ADDENDUM NO 3 ATTACHMENT A FILE 2 ENGINEERS ESTIMATE ARFQ DEP25-09 KEMPTON REFUSE REHABILITATION.pdf

PDF 259 KB Posted

Attached to
AML-Kempton Refuse Rehabilitation
Solicitation number
ARFQ-0313-DEP2500000009-6
Issued by
Tucker County, West Virginia

About this file

This document appears to be an ADDENDUM NO 3 ATTACHMENT A FILE 2 ENGINEERS ESTIMATE for the KEMPTON REFUSE REHABILITATION project, which is being solicited by the West Virginia Department of Environmental Protection (DEP). The document provides a detailed cost estimate for various bid items related to the rehabilitation of the Kempton Refuse site, including site preparation, AMD treatment system removal, earthwork, drainage and conveyance infrastructure, erosion and sediment controls, and revegetation. The bid items outline quantities, unit prices, and total estimated costs for the project, which is estimated to cost a total of $1,875,220.00.

The document indicates that the DEP reserves the right to request additional information and supporting documentation regarding unit prices if they appear unreasonable. Additionally, the document notes that certain bid items, such as AASHTO #57 limestone bed separation layer, 15-inch HDPE culvert, 42-inch HDPE culvert, and topsoil import, have been removed from the contract. The document does not provide any information related to bid submission deadlines, award dates, or contract term.

View the file

Other files

File Type Posted
TCA ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
GEOTECHNICAL INVESTIGATION ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
Final_ARFQ_0313_DEP2500000009_2_WV_ARFQ_FORM.PDF PDF
CONSTRUCTION DRAWINGS ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
DEP CONSTRUCTION BID SUBMISSION FORMS ARFQ DEP25- 9 AML - KEMPTON REFUSE REHABILITATION.pdf PDF
DLR SUPPLEMENTAL SPECS ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
ADDENDUM NO 3 ARFQ DEP25-09 KEMPTON REFUSE REHABILITATION V1.pdf PDF
TECHNICAL SPECS ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
STORM WATER POLLUTION PREVENTION PLAN PART 1 ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
Final_ARFQ_0313_DEP2500000009_1_WV_ARFQ_FORM.PDF PDF
GROUNDWATER PROTECTION PLAN ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
STORM WATER POLLUTION PREVENTION PLAN PART 2 ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
AVS FORM AND INSTRUCTION ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
Final_ARFQ_0313_DEP2500000009_3_WV_ARFQ_FORM.PDF PDF
ADDENDUM 3 ATTACHMENT A FILE 1 PAGES 1-20.pdf PDF
ADDENDUM NO 1 ARFQ DEP25-09 KEMPTON REFUSE.pdf PDF
BABA REQUIREMENTS ARFQ DEP25-9 KEMPTON REFUSE REHABILITATION.pdf PDF
ADDENDUM NO 2 ARFQ DEP25-09 KEMPTON REFUSE REHABILITATION.pdf PDF
ADDENDUM 3 ARFQ DEP25-09 ATTACHMENT A FILE 2 PAGES 21-40.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM

NO. DECRIPTION UNIT QTY UNIT PRICE AMOUNT

1 MOBILIZATION AND DEMOBILIZATION (LIMITED TO 5% OF TOTAL BID) LS 1 $80,000.00 $80,000.00

2 CONSTRUCTION LAYOUT (LIMITED TO 5% OF TOTAL BID) LS 1 $80,000.00 $80,000.00

3 QUALITY CONTROL (LIMITED TO 3% OF TOTAL BID) LS 1 $50,000.00 $50,000.00

4.1 SITE PREPARATION (LIMITED TO 10% OF TOTAL BID) LS 1 $150,000.00 $150,000.00

4.2 EXISTING AMD TREATMENT SYSTEM REMOVAL LS 1 $125,000.00 $125,000.00

4.3 AASHTO #1 AGGREGATE TON 900 $35.00 $31,500.00

4.4 CLASS 1, 1 1/2" CRUSHER RUN AGGREGATE TON 750 $35.00 $26,250.00

4.5 SEPARATION FABRIC SY 1,000 $2.00 $2,000.00

4.6 STABILIZATION STONE TON 200 $35.00 $7,000.00

4.7 STABILIZATION FABRIC SY 250 $2.00 $500.00

4.8 TEMPORARY BRIDGE EA 1 $10,000.00 $10,000.00

4.9 6-FOOT CHAIN LINK FENCING LF 700 $45.00 $31,500.00

4.10 24-FOOT WIDE DOUBLE LEAF VEHICULAR CHAIN LINK GATE EA 2 $2,000.00 $4,000.00

4.11 DITCH RECLAMATION LF 1,650 $30.00 $49,500.00

4.12 SODA ASH BRIQUETTES (50LB BAG) EA 100 $50.00 $5,000.00

5.1 STABILIZED CONSTRUCTION ENTRANCE TON 300 $50.00 $15,000.00

5.2 SILT FENCE LF 6,500 $5.00 $32,500.00

5.3 ROLLED EROSION CONTROL PRODUCT SY 3,500 $6.00 $21,000.00

5.4 STONE CHECK DAM TON 300 $45.00 $13,500.00

6.1 REVEGETATION (PER PLAN VIEW ACRE) AC 4 $2,250.00 $9,000.00

6.2 WETLAND BED PREPARATION AND SEED MIX (PER PLAN VIEW ACRE) AC 0.25 $3,000.00 $750.00

6.3 POLLINATOR SEED MIX (PER PLAN VIEW ACRE ACRE) AC 8 $3,000.00 $24,000.00

7.1 16OZ M288 CLASS 1 NON-WOVEN GEOTEXTILE SY 15,200 $2.00 $30,400.00

7.2 40 MIL HDPE TEXTURED LINER (BOTH SIDES) SY 8,100 $2.00 $16,200.00

7.3 AASHTO #57 (LIMESTONE BED SEPARATION LAYER)(REMOVED FROM CONTRACT) TON 0 $0.00 $0.00

7.4 AASHTO #4 (AMD SYSTEM LIMESTONE BED AND LIMESTONE POND REHAB) TON 7,500 $45.00 $337,500.00

7.5 8 INCH SOLID SDR 35 PIPE LF 930 $70.00 $65,100.00

7.6 8 INCH PERFORATED SDR 35 PIPE LF 690 $70.00 $48,300.00

7.7 15-INCH HDPE CULVERT (REMOVED FROM CONTRACT) LF 0 $0.00 $0.00

7.8 42-INCH HDPE CULVERT(REMOVED FROM CONTRACT) LF 0 $0.00 $0.00

7.9 SPLASH PAD EA 5 $500.00 $2,500.00

7.10 CLEANOUT EA 9 $65.00 $585.00

7.11 4 INCH PVC GATE VALVE (COMPLETE) EA 1 $600.00 $600.00

7.12 8 INCH PVC GATE VALVE (COMPLETE) EA 8 $600.00 $4,800.00

7.13 SIPHON SYSTEM (COMPLETE) EA 2 $5,000.00 $10,000.00

7.14 PIPE ANCHOR EA 25 $1,200.00 $30,000.00

7.15 8 FT X 8 FT CONCRETE VAULT EA 2 $10,000.00 $20,000.00

7.16 TYPE B INLET EA 1 $3,500.00 $3,500.00

7.17 WEIR STRUCTURE (CAST IN PLACE) EA 1 $7,500.00 $7,500.00

7.18 SEEP COLLECTOR WITH PIPES LF 450 $65.00 $29,250.00

7.19 SEEP COLLECTOR WITHOUT PIPES CY 550 $10.00 $5,500.00

7.20 SLIP REPAIR BENCH DRAIN LF 500 $60.00 $30,000.00

7.21 SLIP REPAIR CONVEYANCE PIPE LF 100 $55.00 $5,500.00

7.22 2 FT D X 2 FT BW, RIPRAP "TRAPEZOIDAL" CHANNEL WITH GCL LF 230 $100.00 $23,000.00

7.23 2 FT D X 2 FT BW, GROUTED RIPRAP "TRAPEZOIDAL" CHANNEL WITH GCL LF 368 $115.00 $42,320.00

7.24 3 FT D X 6 FT BW, GROUTED RIPRAP "TRAPEZOIDAL" CHANNEL WITH GCL LF 630 $230.00 $144,900.00

7.25 3 FT D X 8 FT BW, RIPRAP "TRAPEZOIDAL" CHANNEL WITH GCL LF 157 $200.00 $31,400.00

7.26 3 FT D X 10 FT BW, GROUTED RIPRAP "TRAPEZOIDAL" CHANNEL WITH GCL LF 132 $300.00 $39,600.00

7.27 GROUT ANCHOR/KEY LF 225 $40.00 $9,000.00

7.28 WALKWAY, WALKWAY FOOTING, SAFETY RAILING EA 1 $15,000.00 $15,000.00

7.29 SUMP EA 3 $1,000.00 $3,000.00

7.30 CONCRETE CHANNEL (CAST-IN-PLACE) EA 2 $5,000.00 $10,000.00

7.31 AASHTO #1 (LIMESTONE BED SEPARATION LAYER) TON 820 $35.00 $28,700.00

7.32 16-INCH SDR-17 CULVERT LF 180 $80.00 $14,400.00

7.33 AASHTO #57 (LIMESTONE BED PIPE TRENCH LAYER) TON 680 $35.00 $23,800.00

7.34 2 FT D X 2 FT BW, GROUTED RIPRAP "TRAPEZOIDAL" CHANNEL LF 18 $100.00 $1,800.00

7.35 2 FT D X 4 FT BW, GROUTED RIPRAP "TRAPEZOIDAL" CHANNEL LF 61 $115.00 $7,015.00

7.36 2 FT D X 10 FT BW, GROUTED RIPRAP "TRAPEZOIDAL" CHANNEL LF 52 $300.00 $15,600.00

8.0 TOPSOIL IMPORT(REMOVED FROM CONTRACT) CY 0 $4,500.00 $0.00

9.0 SUBSIDENCE DEPRESSION REPAIR TON 10 $45.00 $450.00

10.0 ADMINISTRATION COST (LIMITED TO 3% OF TOTAL BID) LS 1 $50,000.00 $50,000.00

TOTAL $1,875,220.00

KEMPTON REFUSE REHABILITATION

ENGINEERS ESTIMATE

The DEP reserves the right to request additional information and supporting documentation regarding unit prices when the unit price appears to be unreasonable.

rhovatter Stamp rhovatter Pen phakinin

File details come from the government source that posted it. Updated .