Addendum 3 Questions and Answers for IFB No. 27-02-ASO: 12th and 13th Floor Carpet Tile Replacement
This document is an addendum containing questions and answers for a sealed bid solicitation issued by the State of Hawaii, Department of Human Resources Development, for carpet tile replacement services on the 12th and 13th floors of the Leiopapa a Kamehameha Building in Honolulu. The project involves removal of existing carpeting and installation of modular carpet tile (24-inch by 24-inch, solution-dyed nylon with minimum 22 ounces per square yard face weight, PVC-free backing, and CRI Green Label Plus certification) on two floors. A non-mandatory jobsite visit for inspection of the carpet tile area was scheduled for October 15, 2026, with vendor questions due October 20, 2026. Sealed bids were due November 2, 2026 at 2:00 p.m. Hawaii Standard Time. The 12th floor is scheduled for completion by January 6, 2027, and the 13th floor by February 23, 2027, with liquidated damages of $50 per calendar day for phase completion delays. The contract term is one year from the effective date, with one optional six-month extension at the State's discretion.
The estimated contract value ranges from $275,000 to $360,000, including contingency. Bidders must submit prices for four line items covering 12th floor carpet tile, 12th floor contingency (10 percent), 13th floor carpet tile, and 13th floor contingency (10 percent), with all prices inclusive of General Excise Tax. Regarding asbestos concerns, Addendum 2 references the State's "Departmental Asbestos Plan - Building Inventory," which indicates no known Asbestos Containing Materials (ACM) in the project area; however, the awarded contractor remains responsible for conducting its own testing if suspect materials are encountered and for maintaining worker safety. A bid bond of at least 5 percent of total bid price is required, with performance and payment bonds equal to 100 percent of contract price. Bidders must hold a valid Hawaii State contractor license with C-7 classification and meet experience requirements, including prevailing wage compliance and an 80 percent Hawaii resident workforce. Hawaii Bidder Preference (5 percent for evaluation), Taxpayer Preference, and Apprenticeship Agreement Preference are available.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 2 Brand Asbestos Report Timeline.pdf | ||
| Attachment 2 Qualification Form.docx | DOCX document | |
| Attachment 7 Safety and Health Program Certification Form.docx | DOCX document | |
| Attachment 5 Preference Declaration Form.docx | DOCX document | |
| Attachment 6 HRS 103 55.5 Certification Form.docx | DOCX document | |
| Attachment 3 Carpet Tile Product Form.docx | DOCX document | |
| Attachment 4 Joint Contractor and Subcontractor Listing Form.docx | DOCX document | |
| State Holidays 2026 and 2027.pdf | ||
| Attachment 1 Bidder Form.docx | DOCX document | |
| AG008 103D.pdf | ||
| IFB No. 27-02-ASO - 12th and 13th Floor Carpet Tile (2026-10-01).pdf | ||
| Attachment 8 LAK 12th and 13th Floor Sketches.pdf | ||
| Addendum 1 12th and 13th Floor Carpet Tile.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions for solicitation
IFB No. 27-02-ASO (B27000484)
12th and 13th Floor Carpet Tile Replacement 10/26/2026
1. Will there be a jobsite visit to inspect the carpet tile area?
As specified in the IFB, the date earmarked for site visits was October 15, 2026.
2. Regarding the recent addendum, has the existing flooring and adhesive been tested and who would arrange and pay for testing or abatement if needed?
Please refer to Addendum 2, which provides the State’s “Departmental Asbestos Plan – Building Inventory” (Asbestos Plan). With respect to Asbestos Containing Materials (ACM), the Asbestos Plan indicates “No.” The State is not aware of any ACM located in the project area. However, regardless of prior findings, the awarded contractor shall maintain its duty to keep its workers safe and should conduct its own testing if suspect materials are encountered.