient seismic parameters, and 200 PSI ice pressure loads.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ALASKA RAILROAD CORPORATION

327 W. Ship Creek Ave.

Anchorage, AK 99501 wallaces@akrr.com

Phone (907)265-2425 Cell (907)744-0031

ADDENDUM NO. 2

Invitation to Bid (ITB) 26-23-214657 Bridge 158.7 Replacement Alaska Railroad Corporation Date: June 30, 2026

This Addendum No. 2 is issued to provide clarification in response to a bidder question, incorporate a revised plan sheet, and updated cost schedule. All other terms and conditions of the referenced solicitation remain unchanged.

QUESTION AND ANSWERS:

9. Using the Typical Bulkhead Section Sht 10 of 12 and the Proposed Plan and Profile Sht 08 of 12, I am coming up with substantially more Type A and Type C material quantities.

a. The Type C doesn’t appear to take into account the fill area outside the track prism but within the sheet pile cell and also the fact there is no track prism on the south end?

b. Type A and doesn’t appear to take into account the lack of track prism on the south side?

Quantities for both Type A and C fill have been double checked and need the following revision;

Type C, the correct quantity is 237 tons, Type A, the correct quantity is 174 tons. These updated quantities now account for the areas within the sheet pile cell and the track prism outside of the sheet pile cell.

PAY ITEMS (REVISED PAY SCHEDULE BELOW)

Pay Item 203.0006.1: 174 tons (Type A) Pay Item 203.0006.2: 237 tons (Type C)

ATTACHMENT (REVISIED) BR158.7 REPLACEMENT CBD, Page 3 of 12, dated June 6, 2026, this page supersedes all prior versions and replaces the previous version in its entirety.

Please acknowledge receipt of this and all addenda in your firms Supply Bid Form (Form 395-0129).

Sincerely, Contract Administration Specialist Alaska Railroad Corporation mailto:wallaces@akrr.com

SECTION H

(UPDATED) COST SCHEDULE

COST SCHEDULE:

A Bidder’s Failure to provide the information requested in this Appendix may be cause for rejection of the bid on the basis on non-responsiveness. Cost shall be bid in accordance with all specifications and any Technical Specifications incorporated herein.

AWARD CRITERIA:

A contract award resulting from this solicitation may be made to the low, responsive, responsible bidder who meets the requirements as set forth in the Plans and specifications and compliance thereof. An award may be made in the aggregate of Base Bid and or any combination of Base Bid and Add Alternates, whichever is deemed by the Contract Administrator to be in the best interest of the ARRC. The successful bidder shall hold unit prices of all additives firm for a period of thirty (30) days from the date of bid opening. Award is contingent on the availability of ARRC funds.

BR 158.7 REPLACEMENT BASE BID

Pay Item No.

Item Description Unit Quantity Unit Bid

Price Amount Bid

201.0003 Clearing and Grubbing ACRE 2.55

202.0023 Removal of Existing Bridge and Structures

LS 1

203.0003 Unclassified Excavation CY 337

203.0006.1 Selected Material, Type A TON 174

203.0006.2 Selected Material, Type C TON 237

203.2036 Temporary Access LS 1

301.0005 Railroad Sub-ballast, Grading C-1 TON 108

309.0001 Railroad Ballast, Type 3 TON 160

501.0004.1 Class A Concrete, 12"ø x 0.500”t Pile

CY 6

501.0004.2 Class A Concrete, 12"ø x 0.500”t Bollard

CY 1

501.0004.3 Class A Concrete, 24"ø x 0.500”t Pile

CY 6

501.0007.1 Install Precast Concrete Member, 28’ CBD Span

EA 2

501.0007.2 Install Precast Concrete Member, Double Row Cap

EA 3

BR 158.7 REPLACEMENT BASE BID (continued)

Pay Item No.

Item Description Unit Quantity

Unit Bid

Price Amount Bid

503.0001.1 Furnish Reinforcing Steel, 12"ø Pile Cages

LS 1

503.0001.2 Furnish Reinforcing Steel, 24"ø Pile Cages

LS 1

504.0001.1 Furnish Structural Steel, 28’ CBD Falloff Materials

EA 2

504.0001.2 Furnish Structural Steel, Walkway with Handrail Assembly

LS 1

504.0003.1 Install Structural Steel, 28’ CBD Falloff Materials

EA 2

504.0003.2 Install Structural Steel, Walkway with Handrail Assembly

LS 1

505.0005.1 Furnish Structural Steel Piles, 12”ø x 0.500”t Pipe

LF 760

505.0005.2 Furnish Structural Steel Piles, 16”ø x 0.500”t Pipe

LF 240

505.0005.3 Furnish PS-31 Sheet Pile (35 ft Length, ASTM A572, Grade 50)

EA 50

505.0005.4 Furnish PS-31 90° T Pile (35 ft Length, ASTM A572, Grade 50)

EA 8

505.0005.5 Furnish HP12x63 PS-31 Soldier Pile (40 FT Length, ASTM A572, Grade 50)

EA 4

505.0006.1 Drive Structural Steel Piles, 12”ø x 0.500”t Pipe

EA 12

505.0006.2 Drive Structural Steel Piles, 12”ø x 0.500”t Pipe Bollard

EA 2

505.0006.3 Drive Structural Steel Piles, 24”ø x 0.500”t Pipe

EA 3

505.0006.4 Drive Structural Steel Piles, HP12x63 PS-31 Soldier

EA 4

505.0010 Structural Steel Sheet Piles, PS-31 Piles

LS 1

505.2002.1 Pile Pre-Bore, 12”ø Piles EA 12

505.2002.2 Pile Pre-Bore, 24”ø Piles EA 3

505.2002.3 Pile Pre-Bore, HP12x63 PS-31 Soldier

EA 4

607.0003 Chain Link Fence LF 304

611.0001 Riprap, Class II CY 318

615.0001 Standard Sign, Bridge Sign – Type D

SF 2.25

618.0001 Seeding AC 2.55

631.0002 Geotextile, Erosions Control, Class

SY 192

640.0001 Mobilization and Demobilization LS 1

641.0001 Erosion, Sediment and Pollution Control Administration

LS 1

641.0003 Temporary Erosion, Sediment and Pollution Control

LS 1

642.0001 Construction Surveying LS 1

643.0002 Traffic Maintenance LS 1

643.0023 Traffic Price Adjustment CS - - - - - - - - -

646.0001 CPM Scheduling LS 1

647.0001 As-Built Drawings and Specifications

LS 1

802.0001 Track Work, 115# RE Rail TF 120

802.0005 Track Tamping, Surfacing, and Final Dressing

TF 256

803.0001 Track Removal TF 120

Total Base Bid:

BR 158.7 REPLACEMENT ADDITIVE ALTERNATE

Pay Item No.

Item Description Unit Quantity

Unit Bid

Price Amount Bid

614.0001 Concrete Barrier LF 128

520.0001 Temporary Crossing LS 1

Total Additive Alternative Bid:

NOTES:

Bid quantities are approximate. Contractor is responsible for their own quantity take-offs using the information within the Contract Documents to verify the quantities in the Bid Schedule.

NON-COLLUSION AFFIDAVIT:

The Undersigned declares, under penalty of perjury under the laws of the United States, that neither he/she nor the firm, association, or corporation of which he/she is a member, has, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with this Bid.

The Undersigned has read the foregoing proposal and hereby agrees to the conditions stated therein by affixing his/her signature below:

BIDDER’S NAME AND ADDRESS:

COMPANY NAME SIGNATURE BY AND FOR THE BIDDER

COMPANY MAILING ADDRESS PRINTED NAME OF ABOVE BIDDER

CITY, STATE ZIP CODE DATE OF BID

CONTACT PHONE NUMBER CONTACT E-MAIL

BR158.7 REPLACEMENT CBD

PROJECT STATIONS: 13+28.87 TO 15+84.87

AutoCAD SHX Text

MP158.7

AutoCAD SHX Text

1. PAY ITEM QUANTITIES ARE APPROXIMATE. CONTRACTOR IS RESPONSIBLE FOR THEIR OWN QUANTITY TAKE-OFFS USING THE INFORMATION PAY ITEM QUANTITIES ARE APPROXIMATE. CONTRACTOR IS RESPONSIBLE FOR THEIR OWN QUANTITY TAKE-OFFS USING THE INFORMATION WITHIN THE CONTRACT DOCUMENTS TO VERIFY THE QUANTITIES LISTED HEREON. 2. BALLAST REQUIRED FOR TAMPING AND SURFACING TO BE SUBSIDIARY TO TRACK WORK.BALLAST REQUIRED FOR TAMPING AND SURFACING TO BE SUBSIDIARY TO TRACK WORK.

AutoCAD SHX Text

TABLE OF ESTIMATING FACTORS

AutoCAD SHX Text

ITEM DESCRIPTION

AutoCAD SHX Text

ESTIMATING FACTOR

AutoCAD SHX Text

TRACK BALLAST, TYPE 3

AutoCAD SHX Text

110 LB/FT 3

AutoCAD SHX Text

SELECTED MATERIAL

AutoCAD SHX Text

135 LB/FT 3

AutoCAD SHX Text

AGGREGATE BASE COURSE , GRADING C-1

AutoCAD SHX Text

144 LB/FT 3

AutoCAD SHX Text ITEMS FURNISHED BY ARRC: 1. PRECAST CBD SPAN HALVES AND PILE CAPS SHALL BE FURNISHED BY ARRC. CONTRACTOR IS PRECAST CBD SPAN HALVES AND PILE CAPS SHALL BE FURNISHED BY ARRC. CONTRACTOR IS RESPONSIBLE FOR TRANSPORTING ALL PRECAST CONCRETE MEMBERS FROM THE ANCHORAGE WAREHOUSE TO THE SITE, ASSEMBLING, AND SETTING IN PLACE.

AutoCAD SHX Text

SUMMARY OF ESTIMATED QUANTITIES PROVIDED BY ARRC

AutoCAD SHX Text

DESCRIPTION

AutoCAD SHX Text

UNIT

AutoCAD SHX Text

QUANTITY

AutoCAD SHX Text 7"x9"x8'-6" TIE

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 7"x9"x10'-0" TIE

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text

MISC. TRACK MATERIAL (TIE PLATES, ETC.)

AutoCAD SHX Text

CS

AutoCAD SHX Text

ALL REQ'D

AutoCAD SHX Text

NEW 115RE RAIL

AutoCAD SHX Text

TF

AutoCAD SHX Text

AutoCAD SHX Text

PRECAST CONCRETE CBD (HALF SPAN)

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text

PRECAST CONCRETE DOUBLE ROW PILE CAP

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text

PROJECT:

AutoCAD SHX Text

SHEET TITLE:

AutoCAD SHX Text

DESIGNED BY:

AutoCAD SHX Text P:\ENGINEERING\BRIDGES\BR 158_7 COTTONWOOD CREEK\2022 BRIDGE REPLACEMENT PROGRAM\BR 158.7 CBD REPLACEMENT.DWG

AutoCAD SHX Text

PUBLISHED CTB

AutoCAD SHX Text

DRAWING LOCATION

AutoCAD SHX Text

DATE TIME

AutoCAD SHX Text

SCALE

AutoCAD SHX Text

ENGINEERING DEPARTMENT

AutoCAD SHX Text

P.O. BOX 107500 BOX 107500 ANCHORAGE, ALASKA 99510-7500

AutoCAD SHX Text

SHEET

AutoCAD SHX Text

OF

AutoCAD SHX Text

YEAR

AutoCAD SHX Text

AFE NO.

AutoCAD SHX Text

AS NOTED

AutoCAD SHX Text

CHECKED BY:

AutoCAD SHX Text

DRAFTED BY:

AutoCAD SHX Text ALASKA RAILROAD CORPORATION PO BOX 107500, ANCHORAGE, AK 99510-7500 327 W SHIP CREEK AVE ANCHORAGE, AK 99501 (907) 265-2300

AutoCAD SHX Text

KEY MAP

AutoCAD SHX Text

ANCHORAGE

AutoCAD SHX Text

SEWARD

AutoCAD SHX Text

FAIRBANKS

AutoCAD SHX Text

BR158.7 REPLACEMENT CBD

AutoCAD SHX Text

ESTIMATE OF QUANTITIES

AutoCAD SHX Text 12268

AutoCAD SHX Text

AutoCAD SHX Text

AutoCAD SHX Text

BLG

AutoCAD SHX Text

BAO

AutoCAD SHX Text

BLG

AutoCAD SHX Text

AutoCAD SHX Text

ARRC_CTB_2023.CTB

AutoCAD SHX Text

6/26/2026 1:24 PM

AutoCAD SHX Text

TABLE OF PAY ITEMS

AutoCAD SHX Text

PAY ITEM

AutoCAD SHX Text

ITEM DESCRIPTION

AutoCAD SHX Text

PAY UNIT

AutoCAD SHX Text

TOTAL QUANTITY

AutoCAD SHX Text 201.0003

AutoCAD SHX Text

CLEARING AND GRUBBING

AutoCAD SHX Text

AC

AutoCAD SHX Text 2.55

AutoCAD SHX Text 202.0023

AutoCAD SHX Text

REMOVAL OF EXISTING BRIDGE AND STRUCTURES

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 203.0003

AutoCAD SHX Text

UNCLASSIFIED EXCAVATION

AutoCAD SHX Text

CY

AutoCAD SHX Text

AutoCAD SHX Text 203.0006.1

AutoCAD SHX Text

SELECTED MATERIAL, TYPE A

AutoCAD SHX Text

TON

AutoCAD SHX Text

AutoCAD SHX Text 203.0006.2

AutoCAD SHX Text

SELECTED MATERIAL, TYPE C

AutoCAD SHX Text

TON

AutoCAD SHX Text

AutoCAD SHX Text 203.2036

AutoCAD SHX Text

TEMPORARY ACCESS

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 301.0005

AutoCAD SHX Text

AGGREGATE BASE (SUBBALLAST), GRADING C-1

AutoCAD SHX Text

TON

AutoCAD SHX Text

AutoCAD SHX Text 309.0001

AutoCAD SHX Text

RAILROAD BALLAST, TYPE 3

AutoCAD SHX Text

TON

AutoCAD SHX Text

AutoCAD SHX Text 501.0004.1

AutoCAD SHX Text CLASS A CONCRETE, 12"ø x 0.500”t PILEt PILE

AutoCAD SHX Text

CY

AutoCAD SHX Text

AutoCAD SHX Text 501.0004.2

AutoCAD SHX Text CLASS A CONCRETE, 12"ø x 0.500”t BOLLARDt BOLLARD

AutoCAD SHX Text

CY

AutoCAD SHX Text

AutoCAD SHX Text 501.0004.3

AutoCAD SHX Text CLASS A CONCRETE, 24"ø x 0.500”t PILEt PILE

AutoCAD SHX Text

CY

AutoCAD SHX Text

AutoCAD SHX Text 501.0007.1

AutoCAD SHX Text

INSTALL PRECAST CONCRETE MEMBER, 28' CBD SPAN

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 501.0007.2

AutoCAD SHX Text

INSTALL PRECAST CONCRETE MEMBER, DOUBLE ROW PILE CAP

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 503.0001.1

AutoCAD SHX Text FURNISH REINFORCING STEEL, 12"ø PILE CAGES

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 503.0001.2

AutoCAD SHX Text FURNISH REINFORCING STEEL, 24"ø PILE CAGES

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 504.0001.1

AutoCAD SHX Text

FURNISH STRUCTURAL STEEL, 28' CBD FALLOFF MATERIALS

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 504.0001.2

AutoCAD SHX Text

FURNISH STRUCTURAL STEEL, WALKWAY WITH HANDRAIL ASSEMBLY

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 504.0003.1

AutoCAD SHX Text

INSTALL STRUCTURAL STEEL, 28' CBD FALLOFF MATERIALS

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 504.0003.2

AutoCAD SHX Text

INSTALL STRUCTURAL STEEL, WALKWAY WITH HANDRAIL ASSEMBLY

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 505.0005.1

AutoCAD SHX Text FURNISH STRUCTURAL STEEL PILES, 12"Ø x 0.500"t PIPE

AutoCAD SHX Text

LF

AutoCAD SHX Text

AutoCAD SHX Text 505.0005.2

AutoCAD SHX Text FURNISH STRUCTURAL STEEL PILES, 24"Ø x 0.500"t PIPE

AutoCAD SHX Text

LF

AutoCAD SHX Text

AutoCAD SHX Text 505.0005.3

AutoCAD SHX Text

FURNISH PS-31 SHEET PILE (35 FT LENGTH, ASTM A572, GRADE 50)

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.0005.4

AutoCAD SHX Text

FURNISH PS-31 90° T PILE (35 FT LENGTH, ASTM A572, GRADE 50)

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.0005.5

AutoCAD SHX Text FURNISH HP12x63 PS-31 SOLDIER PILE (40 FT LENGTH, ASTM A572, GRADE 50)

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.0006.1

AutoCAD SHX Text DRIVE STRUCTURAL STEEL PILES, 12"ø PIPE

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.0006.2

AutoCAD SHX Text DRIVE STRUCTURAL STEEL PILES, 12"ø PIPE BOLLARD

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.0006.3

AutoCAD SHX Text DRIVE STRUCTURAL STEEL PILES, 24"ø PIPE

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.0006.4

AutoCAD SHX Text DRIVE STRUCTURAL STEEL PILES, HP12x63 PS-31 SOLDIER

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.0010

AutoCAD SHX Text

STRUCTURAL STEEL SHEET PILES, PS-31 PILES

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 505.2002.1

AutoCAD SHX Text

PILE PRE-BORE, 12"Ø PILES

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.2002.2

AutoCAD SHX Text

PILE PRE-BORE, 24"Ø PILES

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 505.2002.3

AutoCAD SHX Text PILE PRE-BORE, HP12x63 PS-31 SOLDIER

AutoCAD SHX Text

EA

AutoCAD SHX Text

AutoCAD SHX Text 607.0003

AutoCAD SHX Text

CHAIN LINK FENCE

AutoCAD SHX Text

LF

AutoCAD SHX Text

AutoCAD SHX Text 611.0001

AutoCAD SHX Text

RIPRAP, CLASS II

AutoCAD SHX Text

CY

AutoCAD SHX Text

AutoCAD SHX Text 615.0001

AutoCAD SHX Text

STANDARD SIGN, BRIDGE SIGN - TYPE D

AutoCAD SHX Text

SF

AutoCAD SHX Text 2.25

AutoCAD SHX Text 618.0001

AutoCAD SHX Text

SEEDING

AutoCAD SHX Text

AC

AutoCAD SHX Text 2.55

AutoCAD SHX Text 631.0002

AutoCAD SHX Text

GEOTEXTILE, EROSION CONTROL, CLASS 1

AutoCAD SHX Text

SY

AutoCAD SHX Text

AutoCAD SHX Text 640.0001

AutoCAD SHX Text

MOBILIZATION AND DEMOBILIZATION

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 641.0001

AutoCAD SHX Text

EROSION, SEDIMENT, AND POLLUTION CONTROL ADMINISTRATION

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 641.0003

AutoCAD SHX Text

TEMPORARY EROSION, SEDIMENT, AND POLLUTION CONTROL

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 642.0001

AutoCAD SHX Text

CONSTRUCTION SURVEYING

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 643.0002

AutoCAD SHX Text

TRAFFIC MAINTENANCE

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 643.0023

AutoCAD SHX Text

TRAFFIC PRICE ADJUSTMENT

AutoCAD SHX Text

CS

AutoCAD SHX Text

AutoCAD SHX Text 646.0001

AutoCAD SHX Text

CPM SCHEDULING

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 647.0001

AutoCAD SHX Text

AS-BUILT DRAWINGS AND SPECIFICATIONS

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text 802.0001

AutoCAD SHX Text

TRACK WORK, 115# RE RAIL

AutoCAD SHX Text

TF

AutoCAD SHX Text

AutoCAD SHX Text 802.0005

AutoCAD SHX Text

TRACK TAMPING, SURFACING, AND FINAL DRESSING

AutoCAD SHX Text

TF

AutoCAD SHX Text

AutoCAD SHX Text 803.0001

AutoCAD SHX Text

TRACK REMOVAL

AutoCAD SHX Text

TF

AutoCAD SHX Text

AutoCAD SHX Text

ADDITIVE ALTERNATE

AutoCAD SHX Text

PAY ITEM

AutoCAD SHX Text

ITEM DESCRIPTION

AutoCAD SHX Text

PAY UNIT

AutoCAD SHX Text

TOTAL QUANTITY

AutoCAD SHX Text 614.0001

AutoCAD SHX Text

CONCRETE BARRIER

AutoCAD SHX Text

LF

AutoCAD SHX Text

AutoCAD SHX Text 617.0001

AutoCAD SHX Text

TEMPORARY RAILROAD CROSSING

AutoCAD SHX Text

LS

AutoCAD SHX Text

AutoCAD SHX Text

ADDENDUM NO. 2
QUESTION AND ANSWERS: