Addendum No. 1 - FS 227 Responsibility Matrix.pdf

PDF 42 KB Posted

Attached to
1202 - County Fire Station 227 New Build
Solicitation number
ANE223-ANE2C-6144
Issued by
San Bernardino County, California

About this file

This is an Addendum No. 1 to a Fire Station 227 New Build project, establishing a responsibility matrix that delineates obligations between the Owner (PFMD) and the Contractor across multiple environmental, regulatory, and operational compliance areas. The matrix addresses eight primary responsibility categories: biological resources (BIO-1), geotechnical requirements (GEO-1 and GEO-2), hazardous materials management (HAZ-1), stormwater and best management practices (HYD-1), noise and hours of operation (NOI-1, NOI-2, NOI-3), project coordination (PS-1), and traffic management (TRA-1 and TRA-2). Key responsibilities include the Owner's engagement of qualified professionals such as a biologist, paleontologist, and archaeologist, while the Contractor is responsible for implementing recommendations from these professionals' findings and adhering to established plans and protocols including the Archaeological Monitoring and Treatment Plan (AMPT).

The addendum establishes extensive cultural resource management requirements involving tribal coordination, including execution of a Tribal Monitoring Agreement, on-site presence of archaeologists and tribal monitors during excavation of undisturbed soil, and protocols for handling unearthed cultural resources and Native American human remains. The Contractor must comply with specific operational constraints including restricted construction traffic during school hours at Arrowhead Elementary School and notification requirements for sensitive receptors within 30 days of construction commencement. The Owner assumes responsibility for coordinating tribal monitoring agreements and engaging qualified archaeological and paleontological professionals, while the Contractor bears primary responsibility for day-to-day implementation of all recommended mitigation measures, plans, and protocols as detailed in the contract documents and referenced appendices.

View the file

Other files

File Type Posted
ATT-PFMD-102125-Fire Permit-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 48 1400 - Photovoltaic System enclosure 17-36.pdf PDF
ATT Prevailing Wage Document 6.17.25.pdf PDF
Addendum No. 1 - FS 227 33 3113 Site Sanitary Sewerage Gravity Piping Enclosure 49-50.pdf PDF
ATT-PFMD-102125-Compliant Grading Plans-CF Station 227.pdf PDF
ATT-PFMD-102125-Building Grading Permit-CF Station 227 New Build.pdf PDF
Prevailing Wage - September 2025 Packet.pdf PDF
Addendum No. 1 - FS 227 Sheet A5.2 Toilet Accessories Enclosure 6.pdf PDF
Addendum No. 1 - FS 227 Sheet L-1 and L-3 Enclosure 61 and 62.pdf PDF
ATT-PFMD-102125-Water Quality Management Report-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 Table of Contents Enclosure 1-5.pdf PDF
Addendum No. 1 - FS 227 33 4211 Stormwater Gravity Piping Enclosure 51.pdf PDF
ATT-PFMD-102125- Bid Documents - CF Station 227 New Build.pdf PDF
ATT-PFMD-102125-Drawings-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 Project Sign Enclosure 60.pdf PDF
Addendum No. 1 - FS 227 Sheet A1.0 Demo Site Plan Enclosure 59.pdf PDF
ATT-PFMD-102125-Geotechnical Study-CF Station 227 New Build.pdf PDF
ATT-PFMD-102125-Compliant Drainage Study-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 21 1300 Fire Protection System Enclosure 7-16.pdf PDF
ATT-PFMD-102125-SCE Final Map-CF Station 227 New Build.pdf PDF
Addendum No. 1 - San Bernardino Fire Station 227_Final AMTP_110425_Signed.pdf PDF
Addendum No. 1 - FS 227 33 0110.58 Disinfection of Water Utility Piping Systems Enclosure 44.pdf PDF
ATT-PFMD-102125-Initial Study_Mitigated Negative Declaration-CF Station 227.pdf PDF
Addendum No. 1 - FS 227 Sheet SN1 Concrete Strength Table Enclosure 38.pdf PDF
Addendum No. 1 - FS 227 Sheet A1.1 Enclosure 37.pdf PDF
Addendum No. 1 - FS 227 33 4230 Stormwater Drains Enclosure 52-53.pdf PDF
Addendum No. 1 - FS 227 33 4923 Storm Drainage Water Retention Structures Enclosure 54-58.pdf PDF
ATT-PFMD-102125-SWPPP Report-CF Station 227.pdf PDF
ATT-PFMD-102125-Appendix 7 Mitigation Monitoring Reporting Program-CF Station 227 New Build.pdf PDF
1202 - Addendum No 1 - Narrative.pdf PDF
ATT-PFMD-102125-Structural Calculations-CF Station 227 New Build.pdf PDF
ATT-PFMD-102125-Technical Specifications-CF Station 227 New Build_.pdf PDF
Addendum No. 1 - FS 227 33 1416 Site Water Utility Distribution Piping Enclosure 45-48.pdf PDF
Addendum No. 1 - FS 227 21 1100 Facility Fire-Suppression Water-Service Piping Enclosure 39-43.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10.10.1202: Fire Station 227 New Build

Responsibility Matrix MM Responsiblility Description

BIO-1 PFMD

Owner to hire qualified Biologist to perform the Pre-Construction survey.

Contractor to implement recommendations from findings.

GEO-1 PFMD

Geotechnical report dated September 6, 2024, is the latest report and supersedes older reports. The recommendations in the geotechnical report are a requirement of the contract.

GEO-2 PFMD

Owner to hire a Professional Paleontologist. Contractor to implement and follow recommendation from findings, Appendix 7 and the AMPT.

HAZ-1 Contractor Hazardous Materials and Waste Management Plan

HYD-1 Contractor

Best Management practices (BMPs) associated with construction activities have been developed, Contractor to implement per the contract documents.

HYD-1 Contractor Structural and nonstructural BMPs have been developed. Contractor to implement as per the contract documents.

NOI-1 Contractor Contractor to comply with the hours of operation stipulated in the contract documents

NOI-2 Contractor Contractor to notify all sensitive receptors, including residences within 30 days of construction Start.

NOI-3 Contractor Contractor to implement the recommendation to mitigate the excess ambient noise levels

PS-1 Contractor/ PFMD

In coordination with PFMD and the Contractor, coordination efforts, including a formal coordination meeting with SBCUSD and Arrowhead Elementary School, will be carried out prior to the start of construction

TRA-1 Contractor The Contractor shall avoid construction traffic during the start and dismissal times of Arrowhead Elementary

TRA-2 Contractor Contractor to coordinate the Traffic Control Plan with the City, Arrowhead

Elementry School and SBCUSD

TCR-1 PFMD Owner to coordinate a Tribal Monitoring Agreement

TCR-2 PFMD Owner to hire a Qualified Archaeologist

TCR-3 PFMD

Cultural Resource Management Plan (CRMP) and/or Archaeological Monitoring and Treatment Plan (AMTP), contractor to implement recommendations.

TCR-4 PFMD/ Contractor Contractor to coordinate with PFMD the attendance of the Qualified

Archeologist and Consulting Tribe[s] at the pre-grade meeting.

TCR-5 PFMD/ Contractor An Archaeologist and the Tribal Monitor(s) shall be on-site during the excavation of undisturbed soil.

TCR-6 Contractor/ Archaeologist Unidentified cultural resources discovered /unearthed during construction, contractor to follow recommendations per appendix 7 and AMPT.

TCR-7 Contractor/ Archaeologist Protect Native American human remains and/or cremations, contractor to follow recommendations per appendix 7 and AMPT

TCR-8 Archaeologist

Final report(s)including CRMP/AMTP, isolate records, site records, survey reports, testing reports, and other related documents shall be submitted to the

Lead Agency and Consulting Tribe(s) for review and comment.