Addendum for Questions and Answers RFP - DS2401.pdf
PDF 86 KB Posted
- Solicitation number
- RFP DS2401
- Issued by
- Lancaster County, Nebraska
About this file
This document is an addendum to a Request for Proposal (RFP) issued by the Nebraska Department of Natural Resources (NeDNR) for "Regional Extreme Precipitation-Frequency Estimation for Nebraska". The addendum provides answers to questions submitted by potential bidders, which cover topics such as the proposal due date, the independent review board, and the project description and scope of work. NeDNR expects the successful consultant to provide/contract with the independent review board and anticipates two online review board meetings, with the possibility of additional meetings if necessary.
The RFP seeks a qualified contractor to provide the requested services, with the resulting contract potentially not being exclusive. Bidders are allowed to include a budget narrative/justification, including supporting pricing assumptions, with their cost proposals. Unnamed staff (TBD) can be included in the proposal, though the project manager and other key staff members should be identified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Evaluation_Criteria.docx | DOCX document | |
| ListofRespondents_DS2401.docx | DOCX document | |
| Intent To Award Letter.pdf | ||
| RFP_DS2401.pdf | ||
| RFP_DS2401.docx | DOCX document | |
| Cost Proposal.xlsx | XLSX spreadsheet | |
| Addendum for Questions and Answers RFP - DS2401.pdf | ||
| RFP_DS2401.pdf | ||
| Evaluation_Criteria.docx | DOCX document | |
| Cost Proposal.xlsx | XLSX spreadsheet | |
| RFP_DS2401.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF NEBRASKA ADDENDUM, QUESTIONS and ANSWERS
ADDENDUM 1, QUESTIONS and ANSWERS
Date: July 10, 2024
To: All Bidders
From: Tim Gokie, Project Manager
Nebraska Department of Natural Resources (NeDNR)
RE: Addendum for Request for Proposal Number DS2401 to be opened July 30, 2024, at 2:00 p.m. Central Time
Questions and Answers
Following are the questions submitted and answers provided for the above-mentioned Request for Proposal. The questions and answers are to be considered as part of the Request for Proposal.
It is the Bidder’s responsibility to check the State Purchasing Bureau website for all addenda or amendments.
Question Number
RFP
Section
Reference
RFP
Page
Number
Question State Response
1. I. Procurement Page 2 Is the proposal due date and time the same as proposal opening?
Yes. All proposals successfully uploaded before and by the Opening Date and Time will be accepted and evaluated.
2. V. A. and E.
Project Description and Scope of Work
Page 28 For the purposes of an independent review of the techniques and results, does Nebraska expect the consultants to provide/contract the independent review board or will Nebraska assemble the board?
Yes. NeDNR expects the successful consultant to provide/contract with the independent review board.
3. V. A. and E.
Project Description and Scope of Work
Page 28 To what extent would Nebraska like to hold review board meetings (i.e., in-person versus on-line;
monthly versus quarterly)?
NeDNR anticipates there will be two on-line review board meetings.
One meeting will be early in the project to discuss the data and techniques that will be utilized. The other will be at the end of the
Question Number
RFP
Section
Reference
RFP
Page
Number
Question State Response project to discuss and review the results.
NeDNR and the successful contractor will determine if additional review board meetings are needed, or if an in-personal review board meeting is necessary.
4. VI. 4. Proposal Instructions
Page 30 Can the State confirm that offerors are allowed to include a budget narrative/justification, including supporting pricing assumptions, with their Cost Proposals?
Yes.
5. VI. 4. A. 1. i.
Summary of Bidder’s Proposed Personnel
Page 32 May unnamed staff (TBD) be included in the proposal?
The project manager and other key staff members should be identified. Others can be included as to be determined.
This addendum will become part of the proposal and should be acknowledged with the Request for Proposal.