This is Addendum 2 to an Invitation for Bids (IFB No. 27-02-ASO) issued by the State of Hawaii, Department of Human Resources Development, for carpet tile replacement services on the 12th and 13th floors of the Leiopapa a Kamehameha Building (LAK) in Honolulu. The addendum amends the original IFB to address asbestos reporting, carpet tile brand specifications, procurement timeline, and project timeline. The carpet tile must be a Mannington Commercial product (such as Moso or Precision) or a comparable non-Mannington product that has been qualified in advance by the State. Bidders proposing alternative products must submit a request for qualification by October 30, 2026 at 4:30 p.m. Hawaii Standard Time, with the State responding by November 5, 2026. The revised bid submission deadline is November 2, 2026 at 2:00 p.m. HST. The public notice was issued October 1, 2026, with a mandatory site visit on October 15, 2026, and vendor questions due October 20, 2026 at 2:00 p.m. HST. The contract term is one year from the effective date with one optional six-month extension at the State's discretion.

The project comprises two phases: Phase 1 (12th floor) with anticipated completion by January 6, 2027, and Phase 2 (13th floor) with completion by February 23, 2027. The carpet tile contractor is responsible for removing existing carpet and installing modular carpet tile while coordinating with the State and the State's furniture contractor. Liquidated damages of $50 per calendar day apply for delays in phase completion dates. The estimated contract value ranges from $275,000 to $360,000, including contingency, with bidders required to submit prices for four line items (12th floor carpet tile, 12th floor contingency at 10 percent, 13th floor carpet tile, and 13th floor contingency at 10 percent), all prices inclusive of General Excise Tax. A bid bond of at least 5 percent of the total bid price is required, along with performance and payment bonds equal to 100 percent of the contract price. Hawaii Bidder Preference (5 percent for evaluation) and Taxpayer Preference are available. The contract includes a one-year workmanship warranty and a 10-year manufacturer's warranty.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION FOR BIDS

DHRD IFB NO. 27-02-ASO

ADDENDUM 2

1. Addendum Purpose

Through this Addendum 2, the STATE has amended the IFB regarding the following:

Asbestos report

Carpet tile brand requirements

Procurement timeline and bid submission due date

Anticipated project timeline

2. Asbestos Report

An excerpt of the State’s “Departmental Asbestos Plan – Building Inventory” is included below. Please see the “State OƯice Tower” line highlighted in yellow. “State OƯice Tower” is the former name of “LAK”

A PDF of the full plan is available at the following link:

https://ags.hawaii.gov/publicworks/wp-content/blogs.dir/33/files/2014/12/management_plan.pdf

(Continues below)

ADDENDUM 2

3. Carpet Tile Brand Requirements

Subsection 5.11 of the IFB is amended as follows – amendments in blue:

5.11 Product Identification and Submittal

Subsection 14.3 details the documentation required for the Bidder’s proposed carpet tile product.

Mannington Commercial Product or a Comparable Non-Mannington Product:

Carpet tile shall be a Mannington Commercial product, such as Moso or Precision, that meets all applicable requirements of Subsection 5.0 Carpet Tile Product Requirements, or a comparable non-Mannington product that meets all applicable requirements of

Subsection 5.0 and is qualified in advance by the State in accordance with this subsection.

A Bidder proposing a comparable non-Mannington product shall submit a request, and such request shall be received by the State, for the State to qualify the product by the deadline specified in the revised Procurement Timeline under “Bidder Request for

Qualification of Comparable Product.” The qualification request shall be submitted to the

State to demonstrate that the proposed product meets all applicable requirements by submitting the following items:

Product samples

A preliminary version of Carpet Tile Product Form (Attachment 3), titled “Request for

Product Qualification”

Requests for product qualification shall be delivered and received by the deadline specified in the revised Procurement Timeline to the following address via hand delivery or certified mail.

235 S. Beretania Street, Suite 1000

Honolulu, Hawaii 96813

Attn: Patrick Lam

ADDENDUM 2

The samples and preliminary Carpet Tile Product Form (Attachment 3) shall be suƯicient to allow the State to evaluate whether the proposed product meets the applicable requirements of this Subsection. Samples submitted for qualification do not replace the samples required following award for final color and pattern selection discussed below.

Only items submitted for qualification purposes are to be physically delivered. All formal bid submissions must be transmitted only through HIePRO, in strict accordance with

Subsection 12.1 Electronic Submission.

The State shall review the request for product qualification and notify Bidders of its determination by the date specified in the revised Procurement Timeline under “State

Response to Qualify Comparable Products.” A comparable product shall not be eligible for use under the Contract unless it has been qualified in writing by the State through this process. The State’s qualification of a product as comparable does not relieve the Bidder of the responsibility to submit all required bid documentation or the Contractor of the responsibility to provide a product that complies with this IFB.

The State’s qualification determination shall be communicated to all Bidders through an addendum to this IFB. Only a product that meets all applicable requirements of Subsection

5.0 and has been qualified by the State, when qualification is required, may be furnished under the Contract.

Color Selection and Other Detail:

The Bidder is not required to identify a final carpet tile color with its Bid. Following award, the State shall select the carpet tile color and pattern from the proposed manufacturer’s product line, subject to availability and compliance with the requirements of this

Subsection 5.0.

The Contractor shall provide samples of the proposed carpet tile product and available colors and patterns for the State’s review and selection following award.

ADDENDUM 2

The State’s selection of color or pattern shall not result in an additional charge to the State, provided the selected color or pattern is within the manufacturer’s standard commercial product line proposed by the Contractor.

No substitution of the manufacturer or product identified in the Bid shall be permitted without the prior written approval of the State. Any approved substitute shall meet or exceed all applicable requirements of this Subsection 5.0 and shall be provided at no additional cost to the State.

4. Procurement Timeline and Bid Submission Due Date

Subsection 3.0 Procurement Timeline is amended as follows – amendments in blue:

3.0 Procurement Timeline

Milestone Date Public Notice October 1, 2026

Site Visit October 15, 2026 Vendor Questions Due October 20, 2026 at 2:00 P.M.

Bidder Request for Qualification of Comparable Product

(hand delivery or certified mail)

October 30, 2026 at 4:30 P.M.

State Response to Qualify Comparable Products

November 5, 2026

Bid Submission Deadline November 16, 2026 at 2:00 P.M.

November 2, 2026 at 2:00 P.M.

All times specified herein are based on Hawaiʻi Standard Time (HST).

Late bids shall be rejected and shall not be considered for award.

The dates above are subject to change by the State through an amendment to this IFB. In the event of conflicting dates within this solicitation, the dates established in HIePRO, including dates established by HIePRO amendments, shall control.

5. Anticipated Project Timeline

Subsection 18.0 Anticipated Project Timeline is amended as follows – amendments in blue:

ADDENDUM 2

18.0 Anticipated Project Timeline

The anticipated sequence of Work is as follows:

Milestone Anticipated Week Of

Responsibility

PHASE 1 – 12TH FLOOR

Project KickoƯ and Planning December 14, December 4, State / Carpet Tile Contractor

Demolition and Removal of Existing Furniture – 12th Floor

December 21, December 14, State's Existing Furniture Contractor

Begin Existing Carpet Removal and Carpet Tile Installation – 12th Floor

December 28, December 21, Carpet Tile Contractor

Complete Carpet Tile Installation and Punchlist Resolution – 12th Floor

January 4, 2027 – January 12, 2027

(completion date) December 28, 2026 – January 6, 2027 (completion date)

Carpet Tile Contractor

Furniture Installation – 12th Floor January 19, 2027 January 11, 2027

(January 18, 2027, is a holiday

– no work to be performed)

State's Existing Furniture Contractor

PHASE 2 – 13TH FLOOR

Demolition and Removal of Existing

Furniture – 13th Floor February 8, 2027 February 1, 2027

State's Existing Furniture Contractor

Begin Existing Carpet Removal and Carpet Tile Installation – 13th Floor

February 16, 2027

(February 15,

– no work to be

Carpet Tile Contractor

February 8, 2027 Complete Carpet Tile Installation and Punchlist Resolution – 13th Floor February 22 – March 2, 2027

(March 2, 2027 is completion date)

February 16-23, (February 15,

– no work to be

(February 23, 2027, is completion date)

Carpet Tile Contractor

Furniture Installation – 13th Floor March 8, 2027 February 25, 2027

State's Existing Furniture Contractor

The timeline establishes the anticipated sequence of Work and the coordination requirements among the State, Contractor, and State's furniture contractor.

The Contractor shall coordinate its Work and schedule with the State and the State's furniture contractor.

The State may modify scheduled dates when necessary to accommodate furniture installation, building operations, or other project requirements.

Any revised schedule issued by the State shall, to the extent reasonably practicable, preserve the Work duration allocated to the applicable phase. A change in scheduled dates shall not, by itself, reduce the Contractor's allotted Work duration for that phase.

Failure to meet an applicable required completion date, as established by the Contract, NTP, or properly authorized revised schedule, may subject the Contractor to liquidated damages as provided in the Contract.

ADDENDUM 2

Liquidated damages shall not be assessed for a delay resulting solely from a State-directed schedule change where the Contractor timely performs the applicable Work within the revised schedule and the Contractor is not otherwise responsible for the delay.