About this file

This Addendum No. 2 document issued by the San Bernardino County Flood Control District clarifies specifications and requirements for Request for Proposal No. PWG126-ADMIN-6296 for professional land surveying services on the Del Rosa Channel project in San Bernardino. The addendum addresses bidder questions regarding topographic data collection methodologies, pickup survey locations, survey control documentation, feature library requirements, and site limit extents. Key clarifications include confirmation that ground survey is required as the primary data collection method, that GPS and aerial survey methodologies may be used where appropriate (though GPS is typically not used on hard surfaces), that pickup refers to additional areas of topo collection beyond the 2024 ground survey completed by the County Surveyor's Office, and that survey data collection must include parking lots and building structures within specified red boundary limits per the Survey Limits Map. The addendum provides four attachments including updated External Topo Standards, Del Rosa Channel Field Survey Notes, CAD files, and ground control data, which must be considered in conjunction with existing RFP documents during proposal preparation.

Bidders are required to submit a detailed fee proposal in accordance with Attachment E (Fee Proposal Sheet) at the time of proposal submission, and must acknowledge receipt of Addendum No. 2 with a signed Bidder's Certification completed by the same individual authorized to sign the proposal. Any proposal submitted without the executed Bidder's Certification will not be accepted. The addendum clarifies that exceptions noted in Attachment H include exceptions to both the County and the District requirements. All attachments are provided separately through the ePro procurement system. The revised proposal submission deadline is 4:00 p.m. on Monday, March 30, 2026, via email through the ePro System.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 2 Page 1 of 2 RFP for Proposal No. PWG126-ADMIN-6296 March 26, 2026

ADDENDUM NO. 1

REQUEST FOR PROPOSAL NO. PWG126-ADMIN-6296

PROFESSIONAL LAND SURVEYING SERVICES

AREA: SAN BERNARDINO AREA

DEADLINE FOR PROPOSAL: 12:00 PM, THURSDAY, MARCH 26, 2026

DEADLINE FOR PROPOSAL: 4:00 PM, MONDAY, MARCH 30, 2026

By Email via ePro System

Questions on EPRO:

1. a) The Type of Data required section includes a check mark for Topo/Aerial Survey. Please confirm whether aerial survey data collection is required as part of this scope. b) The form indicates a pick-up No. 1 is required. Could you please clarify what this refers to and provide a sample file or example deliverable? c) Does the County have existing survey control from previous channel surveys that this work should tie into? If so, please provide the available control data and documentation. d) The document states All topo to be collected via total station, not RTK. Please confirm whether GPS or aerial survey methodologies are prohibited for topographic data collection, or if these methods may be used where appropriate. e) be collected using the County’s feature library? If so, please provide a copy of the codebook and feature library files or advise if additional time may be included to develop the required files. f) On sheet 1 of 4 of the Site Limits Map, please confirm the extents of the parking lot and building structures within the red boundary.

a) Ground survey is required for this project.

b) Pickup is the term used for additional areas of topo collection. A ground survey was completed by the County Surveyor’s Office in 2024. This new survey data collection is for Pick-up No. 1.

c) Yes, see attachment.

d) These methods may be used where appropriate. Typically, the District and County does not use GPS on hard surfaces.

e) Yes, see attachment.

f) For the extents of parking lot area, the survey data collection should include the parking lot and building structures within the red boundary per Note 1 of the Survey Limits Map, see Sheet 1 of 4.

2. On Page 8 of 54, the RFP references the San Bernardino County Topographic Survey Standard Notes.

Please provide the most current version of these standards.

See current version (attached).

3. We acknowledge that Attachment E – Fee Proposal Sheet requests hourly rates and other additional relevant costs are included in this submittal. Can the County please confirm if a detailed fee for the specific scope of work provided in the RFP is required at this time, or if it will be requested only from the awarded firm?

A detailed fee is required at this time in accordance with Attachment E (Fee Proposal Sheet(s).

ADDENDUM NO. 2 Page 2 of 2 RFP for Proposal No. PWG126-ADMIN-6296 March 26, 2026

4. The RFP asks that we complete Attachment H, exceptions to RFP, can you please clarify if this includes exceptions to the District.

Yes, it includes exceptions to the District.

ATTACHMENTS:

All attachments are provided separately on Epro.

Attachment A: External Topo Standards Attachment B: Del Rosa Channel Field Survey Notes Attachment C: CAD File Attachment D: Del Rosa Channel Control-Combo (ground)

The addition of these requirements shall be considered in concert with existing documents in preparation of bids. THE BIDDER’S CERTIFICATION FOR THIS ADDENDUM NO. 2 SHALL BE SIGNED BY THE SAME

PERSON WHO SIGNS THE PROPOSAL AND SHALL BE SUBMITTED WITH THE PROPOSAL. ANY

proposal not accompanied by a signed BIDDER’S CERTIFICATION (below) acknowledging receipt of this Addendum No. 2 will NOT be accepted.

Noel Castillo, Director Department of Public Works

By:

Lawrence G. White, P.E., Chief

Flood Design Division

LW:MR

BIDDER'S CERTIFICATION:

By my signature hereunder, I acknowledge receipt of Addendum No. 2 and I fully understand the intent and detail of Addendum No. 2, which I have considered in my preparation of the attached proposal.

Bidder's Signature Date Note: The page containing the executed BIDDER’S CERTIFICATION (just this page), must be included with the proposal.