This is an Addendum 1 document issued by the New Hampshire Department of Natural and Cultural Resources (DNCR) Capital Projects & Maintenance Bureau on July 1, 2026, addressing bidder questions and responses for the CAP2609 Mt. Washington Tank Inspection project. The project involves comprehensive interior inspection, cleaning, and sludge disposal services for five fuel storage tanks at the Mt. Washington facility, with work anticipated during the 2026 summer operating season. Tank specifications include Tank 1 (97" depth, approximately 15,285 gallons), Tank 2 (12" depth, approximately 1,200 gallons), Tank 3 (out of service), Tank 4 (67" depth, approximately 9,592 gallons), and Tank 5 (empty). All tanks remain in scope despite their varying operational status. The addendum clarifies that bids may be submitted electronically, a certified tank inspector is acceptable in lieu of a New Hampshire Professional Engineer, and manhole access dimensions are 19.5 inches ID.

Critical operational clarifications provided in the addendum address site logistics and contractor responsibilities. Contractors must provide their own pumping equipment as no internal transfer capability exists between tanks; however, usable fuel may be stored in the empty Tank 5 during cleaning operations. The surrounding parking lot area near the tanks can be exclusively blocked off except for essential park staff access. Contractors are responsible for weather-related delays and time loss, though the Sherman Adams building is available for shelter. Access to the Mt. Washington Auto Road operates from 9:00 a.m. to 6:00 p.m. with off-hours coordination available, and no per-person fees apply, though oversized-vehicle fees and toll charges are applicable. Frac tanks may be stored on-site with prior arrangement, and the project is not subject to prevailing wage requirements. Previous API inspections were performed by Interspec LLC, though no preferred vendor is specified for the current project.

View the file

Other files

File Type Posted
rfb-dncr-2027-01.pdf PDF
rfb-dncr-2027-01-rev1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum 1 – Questions & Responses Project: CAP2609 – Mt. Washington Tank Inspection

Date: 7/1/2026

To: All Interested Bidders

From: DNCR-Capital Projects & Maintenance Bureau

Subject: Addendum 1 – Bidder Questions and Responses

This Addendum forms part of the Request for Proposals (RFP) documents for the CAP2609 Mt.

Washington Tank Inspection Project. The following questions were submitted by prospective bidders. The official responses below are to be incorporated into the final contract documents.

Can bids be emailed?

Yes. Bids may be submitted electronically and should be sent directly to the project contact prior to the bid closing date.

What is the expected period of performance for the inspections?

Work is anticipated to occur during the 2026 summer operating season.

Is a NH Professional Engineer required, or is a certified tank inspector acceptable?

A certified tank inspector is acceptable. A P.E. is not specifically required.

What are the current fuel levels and tank statuses?

Tank 1: 97” depth – approx. 15,285 gal. Tank 2: 12” – approx. 1,200 gal. Tank 3: Out of service.

Tank 4: 67” – approx. 9,592 gal. Tank 5: Empty. All remain in scope.

Will all fuel need to be disposed of?

Disposal is not required; reusable product will be retained.

Can fuel be transferred between tanks?

No internal transfer capability exists; contractors must bring pumps.

Can usable product be stored in another tank during cleaning?

Yes. Tank #5 is empty and available for storage.

What portion of the surrounding parking lot can be blocked off?

The area near the tanks can be made exclusively available except for essential park staff.

How is fuel delivered to the site?

By tanker truck.

What are the manhole access dimensions?

Manholes are 19.5 inches ID.

Is daily check-in required?

Contractors should coordinate with MWSP staff and monitor weather.

If called off due to weather, is the contractor responsible for time loss?

Yes. Plan for weather-related delays.

Is there shelter available?

Yes. The Sherman Adams building is available.

What are the mountain access hours?

Auto Road hours are 9am–6pm. Off-hours possible with coordination.

Will contractors be charged for road use?

No per-person fees. Only oversized-vehicle fees apply.

Will vehicles be weighed or charged?

No per-person fees. Oversized-vehicle rules apply.

Who performed past API inspections?

Interspec LLC.

Is there a preferred vendor?

No.

Can frac tanks be stored on site?

Yes, with prior arrangement with MWSP staff.

Is this a prevailing wage project?

No.

Is there an expected start/completion date?

As advertised in the RFP.

Extension request for July 3rd?

No.

Can bids be emailed?
What is the expected period of performance for the inspections?
Is a NH Professional Engineer required, or is a certified tank inspector acceptable?
What are the current fuel levels and tank statuses?
Will all fuel need to be disposed of?
Can fuel be transferred between tanks?
Can usable product be stored in another tank during cleaning?
What portion of the surrounding parking lot can be blocked off?
How is fuel delivered to the site?
What are the manhole access dimensions?
Is daily check-in required?
If called off due to weather, is the contractor responsible for time loss?
Is there shelter available?
What are the mountain access hours?
Will contractors be charged for road use?
Will vehicles be weighed or charged?
Who performed past API inspections?
Is there a preferred vendor?
Can frac tanks be stored on site?
Is this a prevailing wage project?
Is there an expected start/completion date?
Extension request for July 3rd?