This document is Addendum No. 2 for the Invitation to Bid (ITB) DMS-23/24-057 for Lawn Care Services - Tampa Group issued by the Florida Department of Management Services. The ITB includes amendments to the Statement of Work, such as requirements for irrigation system maintenance, and the replacement of the original Price Sheet. The solicitation is for lawn care services at three locations in the Tampa, Florida area. Responses are due according to the original ITB timeline, and the contract will be awarded to the overall lowest responsive and responsible bidder.
The revised Price Sheet and clarifications on the scope of work, including pressure washing requirements and plans for resodding, are provided in this addendum. Respondents are instructed to use the REVISED Attachment D - Price Sheet, which now includes pricing for all three locations. The Department has indicated the current irrigation systems are in good working order, and the successful contractor will have the opportunity to inspect them prior to commencing work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lawn Care Services – Tampa Group
Invitation to Bid (ITB)
DMS-23/24-057
Addendum No. 2
FAILURE TO FILE A PROTEST WITHIN THE TIME PRESCRIBED IN SUBSECTION 120.57(3), FLORIDA STATUTES (AS ALTERED BY SECTION 110.123(3)(D)4, FLORIDA STATUTES), OR FAILURE TO POST
THE BOND OR OTHER SECURITY REQUIRED BY LAW WITHIN THE TIME ALLOWED FOR FILING A
BOND SHALL CONSTITUTE A WAIVER OF PROCEEDINGS UNDER CHAPTER 120, FLORIDA
STATUTES.
Any protest concerning this agency decision or intended decision must be timely filed with the Agency Clerk. Protests may be filed by courier, hand delivery, or U.S. mail at Department of Management Services, Office of the General Counsel, Attention: Agency Clerk, 4050 Esplanade Way, Suite 160, Tallahassee, FL 32399-0950. Protests may also be filed by fax at 850-922-6312 or by email at agencyclerk@dms.fl.gov. It is the filing party’s responsibility to meet all filing deadlines.
DMS-23/24-057, Addendum 2
ITB No. DMS-23/24-057 is hereby amended within Addendum No. 2 as noted below.
All language additions are underlined, and all language deletions are stricken, respectively. All are highlighted for ease of identification.
In the event of a conflict between previously released information and the information contained herein, the information herein shall control. The information included in this addendum is now made part of this solicitation. This addendum does not need to be returned with the response.
Amendments are as follows:
1. Attachment A-Statement of Work, Section 2.6.1, is hereby modified as follows:
2.6.1 All maintenance, repairs, or alterations to the existing irrigation system (excluding pumps and timers), are the responsibility of the Contractor and must be performed by an Irrigation Specialty Contractor certified pursuant to Rule 61G4-15.035, Florida Administrative Code.
The irrigation system will be maintained by the Contractor through head- to-head checks, balancing, and adjustments. Spray pattern of each sprinkler head to be maintained for proper water distribution and to minimize overflow of water onto sidewalks, driveways, roads, and facilities.
The cost of any repairs, replacements, or alterations made to any portion of the irrigation system and/or parts which have been damaged by a third party shall be the Department’s responsibility.
The Contractor shall charge the Department its additional irrigation services hourly price and percentage mark up on parts, if required.
2. Attachment D – Price Sheet is deleted in its entirety and replaced with REVISED
Attachment D – Price Sheet.
All references to Attachment D – Price Sheet contained in ITB No. DMS-23/24-057 are hereby amended to refer to REVISED Attachment D – Price Sheet.
End of Addendum 2.
QUESTIONS AND ANSWERS
All written questions are reproduced in the same format as submitted by the Respondent.
NO. QUESTION ANSWER
1.
Why is Lawn Care Services - Tampa Group;
DMS-23/24-057 being rebid?
Previous solicitations have been issued without success.
2.
Beside pressure washing concrete, could you let us know what other surfaces you expect us to clean?
Are we expected to pressure wash any buildings?
a. There are no other surfaces that will require pressure washing.
b. No.
3.
Is Pest Control twice a year along with the fertilization?
Yes.
4.
Also, section 2.2 Trimming and Edging Service paragraph 2.2.6 states: “ Tree branches must be thinned and elevated as needed. This applies to tree branches, limbs, and palm fronds fifteen (15) feet or less from the ground.”
Is this expected as part of the regular landscape maintenance service or part of Section 3 Other services paragraph 3.3 Tree trimming?
The requirements of Attachment A – Statement of Work, Section 2.2 are part of regular services.
5.
Bids are required for 3 locations with separate pricing sheets for each property.
Will the contract be awarded for the overall lowest price of the 3 properties combined or individually?
See Section 4.1, Basis of Award, of the ITB document.
6.
Both Hargrett and Trammell locations have numerous large oak trees , do you require all the leaves in the parking lots, walkways, and hard surfaces to be removed each service?
See Attachment A – Statement of Work, Section 2.3, Debris Removal Service.
7.
Where possible is it acceptable to blow leaves into grassy areas and mulch them up with mowers as a solution to scope of work 2.2.8?
No.
8.
Section 2.2.7 refers to “selective pruning and hard cutbacks” . What does this pruning and hard cutback pertain to ?
Shrubbery.
9.
Section 2.4.1 refers to fertilization of all grass , trees, shrubs, and plants. During our walk through of all 3 locations no shrubs nor plants were observed.
There are no plans to install new plants or shrubbery.
What plans, if any, do you have regarding installation of any new plants and shrubs?
We are asking this so that we can factor in any additional fertilization and irrigation costs.
10.
Section 2.4.1 requires lawn areas be treated with broadleaf weed control etc. During our walk through we noted that most of the grass areas are in very poor health and full of weeds.
Applying weed control will remove these weeds but will leave large areas with just dirt.
Does the state have any plans to resod at any of the 3 locations?
The Department does have plans for resodding and will work with the selected vendor on the best approach and cost.
Any resodding work, when required, will be considered outside the scope of this contract.
11.
Section 2.5.2 requires the contractor to maintain a minimum depth of 3 inches of mulch throughout the year. This section also requires re-mulching of the properties in April and October.
By definition, if we are maintaining the mulch at 3 inches , why is there a need to re-mulch twice a year?
Is this because you require removal of the old mulch and installation of new in April and October?
Yes. The old mulch must be removed and replaced with new mulch in April and October as indicated in Attachment A- Statement of Work, Section 2.5.
12.
During our walk throughs we noted many areas were not mulched to the required 3-inch depth.
Are we to assume that the successful bidder will be responsible for the rectification of this situation?
Yes. Any areas devoid of mulch will be required to have mulch installed in April per Attachment A – Statement of Work, Section 2.5.2.
13.
Section 2.6.1 states “All maintenance repairs or alterations to the existing irrigation system ( excluding pumps and timers) are the responsibility of the contractor”.
In the event of a line break or irrigation issue which has not been caused by the contractor, who is responsible for the associated costs?
See Addendum 2, item 1.
14.
Irrigation systems- Please can you confirm that the irrigation systems at both Grizzle and Trammell are currently fully operational and in good working order?
Will the successful contractor get the opportunity to confirm the status of these systems?
a. Both are in good working order.
b. Yes. The Contractor may inspect the irrigation system during the mandatory site visit, and if awarded, before work begins on each occasion.
15.
Attachment D -Price sheets. You appear to have issued requests for pricing on Trammell building twice and omitted Hargrett. We assume this is a typo.
Are you going to reissue the price sheets, or should we amend manually before submitting?
Please use REVISED Attachment D – Price Sheet, provided as part of Addendum 2.
16.
What is to be pressure washed at each site See Attachment A, Statement of Work, Section 3.1.
17. Approximate square footage of each area at the sites that will be pressure washed
This information is not available.
18. how often should each site be pressure washed See Attachment A, Statement of Work, Section 3.1.
19. what is the size of the crews that typically perform these contracts for each site
This information is not available.
20. Question what was the breakdown of the previous contract that was awarded
See Section 1.1 of the Invitation to Bid document.
File details come from the government source that posted it. Updated .