Addendum 1_MDOT 591-25416_Superior Region Office HVAC.pdf

PDF 4 MB Posted

Attached to
591/25416. AGY; Superior Region HVAC
Solicitation number
RFQ 171 260000000385 2
Issued by
Delta County, Edmore Village, Michigan

About this file

This Construction Bid Addendum No. 01 is issued by the Michigan Department of Technology, Management and Budget, State Facilities Administration Design & Construction Division for the Superior Region Office HVAC Replacement project (File Number 591/25416). The project involves replacing HVAC systems at the Superior Region Office, with a prebid meeting held on July 21, 2026, and a bid opening scheduled for August 5, 2026. The work includes boiler replacement with a corrected specification for a Weil McLain LGB-4 unit, condensing unit replacement with an approved Trane IntelliCore Air-Cooled 30-ton model, main pumps, valves, expansion tank installation, exhaust system upgrades to code compliance, and inspection of remaining systems. The project completion date is May 31, 2027. Matthew Lusby, MDOT Project Director, issued this addendum on July 23, 2026, which incorporates clarifications from the prebid meeting and must be acknowledged by all bidders in their bid submissions.

The addendum specifies a cash allowance of $10,000 already included in the bid schedule with no contingency allowance. Work scope includes replacing all lines, valves, and components required for the new R454B refrigerant system, upgrading exhaust systems with 10-inch connected exhaust using a Y manifold to the existing 14-inch exhaust stack, and inspecting remaining system components for replacement or code compliance needs. Bidders proposing alternative condensing unit models must submit specification sheets prior to the bid deadline. Bidders must acknowledge receipt of this addendum to avoid bid rejection, as the addendum becomes part of the contract documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 6/25)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND

BUDGET

State Facilities Administration Design & Construction Division

CONSTRUCTION BID ADDENDUM NO. 01

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

7/23/2026

PROJECT NAME

Superior Region Office – HVAC Replacement

FILE NUMBER

591/25416

PROFESSIONAL

PSC Name

PROJECT DIRECTOR BID OPENING DATE:

Matthew Lusby - MDOT 8/5/2026

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

This Addendum is to post the prebid sign in sheet and response to some questions/discussion from the prebid

1. Prebid Sign in sheet

2. Clarification/Questions from Prebid on 7/21

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL:

DATE: Click to enter date

APPROVED BY:

PROJECT DIRECTOR: Matthew Lusby DATE: 7/23/2026 http://www.michigan.gov/SIGMAVSS

Superior Region Office HVAC Replacement

Clarification/Questions from Prebid

7/21/26

Allowances

Cash allowance - $10,000 already on bid schedule

Contingency allowance – none

Boilers and what’s included

Incorrect boiler/size on the sheet – Weil Mclain LGB-4 is a better match to the existing than what was in the specs originally o Upgrading exhaust as required by code and manufacture. Each boiler to have

10” connected exhaust using a y manifold to the 14” exhaust stack

Main pumps

Valves

Expansion tank

Inspecting the rest of the system and letting project manager know if something is needing replaced or out of code

Condensing unit

Replaces all lines, valves and other components required for the new R454B

Model in the specs was incorrect, one approved unit shown below, please send me the spec sheet of any other you would like to bid for before bids are due

Trane IntelliCore™ Air-Cooled Condensing Units 30 ton

Completion Date

– 5/31/27