Addendum No 2~1.pdf
PDF 3 MB Posted
- Solicitation number
- S-KN0040-00017044
- Issued by
- Oregon
About this file
This Addendum No. 2 document supports the City of Pendleton, Oregon's WWTRRF 2025 Improvements Project for West Secondary Clarifier Rehabilitation. The project scope includes mobilization and demobilization, demolition and salvage, west clarifier rehabilitation and equipment installation, topping grout placement, concrete sump crack repair, miscellaneous concrete work, installation of 20 secondary clarifier floor pressure relief valves, miscellaneous metals coating, and clarifier mechanism coating. The contract completion deadline is June 30, 2027. Sealed bids were due June 25, 2026 at 2:00 p.m., with a mandatory pre-bid meeting and site visit scheduled for June 3, 2026 from 12:00 to 1:00 p.m. at 4300 SW Houtama Road, Pendleton. Prequalification applications were required by June 24, 2026 at 1:00 p.m. Award was anticipated at the City Council meeting on July 7, 2026.
Pricing is structured on a unit price and lump sum basis, with bid items including a $100,000 contingency allowance for unanticipated work such as unmarked utilities and unforeseeable subsurface conditions, which is payable only through work change directives on a time and materials basis. The project is funded through a Clean Water State Revolving Fund loan and is subject to federal disadvantaged business enterprise provisions and prevailing wage requirements under Oregon Bureau of Labor and Industries standards and the Davis-Bacon Act, whichever is higher. All contractors and subcontractors must hold current Oregon Public Works Contractor licenses, and all iron and steel products must meet American Iron and Steel requirements. The contractor assumes all costs for temporary facilities, dewatering, equipment modifications, waste disposal, environmental controls, and any night, weekend, or holiday work required to maintain facility operations with a maximum 90-consecutive-day outage and at least one secondary clarifier operational at all times. A 5% bid bond is required, and contractors with contract prices exceeding $100,000 must file a $30,000 Statutory Public Works Bond before commencing work. Performance and payment bonds in the full contract amount and Certificate of Insurance naming the City as co-insured are required, with liquidated damages of 0.1% per calendar day of total contract cost for missed completion dates.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WWTRRF 2025 Improvements – West Secondary Clarifier Rehab – Addendum No. 2
BIDDER'S ACKNOWLEDGMENT:
Company Name (please print)
Bidder's Name (please print)
Signature
Title
Address
City, State
Proposal - Page 3 of 4
WWTRRF IMPROVEMENTS PROJECT 2025
WEST SECONDARY CLARIFIER REHABILITATION
Time of Completion: No later than June 30, 2027
Base Bid Items
Bid items shall include all incidental cost, see Division 00 Section 13.0. Reference Section 01 20 00 – Measurement and Payment for a description of the Bid Items.
Item Approx. Extended No. Quantity Item with Unit Price Bid Unit Price Total Bid Item
Approx.
Qty
Item Description*
Unit Price Extended Price
1. 1 LS Mobilization/Demobilization
2. 1 LS Demolition/Salvage
3. 1 LS West Clarifier Rehab and Equipment Installation
4. 1 LS Furnish and Place Topping Grout
5. 1 LS Concrete Sump Crack Repair
6. 1 LS Miscellaneous Concrete Work
7. 20 EA Secondary Clarifier Floor Pressure Relief Valve Installation
8. 1 LS Miscellaneous Metals Coating
9. 1 LS Clarifier Mechanism Coating
10. 1 LS Contingency Allowance $100,000 $100,000
*Note to Bidders: Items outside the definition of the bid items mentioned here are considered incidental to the project, see Division 00 Section 13.0 for more details. It is the bidder’s responsibility to ensure that all project related costs are included in the Grand Total Bid Amount as defined in the bid documents (Drawings and Specifications). Systems that cross physical boundaries, such as utility feeds, may be allocated proportionately to either bid items and at the discretion of the bidder.
GRAND TOTAL BID AMOUNT:
CITY OF PENDLETON WWTRRF 2025 IMPROVEMENTS
WEST SECONDARY CLARIFIER REHAB 225096-001
MEASUREMENT AND PAYMENT 01 20 00 - 1
C. West Clarifier Rehabilitation and Equipment Installation
1. This item applies to furnishing and installing the new clarifier equipment in the west secondary clarifier. Payment for this item shall include all costs for materials, labor, and equipment associated with furnishing and installing the clarifier equipment; platform, bridges, and stairways; re-installation of the anti-rotation baffle with new wipers; re-installation of the local control station;
reinstallation of the launder brush system; and instrumentation, electrical, and controls for a complete and operable clarifier. Measurement for this item will be by lump sum.
D. Furnish and Place Topping Grout
1. This item applies to furnishing and placing the topping grout with the existing clarifier mechanism on the floor of the west secondary clarifier including dewatering as required. This item will be measured by the lump sum. Payment for this item includes all costs associated with furnishing and placing the topping grout to complete the installation of the clarifiers.
E. Concrete Sump Crack Repair
1. This item applies to repair of cracks in the existing sump to prevent groundwater infiltration as shown on the drawings and described in the specifications. This work shall include dewatering as required to perform the work. This item will be measured by the lump sum.
F. Miscellaneous Concrete Work
1. This item shall include all costs for materials, labor and equipment associated with constructing the concrete bridge anchor blocks and the concrete slabs for the stairs as shown on the drawings, as well as any site restoration needed at the completion of construction. Measurement for this item shall be by lump sum.
G. Secondary Clarifier Floor Pressure Relief Valve Installation
1. This item shall include all costs for materials, labor and equipment to install floor pressure relief valves as shown on the drawings and described in the specifications including dewatering as required to complete the work.
Measurement for this item shall be by each floor pressure relief valve installed.
H. Miscellaneous Metals Coating
1. This item includes all costs for cleaning, surface preparation, and coating Miscellaneous Metals as shown on the drawings and described in the specifications. Measurement for this item shall be by lump sum.
I. Clarifier Mechanism Coating
1. This item includes all costs for cleaning, surface preparation, and coating the clarifier mechanism as shown on the drawings and described in the specifications. Measurement for this item shall be by lump sum.
J. Contingency Allowance
1. This is a contingency item to be paid on a time and materials charge account basis to reimburse the Contractor for work not identified or implied in the contract documents. The Contingency Allowance is shown as an amount on the Bid Schedule to be added into the Total Bid Amount. This bid item is intended
CITY OF PENDLETON WWTRRF 2025 IMPROVEMENTS
WEST SECONDARY CLARIFIER REHAB 225096-001
MEASUREMENT AND PAYMENT 01 20 00 - 2
to address unanticipated items such as unmarked utilities, unforeseeable subsurface conditions, and conditions that are clearly different than those indicated in the contract documents.
2. The Engineer will provide a Work Change Directive document on the terms for completing the additional work. Within five days after the request from the Engineer, the Contractor shall submit to the Engineer a complete price breakdown of labor, equipment, and materials to complete the additional requested work not included in the contract documents. Any Contingency Allowance amount will only be paid to the Contractor through a work change directive on a time and materials basis.
3. All work is at the directive of the Engineer. Any work completed without the written authorization of the City of Pendleton and the Engineer will be denied payment.
1.3 SCHEDULE OF VALUES
A. The Contractor shall prepare and submit a detailed Schedule of Values to the Engineer and Owner within 30 days from the date of Notice to Proceed. The detailed Schedule of Values shall be based on the values listed in the Bid Schedule. Because the ultimate requirement is to develop a detailed Schedule of Values, sufficient detailed breakdown shall be provided to meet this requirement. The Engineer shall be the sole judge of acceptable numbers, details and description of values established. If, in the opinion of the Engineer, a greater number of Schedule of Values items than proposed by the Contractor are necessary, the Contractor shall add the additional items so identified by the Engineer.
B. The Contractor, Owner, and Engineer shall meet and jointly review the detailed Schedule of Values within 35 days from the date of Notice to Proceed. The value allocations and extent of detail shall be reviewed to determine any necessary adjustments to the values and to determine if sufficient detail has been proposed. Any adjustments deemed necessary to the value allocation or level of detail shall be made by the Contractor and a revised detailed Schedule of Values shall be submitted within 40 days from the date of Notice to Proceed.
1.4 CHANGES TO SCHEDULE OF VALUES
A. Changes to the schedule of values shall be made to reflect Owner approved change orders.
B. In the event that the Contractor and Engineer agree to make adjustments to the original Schedule of Values because of inequities discovered in the original accepted detailed Schedule of Values, increases and equal decreases to values.
PART 2 - PRODUCTS NOT USED
PART 3 - EXECUTION NOT USED
END OF SECTION 01 20 00