This Addendum 1 to RFP #26-173-Q modifies the bidding documents for the Eugene Water & Electric Board's (EWEB) Leaburg-Walterville 6th Comprehensive Safety Inspection Report (Part 12D) project. The addendum clarifies the scope of work to include evaluation of project safety and integrity encompassing structural stability and mechanical and electrical systems as applicable to the hydroelectric facilities. The closing date and time for proposal submission remains November 10, 2026, at 2:00 PM. Bidders must acknowledge receipt of this addendum by signature and return a copy with their response or by circling the addendum number on the bid form, as this constitutes a material change to the bid.

The addendum addresses two critical questions from potential proposers regarding technical documentation. The 2026 Supporting Technical Information Document (STID) referenced in the RFP is currently under development and unavailable; however, proposers may request the 2024 STID upon execution of a Critical Energy Infrastructure Information General Non-Disclosure Agreement by emailing Sandra Hahn at sandra.hahn@eweb.org. The scope of a Part 12D inspection includes comprehensive evaluation of structural stability, mechanical systems, and electrical systems as applicable to the Leaburg Development and Walterville Development projects on the McKenzie River, with proposers directed to review the RFP for complete scope details and minimum qualification requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rev 4-21-20

November 4, 2026

ADDENDUM # 1

Leaburg-Walterville 6th CSIR Part 12D Report

RFP # 26-173-Q

This addendum modifies the bidding document(s) for work only to the extent indicated herein. All other areas not specifically mentioned or affected by this addendum shall remain in full force. This addendum shall be added as a part of the original bidding document and shall become part of the work required.

QUESTION & ANSWER

Question 1 - For this project, are you looking at electrical and mechanical? Are you looking at inspections for structural integrity of the actual dam structure itself and the penstock and such?

Response - The scope of a Part 12D inspection includes the evaluation of project safety and integrity, including structural stability and integrity, as well as mechanical and electrical systems, as applicable to the project and the requirements outlined in the RFP. Please refer to the RFP for the full scope of work and minimum qualification requirements to ensure your team’s experience and proposed approach align with the requirements.

Question 2 – We are hoping that you can provide us with the technical information referenced in the RFP: “More detailed project information is found in the 2026 Supporting Technical Information Document (STID) that can be provided upon request and execution of a Critical Energy Infrastructure Information General Non-Disclosure Agreement.” Please let us know what we must do to obtain and sign the NDA, and gain this information.

Response - The 2026 STID referenced in the RFP is currently in development and is not yet available for distribution after all. Proposers may request access to the 2024 STID, which will be provided upon receipt of a fully executed NDA. Please email your request to Sandra Hahn at sandra.hahn@eweb.org.

CLOSING DATE AND TIME: November 10, 2026, 2:00 PM. Remains unchanged.

This addendum constitutes a MATERIAL CHANGE to the bid. ITS RECEIPT BY THE BIDDER IS TO BE ACKNOWLEDGED BY A SIGNATURE AND RETURNING A COPY OF THE ADDENDUM WITH ITS RESPONSE OR BY

CIRCLING THE ADDENDUM NUMBER IN THE APPROPRIATE AREA ON THE BID FORM.

Addendum prepared by:

Sandra Hahn, Purchasing Contact

The undersigned hereby acknowledges receipt of this Addendum and agrees to be bound by the conditions therein.

Company Name: ________________________________

Signature: ______________________________________

Date __________________________

End of Addendum

File details come from the government source that posted it. Updated .