Addendum 2_Sullivan Circle Drainage_upd.pdf
PDF 338 KB Posted
- Attached to
- Sullivan Circle Drainage Improvements
- Solicitation number
- PE-66983-NONST-2026-000000008
- Issued by
- Pickens County, Georgia
About this file
This is Addendum No. 2 to the bid documents for the Sullivan Circle Drainage Project issued by the Town of Pine Mountain, Georgia, dated October 21, 2025, for Engineer's Project No. P22-121. The addendum modifies the original September 2025 bid documents and addresses clarifications regarding project scope, including drainage infrastructure installation, utility coordination, and site restoration. The project requires the installation of reinforced concrete pipe (RCP) storm lines in 15-inch, 18-inch, and 24-inch diameters totaling 410 linear feet, six drop inlets with pedestal tops, two flared end sections, and one headwall. Additional work includes clearing and grubbing, asphalt and concrete replacement, grading, erosion control, permanent grassing, and coordination of power pole relocation. The bid submission deadline is October 28, 2025, at 10:30 AM, with a questions deadline of October 21, 2025, at 10:30 AM. The contract term is 150 consecutive calendar days from the Notice to Proceed. Twenty-two contractors are listed as plan holders, including firms such as Barksdale Contracting & Supply, Crawford Grading & Pipeline, Inc., Cleary Construction, and Mid-South Builders, Inc.
The revised bid form specifies unit price items with estimated quantities, including flowable fill reduced from 50 cubic yards to 5 cubic yards and separate line items for standard and decorative concrete driveway replacement. Bid pricing shall be presented in both words and figures, with amounts written in words taking precedence in case of discrepancy. Bidders must acknowledge receipt of the addendum on Bid Form 00300-5 and are required to submit a bid security equal to five percent of the total bid amount. The bid is valid for 60 calendar days following the submission deadline. Utility conflicts discovered during construction will be addressed on a case-by-case basis, and power pole relocation will be positioned approximately 15 feet south within the permanent slope and maintenance easement. Road crossing replacement must be asphalt only and cannot be substituted with concrete or black concrete.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1_Sullivan Circle Drainage.pdf | ||
| SEC00030_Advertisement.pdf | ||
| Addendum 3_Sullivan Circle Drainage_upd.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pine Mountain Sullivan Circle Drainage Project ADDENDUM NO. TWO (2) P22-121 | Addendum No. 2 dated 10/21/2025 Page 1
ADDENDUM NO. TWO (2)
Date: October 21, 2025 Engineer’s Project No. P22-121
PROJECT: Sullivan Circle Drainage Project
Client: Town of Pine Mountain
This Addendum forms a part of the Contract Documents and Construction Drawings and modifies the original Bid Documents for the above referenced project. Total pages of this addendum is 7 pages.
The following items shall take precedence over the specifications for the above named project and shall become a part of the contract documents.
The following changes are to be incorporated into the solicitation documents dated September 2025.
All those receiving this addendum should modify their documents to show the below described changes or clarifications.
Questions:
Q1. If I have not aliens working for me, do I need to submit section 00491?
A1. Mark as does not apply.
Q2. Where does the power pole get relocated?
A2. The pole shall be located approximately 15’ to the south within the permanent slope/maintenance easement.
Q3. The detail on the last page for a pedestal top, are all six drop inlets to have the pedestal tops?
A3. Yes.
Q4. My calculations show that I only need 3.5 cubic yards of flowable fill. That will cover the 12” x 45’ and the 15” x 45’ CMP pipes. On the bid price sheet it has us bidding 50 cy.
A4. See revised Bid Form attached.
Q5. The existing water main appears to conflict with the proposed storm line. What is the plan to mitigate the water and sewer laterals if they are in conflict?
A5. Any utility conflicts found in the field will be addressed on a case-by-case basis.
Q6. If rerouting existing water main is required, would this scope of work require a state issued utility contractor’s license?
A6. See answer to Q5.
Q7. Can the cost to replace the decorative concrete be its own line item separate of the standard concrete due to the difference in cost?
A7. See revised Bid Form attached.
Q8. Can the road crossing be replaced with concrete and/or black concrete in lieu of asphalt?
A8. No.
Q9. Is there a reason the FES could not be shifted or an additional stick of pipe laid to avoid the relocation of the power pole?
A9. No, the suggestion has been reviewed and determined that it is not feasible.
Attachments
• Plan Holders List (1 Page)
• Bid Form Revised (5 Pages)
PLEASE NOTE: Contractors should acknowledge receipt of this addendum on Bid Form 00300-5.
END OF ADDENDUM NO. TWO (2)
G:\DOCUMENT\22\P22-121 PINE MOUNTAIN GEN SERVICES\SULLIVAN CIRCLE DRAINAGE\BID PHASE\Plan Holder List.doc
PLAN HOLDER LIST
Town of Pine Mountain Sullivan Circle Drainage Project
PPI Project No. P22-121
BID DATE: 10/28/2025 @ 10:30 AM
PRE-BID CONFERENCE: N/A
Questions Deadline: 10/21/2025 @ 10:30 AM to 861np@ppi.us
CONTRACTORS
Barksdale Contracting & Supply Ryan Durden ryan@barksdalecontracting.com
QX Ground Duane Quick qxgound@outlook.com
Crawford Grading & Pipeline, Inc.
Madison Moore admin@crawfordgrading.com
Cleary Construction John Connelly estimating@clearyconst.com
Mid-South Builders, Inc.
Ben Weaver ben@mid-southbuildersinc.com
Bash Contracting, LLC Scott Hapner sdhapner@gmail.com
Conner Grading Brooke Wenzel brooke@connergrading.com
Helix Grading and Utility, LLC Tina Chastain office@helixllc.us
Blount Construction Company Aaron Tamba Aaron.tamba@blountconstruction.com
Coggins Construction Company Jackson Reddick jackson@cogginsconstruction.com
FS Scarbrough, LLC Ajanee Logan alogan@fsscarbrough.com
RLC Farms, LLC Kyrsteyn Boyt Rlcfarms1062@gmail.com
Matthew Development Matt Arp matt@mdccivil.com
Cline Service Corp Ray Cline Clineserv@aol.com
Piedmont Paving, Inc.
Scott Marchman scott@piedmontpaving.com
McLeRoy, Inc.
Eric McLeRoy eric@mcleroyinc.com
RM Concrete Specialist Carolina Angel cangel@rmconcretespecialist.com
3B Services LLC Logan Baggett lbaggett@3bservices.net
4H Clearing and Grading Casey Hall Casey@4h-services.com
Elite Southern Services Hayden Bishop elitesouthernservicesllc@gmail.com
McCoy Grading, Inc.
Craig Sinclair csinclair@mccoygrading.com mailto:861np@ppi.us mailto:ryan@barksdalecontracting.com mailto:qxgound@outlook.com mailto:admin@crawfordgrading.com mailto:estimating@clearyconst.com mailto:ben@mid-southbuildersinc.com mailto:sdhapner@gmail.com mailto:brooke@connergrading.com mailto:office@helixllc.us mailto:Aaron.tamba@blountconstruction.com mailto:jackson@cogginsconstruction.com mailto:alogan@fsscarbrough.com mailto:Rlcfarms1062@gmail.com mailto:matt@mdccivil.com mailto:Clineserv@aol.com mailto:scott@piedmontpaving.com mailto:eric@mcleroyinc.com mailto:cangel@rmconcretespecialist.com mailto:lbaggett@3bservices.net mailto:Casey@4h-services.com mailto:elitesouthernservicesllc@gmail.com mailto:csinclair@mccoygrading.com
P22-121 | 09-2025 | Addendum No. 2 (Bid Form) 00300-1
BID FORM
Sullivan Circle Drainage Project For the Town of Pine Mountain, Georgia
THIS BID IS SUBMITTED TO:
Town of Pine Mountain 250 McDougald Avenue P. O. Box 8 Pine Mountain, Georgia 31822
(706) 633-2213 (Hereinafter called "Owner")
THIS BID IS SUBMITTED BY:
(Name) (Address)
(Telephone) (Hereinafter called "Bidder")
BIDDER, in compliance with the Advertisement for Bids for the construction of this project, having examined the Drawings and Specifications with related documents and the site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed project, including the availability of materials and labor, hereby proposes to furnish all labor, materials and supplies, and to construct the project in accordance with the CONTRACT DOCUMENTS, within the time set forth therein, and at the price(s) stated below. This price(s) is to cover all expenses including overhead and profit incurred in performing the Work required under the CONTRACT DOCUMENTS, of which this proposal is a part.
P22-121 | 09-2025 | Addendum No. 2 (Bid Form) 00300-2
The Contractor is directed to Section 01025 "Measurement and Payment" for the methods and limits for payments to the Contractor for the pay items listed below.
Item No. Description Unit Est. No.
of Units
Unit Price Bid Total for Item
Clearing and Grubbing LS 1 Dollars and Cents
Unit Price in Words)
2 Sawcut, Remove and Replace Asphalt
SY 45
Unit Price in Words)
3 Remove Existing Storm Pipes LF 87 Dollars and Cents
Unit Price in Words)
4 Sawcut (or Remove to a Joint), Remove and Replace Concrete Driveway
SY 30
Dollars and Cents
Unit Price in Words)
4a. Sawcut (or Remove to a Joint), Remove and Replace Decorative Concrete Driveway
SY 55
Dollars and Cents
5 Grading Complete LS
6 15” RCP Storm Pipe
LF
7 18” RCP Storm Pipe LF 65 Dollars and Cents
8 24” RCP Storm Pipe LF 63
P22-121 | 09-2025 | Addendum No. 2 (Bid Form) 00300-3
Item No. Description Unit Est. No.
of Units
Unit Price Bid Total for Item
9 Drop Inlet EA 6 Dollars and Cents
Unit Price in Words)
10 Flowable Fill CY 5 Dollars and Cents
Unit Price in Words)
11 Flared End Section EA 2 Dollars and Cents
Unit Price in Words)
12 Headwall EA 1 Dollars and Cents
Unit Price in Words)
13 Temporary Erosion and Sediment Control
LS 1
Dollars and Cents
Unit Price in Words)
14 Permanent Grassing (incl Sod where required) and Clean Up
LS 1
Dollars and Cents
Unit Price in Words)
15 Coordinate the Removal and Relocation of the Power Pole with the Utility
LS 1
Total Amount Bid (Items 1-15):
(Dollars and Cents)
(Price in Words)
NOTE: Amounts shall be shown in words and figures; the amount written in words shall take precedence.
P22-121 | 09-2025 | Addendum No. 2 (Bid Form) 00300-4
BIDDER acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities provided, determined as provided in the Contract Documents.
BIDDER hereby agrees to commence work under this contract on or before a date to be specified in a written "Notice to Proceed" from the OWNER and to fully complete WORK within a total construction time of ONE HUNDRED FIFTY (150) consecutive calendar days of the date specified in this "Notice to Proceed".
BIDDER acknowledges receipt of the following addenda:
Addendum No.
Date Received
BIDDER agrees to perform all of the construction of the project complete with appurtenances and accessory work described in the Specifications and shown on the Drawings for the above scheduled price(s).
The above scheduled price(s) shall include all labor, materials, bailing, shoring, removal, overhead, profit, insurance, etc., to cover the finished work of the several kinds called for.
BIDDER understands that OWNER reserves the right to reject any or all bids and to waive any informalities in the bidding.
BIDDER agrees that his bid shall be good and may not be withdrawn for a period of SIXTY (60) calendar days after the scheduled closing time for receiving bids.
P22-121 | 09-2025 | Addendum No. 2 (Bid Form) 00300-5
Upon receipt of the written notice of the acceptance of this bid, BIDDER will execute the formal Contract attached within ten (10) days and deliver a surety bond or bonds, as required by the General Conditions. The bid security attached in the sum of five (5%) percent of the total bid is to become the property of the OWNER in the event the Contract and bond are not executed within the time set forth, as liquidated damages for the delay and additional expense to the OWNER caused thereby.
Respectfully Submitted: Name:
Address:
Phone No.:
FEDERAL TAX NO. OR
SOCIAL SECURITY NO.:
Signature of Principal:
Title:
Date:
Telephone:
ATTEST:
Signature:
Corporate Secretary/Partner/Notary (SEAL)
Name:
(Please type)
NOTE: Attest for a corporation must be by the corporate secretary; for a partnership by another partner;
for an individual by a Notary.
END OF SECTION 00300
| Plan Holder List.pdf |
| PLAN HOLDER LIST |
| Town of Pine Mountain Sullivan Circle Drainage Project |
| PRE-BID CONFERENCE: N/A |