Addendum 2~21.pdf

PDF 723 KB Posted

Attached to
EWEB RFP 25-151-G Switchgear
Solicitation number
S-P00140-00014569
Issued by
Lane County, Oregon

About this file

This document is Addendum #2 for an Invitation to Bid (ITB # 25-151-G) issued by the Eugene Water & Electric Board (EWEB) for Metal Clad Switchgear at Jessen and Willow Creek Substations. The Request for Proposal (RFP) seeks two lineups of indoor switchgear to be installed in existing CMU block control houses at two different locations. The bid closing date is September 24, 2025, at 2:00 PM, and the addendum addresses multiple vendor questions regarding site requirements, access, crane services, and installation specifications. EWEB will handle power cable connections and equipment installation, with the key requirement that switchgear shipping sections must fit through 9'-4" x 9'-4" roll-up doors.

The addendum clarifies that no field services are required for this project, and EWEB is seeking identical electrical designs for both substation locations. Two approved crane contractors were identified: Oldham Crane Services and Ness Campbell Crane Services. Exhibit #1 provides a floor plan for the Jessen Substation control building, while Exhibit #2 shows the protection and control single-line drawing. Bidders must acknowledge receipt of this addendum by signing and returning a copy or circling the addendum number on the bid form, indicating this is a material change to the original bid documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rev 4-21-20

August 25, 2025

ADDENDUM # 2

Metal Clad Switchgear for Jessen and Willow Creek Substations

ITB # 25-151-G

This addendum modifies the bidding document(s) for work only to the extent indicated herein. All other areas not specifically mentioned or affected by this addendum shall remain in full force. This addendum shall be added as a part of the original bidding document and shall become part of the work required.

QUESTION & ANSWER

1. Please confirm if the RFP is for 2 lineups of indoor switchgear going into an existing enclosure.

Response: Yes, this RFP is for two (2) lineups of indoor switchgear going into two (2) different CMU block control houses which are existing structures. The lineups will be installed at different locations as noted in the Legal Advertisement.

2. Is EWEB able to provide a list of bidders who intent to bid for this RFP?

Response: We are provided a list of bidders from OregonBuys who have registered to be notified when we have bids with the same NIGP codes that the bidders are interested in, but the list does not indicate actual intention to bid.

3. What are the physical site requirements/description for both Jessen and Willow Creek substations to determine an accurate equipment lift plan ?

Response: Both Jessen and Willow Creek are electric substations that have CMU block constructed control houses. The access for each set of switchgear into the control house will be via a roll up door with a 9’-4” x 9’-4” opening (approximate). This contract does not include any field services (including offloading or field assembly) so EWEB will handle this work as long as the switchgear shipping section can fit through the roll up door.

4. Can you provide a list of approved crane contractors that are approved by EWEB currently?

Response: Oldham Crane Services and Ness Campbell Crane Services

5. Is Contractor to do any cabling? EWEB specifically states the power transformer is not in scope but there is a detailed description of the connections.

Response: EWEB will be responsible for bringing power cables to the switchgear and making connections.

6. Do we need to include a quote for field services?

Rev 4-21-20

Response: No field services are required for this RFP. The specification has provision for including field services and a Field Engineer but we are not using those provisions for this RFP. Again, this contract does not include any field services (including offloading or field assembly) so EWEB will handle this work as long as the switchgear shipping section can fit through the roll up door.

7. The enclosure does not appear to be defined- there is no specification regarding the building or site plan to provide guidance as to foundation, dimensions, environmental, building codes.

Response: The enclosure will be a block building to house the switchgear and EWEB-owned control panels. Exhibit #1 is provided and shows a building floor plan for Jessen Substation with the planned layout.

8. There are lots of control and protection drawings included in the bid documents but where are the electrical single line drawings? Are we supposed to assume that Jessen and Willow Creek are identical?

Response: Exhibit #2 has been added which shows the protection and control single line drawing for Jessen Substation. EWEB is looking for two identical designs and the electrical requirements of the switchgear are identical for both stations.

CLOSING DATE AND TIME: SEPTEMBER 24, 2025; 2:00 PM

Remains unchanged.

This addendum constitutes a MATERIAL CHANGE to the bid. ITS RECEIPT BY THE BIDDER IS TO BE ACKNOWLEDGED BY A SIGNATURE AND RETURNING A COPY OF THE ADDENDUM WITH ITS RESPONSE OR

BY CIRCLING THE ADDENDUM NUMBER IN THE APPROPRIATE AREA ON THE BID FORM.

Addendum prepared by:

Sandra Hahn, Purchasing Contact

The undersigned hereby acknowledges receipt of this Addendum and agrees to be bound by the conditions therein.

Company Name: ________________________________

Signature: ______________________________________

Date __________________________

End of Addendum

FUNC BY CHK APP

DES

DWN

EWEB WORK ORDER NO.

DATE:

REV DATE DWN CHK APP

DWG NO:

REV

5/ 1/

:3

PM

KE

LL

Y

RO

PE

R

STD

STANDARDS CHECK

PROJECT SHEET NO:

SCALE:

REVISION DESCRIPTION

LINE IS 2 INCHES

AT FULL SIZE

(IF NOT 2" - SCALE ACCORDINGLY)

REV NO.

C

2302090

1/4" = 1'-0"

05/2025

D-39954-A2

MARCUM

ROPER

ARCHITECTURAL

JESSEN SUBSTATION

CONTROL BUILDING

FLOOR PLAN

EXHIBIT #1

FUNC BY CHK APP

DES

DWN

EWEB WORK ORDER NO.

DATE:

REV DATE DWN CHK APP

DWG NO:

REV

8/

/2

3:

P

M P

H

IL

IP

P

ET

ER

SO

N STD

STANDARDS CHECKEWEB

PROJECT SHEET NO:

SCALE:

REVISION DESCRIPTION

LINE IS 2 INCHES

AT FULL SIZE

(IF NOT 2" - SCALE ACCORDINGLY)

REV NO.

E

2302090

NONE

02/2025

D-39955-1B

EDENS

CHANDIWALLA

ELECTRIC SYSTEMS

JESSEN SUBSTATION

METER AND RELAY

ONE LINE DIAGRAM

EXHIBIT #2

Exhibit 2 - Jessen Single Line.pdf
Sheets and Views
39955-1B-39955-1B

File details come from the government source that posted it. Updated .