Addendum Four.pdf

PDF 228 KB Posted

Attached to
RFB-71-27 KHP Stalls & Mats New Comp Barn BP-2
Solicitation number
RFB 785 2700000110 5
Issued by
Kentucky

About this file

This is Addendum Four issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration for Invitation to Bid No. RFB-71-27, a re-advertisement of RFB-264-25 for stalls and mats in the new Competition Barns BP-2 at Kentucky Horse Park in Lexington, Kentucky. The addendum, dated September 16, 2026, addresses contractor questions and provides architectural specifications clarifications. Key specifications clarified include requirements for powder-coated finishes over 14-gauge 2-inch square galvanized tube frames, light gray coloring to match recently constructed barns C and D (to be selected by the architect and owner post-award), 1-inch-diameter tubes spaced 3 inches on center for grillwork, 2-inch square tubing for all door frames and stall frames, and light gray HDPE panels. The addendum also adds three approved manufacturers: Triton Barn Systems, Barnwalkers, and Grytfit/Humane Manufacturing LLC to the specification manufacturer lists.

No pricing terms, bid amounts, response deadlines, site visit requirements, bidder conferences, or contract term information is provided in this addendum document. The addendum serves solely to clarify specifications and expand the list of acceptable manufacturers in response to contractor inquiries submitted during the bidding phase.

View the file

Other files

File Type Posted
Final_RFB_785_2700000110_5_SO_FORM.PDF PDF
Final_RFB_785_2700000110_2_SO_FORM.PDF PDF
Addendum Three.pdf PDF
Final_RFB_785_2700000110_1_SO_FORM.PDF PDF
Final_RFB_785_2700000110_3_SO_FORM.PDF PDF
Addendum Two.pdf PDF
Final_RFB_785_2700000110_4_SO_FORM.PDF PDF
Addendum One.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF KENTUCKY

DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES

DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION

INVITATION TO BID NO: RFB-71-27

FOR: Re-Advertisement of RFB-264-25 Stalls and Mats New Competition Barns BP-2 Kentucky Horse Park Lexington, Kentucky

DATE: September 16, 2026

RFB-785-2700000110

ADDENDUM NO. Four (4)

BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING

UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.

Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.

END OF ADDENDUM

Invitation to Bid No. RFB-71-27 For: Re-Advertisement of RFB-264-25 Stalls and Mats New Competition Barns BP-2 Kentucky Horse Park Lexington, Kentucky

Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration

KHP - Stalls and Mats for New Competition Barns BP-2 – Re Bid

665-CBTF-HP97-01

Kentucky Horse Park Lexington, KY

EOP Architects • 201 W. Short Street • Suite 700 • Lexington, KY 40507 • 859.231.7538 • fax 859.255.4380 • www.eopa.com

Addendum 4

Date: 09-15-2026

Addendum 4 Items:

Contractor Questions:

1. Finish: Is a powder-coated finish required, or would hot-dip galvanized steel be acceptable?

Answer: A powder-coated finish is required over 14-gauge 2” square galvanized tube frame per the specifications.

2. Powder-Coat Color: If powder coating is required, please provide the specified RAL color number.

Answer: Color to be selected by Architect and owner after award of bid, but will be a light gray to match the recently constructed barns C and D.

3. Grill Tubing: May the grillwork use 7/8-inch-diameter tubes spaced 3-1/4 inches on center, or are 1-inch-diameter tubes spaced 3 inches on center required?

Answer: Per the specifications, 1-inch-diameter tubes spaced 3 inches on center are required.

4. Door Frame: The stall frame will be constructed from 2-inch square tubing. May the door frame be constructed from 1-3/4-inch square tubing?

Answer: No, all square tubing to be 2” square per the specifications and drawings.

5. Puckboard Color: Please confirm whether the puckboard should be white.

Answer: If you are referring to the HDPE panels, per the specifications, the color is to be light gray to match the recently constructed barns C and D, and to be selected by Architect and owner after award of bid.

Architectural Addenda Items (A):

Specifications:

Item A1: See specification Section 110001: Refer to Section 2.1 MANUFACTURERS. Add f. Triton Barn Systems

Item A2: See specification Section 110001: Refer to Section 2.1 MANUFACTURERS. Add g.

Barnwalkers

KHP – Stalls and Mats for New Competition Barns BP-2 – Rebid Kentucky Horse Park

Addendum-4 BP-2 Account # 665-CBTF-HP97-01

EOP Architects • 201 W. Short Street • Suite 700 • Lexington, KY 40507 • 859.231.7538 • fax 859.255.4380 • www.eopa.com

Item A3: See specification Section 096540: Refer to Section 2.1 MANUFACTURERS. Add e.

Grytfit / Humane Manufacturing LLC.

End of Addendum

Addendum Four
Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM

CBTF_BP-2_Re Bid_Addendum 4