Addendum No. 1 - FS 227 33 4211 Stormwater Gravity Piping Enclosure 51.pdf

PDF 126 KB Posted

Attached to
1202 - County Fire Station 227 New Build
Solicitation number
ANE223-ANE2C-6144
Issued by
San Bernardino County, California

About this file

This document is an Addendum No. 1 to the specification for stormwater gravity piping work at SBC Fire Station 227, prepared by STK Architecture, Inc. in August 2025. The specification covers stormwater drainage piping installation, including pipe materials, accessories, and related work such as excavation, fill, backfill, and bedding operations. The scope requires corrugated polyethylene drainage pipe compliant with AASHTO M 252 and ASTM D3350 standards, along with associated fittings in various configurations including tees, bends, elbows, cleanouts, reducers, and traps. Installation requirements mandate that pipe be laid to slope gradients as noted on layout drawings with a maximum variation from true slope of 1/8 inch in 10 feet, and the stormwater drainage system must be connected as shown on the construction plans.

The specification establishes execution requirements for trenching and backfill operations, requiring cover fill to be tamped in place and compacted around pipe sides and to the top of the pipe. All pipe and bedding must be protected from damage or displacement until backfilling operations commence. The document references related specification sections for excavation procedures, fill and backfill requirements, and stormwater drain details, and requires all submittals to follow the procedures outlined in Section 01 3000 Administrative Requirements. No pricing terms, contract duration, bid submission dates, or award information is included in this technical specification addendum.

View the file

Other files

File Type Posted
ATT-PFMD-102125-Fire Permit-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 48 1400 - Photovoltaic System enclosure 17-36.pdf PDF
ATT Prevailing Wage Document 6.17.25.pdf PDF
Addendum No. 1 - FS 227 33 3113 Site Sanitary Sewerage Gravity Piping Enclosure 49-50.pdf PDF
ATT-PFMD-102125-Compliant Grading Plans-CF Station 227.pdf PDF
ATT-PFMD-102125-Building Grading Permit-CF Station 227 New Build.pdf PDF
Prevailing Wage - September 2025 Packet.pdf PDF
Addendum No. 1 - FS 227 Responsibility Matrix.pdf PDF
Addendum No. 1 - FS 227 Sheet A5.2 Toilet Accessories Enclosure 6.pdf PDF
Addendum No. 1 - FS 227 Sheet L-1 and L-3 Enclosure 61 and 62.pdf PDF
ATT-PFMD-102125-Water Quality Management Report-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 Table of Contents Enclosure 1-5.pdf PDF
ATT-PFMD-102125- Bid Documents - CF Station 227 New Build.pdf PDF
ATT-PFMD-102125-Drawings-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 Project Sign Enclosure 60.pdf PDF
Addendum No. 1 - FS 227 Sheet A1.0 Demo Site Plan Enclosure 59.pdf PDF
ATT-PFMD-102125-Geotechnical Study-CF Station 227 New Build.pdf PDF
ATT-PFMD-102125-Compliant Drainage Study-CF Station 227 New Build.pdf PDF
Addendum No. 1 - FS 227 21 1300 Fire Protection System Enclosure 7-16.pdf PDF
ATT-PFMD-102125-SCE Final Map-CF Station 227 New Build.pdf PDF
Addendum No. 1 - San Bernardino Fire Station 227_Final AMTP_110425_Signed.pdf PDF
Addendum No. 1 - FS 227 33 0110.58 Disinfection of Water Utility Piping Systems Enclosure 44.pdf PDF
ATT-PFMD-102125-Initial Study_Mitigated Negative Declaration-CF Station 227.pdf PDF
Addendum No. 1 - FS 227 Sheet SN1 Concrete Strength Table Enclosure 38.pdf PDF
Addendum No. 1 - FS 227 Sheet A1.1 Enclosure 37.pdf PDF
Addendum No. 1 - FS 227 33 4230 Stormwater Drains Enclosure 52-53.pdf PDF
Addendum No. 1 - FS 227 33 4923 Storm Drainage Water Retention Structures Enclosure 54-58.pdf PDF
ATT-PFMD-102125-SWPPP Report-CF Station 227.pdf PDF
ATT-PFMD-102125-Appendix 7 Mitigation Monitoring Reporting Program-CF Station 227 New Build.pdf PDF
1202 - Addendum No 1 - Narrative.pdf PDF
ATT-PFMD-102125-Structural Calculations-CF Station 227 New Build.pdf PDF
ATT-PFMD-102125-Technical Specifications-CF Station 227 New Build_.pdf PDF
Addendum No. 1 - FS 227 33 1416 Site Water Utility Distribution Piping Enclosure 45-48.pdf PDF
Addendum No. 1 - FS 227 21 1100 Facility Fire-Suppression Water-Service Piping Enclosure 39-43.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STK Architecture, Inc. August 2025

SBC Fire Station 227 33 4211-1 Stormwater Gravity Piping

SECTION 33 4211

STORMWATER GRAVITY PIPING

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Stormwater drainage piping.

B. Stormwater pipe accessories.

1.02 RELATED REQUIREMENTS

A. Section 31 2316 - Excavation: Excavating of trenches.

B. Section 31 2323 - Fill and Backfill: Bedding and backfilling.

C. Section 33 4230 - Stormwater Drains.

1.03 REFERENCE STANDARDS

A. AASHTO M 252 - Standard Specification for Corrugated Polyethylene Drainage Pipe; latest edition.

B. ASTM D3350 - Standard Specification for Polyethylene Plastics Pipe and Fittings Material;

2014.

1.04 SUBMITTALS

A. See Section 01 3000 - Administrative Requirements, for submittal procedures.

PART 2 PRODUCTS

2.01 STORMWATER PIPE MATERIALS

A. Provide products that comply with applicable code(s).

2.02 PIPE ACCESSORIES

A. Fittings: Same material as pipe molded or formed to suit pipe size and end design, in required tee, bends, elbows, cleanouts, reducers, traps and other configurations required.

PART 3 EXECUTION

3.01 TRENCHING

A. Backfill around sides and to top of pipe with cover fill, tamp in place and compact, then complete backfilling.

3.02 INSTALLATION

A. Lay pipe to slope gradients noted on layout drawings; with maximum variation from true slope of 1/8 inch in 10 feet.

B. Connect storm drainage system as shown on plans.

3.03 PROTECTION

A. Protect pipe and bedding cover from damage or displacement until backfilling operation is in progress.

END OF SECTION Enclosure #51

Fire Station #227 11/17/25

PART 1 GENERAL
1.01 SECTION INCLUDES
A. Stormwater drainage piping.
B. Stormwater pipe accessories.
1.02 RELATED REQUIREMENTS
A. Section 31 2316 - Excavation: Excavating of trenches.
B. Section 31 2323 - Fill and Backfill: Bedding and backfilling.
C. Section 33 4230 - Stormwater Drains.
1.03 REFERENCE STANDARDS
A. AASHTO M 252 - Standard Specification for Corrugated Polyethylene Drainage Pipe; latest edition.
B. ASTM D3350 - Standard Specification for Polyethylene Plastics Pipe and Fittings Material; 2014.
1.04 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
PART 2 PRODUCTS
2.01 STORMWATER PIPE MATERIALS
A. Provide products that comply with applicable code(s).
2.02 PIPE ACCESSORIES
A. Fittings: Same material as pipe molded or formed to suit pipe size and end design, in required tee, bends, elbows, cleanouts, reducers, traps and other configurations required.
PART 3 EXECUTION
3.01 TRENCHING
A. Backfill around sides and to top of pipe with cover fill, tamp in place and compact, then complete backfilling.
3.02 INSTALLATION
A. Lay pipe to slope gradients noted on layout drawings; with maximum variation from true slope of 1/8 inch in 10 feet.
B. Connect storm drainage system as shown on plans.
3.03 PROTECTION
A. Protect pipe and bedding cover from damage or displacement until backfilling operation is in progress.