Addendum _1 IFB _495_26.pdf
PDF 870 KB Posted
- Solicitation number
- PE-64200-NONST-2026-000000073
- Issued by
- Douglas County, Georgia
About this file
This is Addendum #1 to Invitation for Bid (IFB) #495-26 issued by Dawson County for Roadway Rehabilitation and Culvert Replacements. The project encompasses four tasks: Task 1 involves rehabilitation of Afton Road including deep patching, recycled asphalt concrete placement, mill butt joints, traffic striping, and rumble strips; Task 2 covers mill and overlay work on Emma Terrace from State Route 183 to State Route 136 (approximately 0.28 miles) with recycled asphalt concrete and traffic striping; Task 3A addresses comprehensive rehabilitation of Cowart Road including cement reclaimed base, Portland cement, asphalt binder, asphalt topping, rumble strips, and traffic striping with permanent grassing on shoulders; and Task 3B involves culvert replacements on Cowart Road with storm drain pipes in three sizes (18", 24", and 30") and concrete headwalls. The estimated quantities include 6,000 tons of recycled asphalt concrete for Afton Road, 900 tons for Emma Terrace, 4,000 tons of B-MOD asphalt binder for Cowart Road, and 160 linear feet of 30-inch storm drain pipe. The IFB was originally issued March 17, 2026, with this addendum issued April 10, 2026, and the closing date is April 16, 2026, at 10:30 a.m. All work must be completed during daylight hours Monday through Friday, and contractors are required to submit a revised Price Proposal Form included in the addendum.
The addendum addresses clarifications regarding milling operations, payment structures, mailbox conflicts, asphalt application timelines, and material disposal. Milling costs are included in tonnage pricing rather than as separate line items. The County will remove concrete driveways on Afton Road and backfill with graded aggregate base, while millings from Afton Road and Emma Terrace may be hauled to the Georgia WMA site on Amicalola Church Road. Material Transport Vehicles must be utilized for Task 2 (Emma Terrace) and Task 3A (Cowart Road). Contractors must meet striping requirements including 10-foot lanes and 2-foot paved shoulders on Afton Road and Cowart Road, with Emma Terrace requiring only 10-foot lanes with no shoulder work. Warranty requirements include a 2-year warranty for all asphalt work, a 3-year warranty for Full Depth Reclamation, and a 1-year warranty for Task 3B culvert work. The addendum specifies that no permanent mailboxes in conflict are to be removed and that temporary wedges must be placed in mill butt joints if paving cannot be completed within one day.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB #495-26 ROADWAY REHABILITATION AND CULVERT REPLACEMENTS
ADDENDUM #1
IFB Closing Date: April 16, 2026, at 10:30 a.m.
IFB Issue Date: March 17, 2026 IFB Addendum Issue Date: April 10, 2026 By: Hanna Milford, Purchasing Manager
The following are questions, answers, and clarifications to the IFB #495-26 Roadway Rehabilitations and Culvert Replacements:
1. QUESTION: On page 9 the description for Afton Rd and Emma Terrace calls for mill and overlay, which one would assume that the whole road would be milled. Afton Rd has a pay item for Mill Butt Joins and Emma Terrace does not have a pay item for any milling. Please clarify the milling operation on these two roads.
ANSWER: Milling included in the tonnage.
2. QUESTION: How will dirt or gravel side roads and driveways be handled in this project? Will the contractor run the spreader gate out or should we use the GDOT misc. Unpaved Spec for paving roads and driveways? Please clarify.
ANSWER: Tie in dirt/gravel driveways 20 feet minimum or all other driveways, catch with spreader gate.
3. QUESTION: On Cowart Rd there is (5) existing brick mailboxes @ 859, 1681, 1772, 2031, & 2307. Generally the brick mailboxes are moved or replaces by the homeowner not the contractor.
Please advise.
ANSWER: No permanent mailboxes in conflict and therefor no permanent mailboxes are to be removed.
4. QUESTION: How will milling of the roads be paid for in task 1 & 2? Will a pay item be added?
ANSWER: Included in the tonnage.
5. QUESTION: How will milling of the roads be paid for in task 1 & 2? Will a pay item be added?
ANSWER: Included in the tonnage.
6. QUESTION: Do mill butt joints need to be beginning and end?
ANSWER: Per contract bid quantity (4 each)
7. QUESTION: As far as putting asphalt on a mill surface – how many days for cover up?
ANSWER: No time limit on butt joints, but must put in temporary wedges if more than a day.
8. QUESTION: Cowart – across drains do we want a deeper mix?
ANSWER: No.
Clarifications
1. Millings from Afton Road and Emma Terrace can be hauled to the Georgia WMA site on Amicalola Church Road for disposal
2. County will remove concrete driveways on Afton Road and backfill to match existing with graded aggregate base
3. Work Hours: Daylight hours only Monday-Friday for all tasks
4. Striping Requirements
a. Task 1 – Afton Road: Paving and striping requirements are 10’ lanes and 2’ paved shoulders.
b. Task 3A – Cowart Road: Paving and striping requirements are 10’ lanes and 2’ paved shoulders
5. Material Transport Vehicles (MTV)
a. Task 2 – Emma Terrace: Material Transport Vehicle (MTV) shall be utilized throughout the entire project
b. Task 3A – Cowart Road: Material Transport Vehicle (MTV) shall be utilized throughout the entire project
6. Task 2 – Emma Terrace Revision
a. Mill and overlay from State Route 183 to State Route 136 approximately 0.28 miles. No widening
b. Paving and striping requirements for 10’ lanes
c. No shoulder work necessary
7. See attached amended Price Proposal Form, this must be submitted instead of the original.
IFB #495-26 Roadway Rehabilitations and Culvert Replacements 21
Vendor’s Price Proposal Form (Sheet A)
Company Name: __________________________________________________________
TASK 1- Afton Road
Line Item
Description Estimated Quantity
Unit Unit Cost Total Estimated Cost
1.1 Traffic control, shoulders, signage and mobilization 1
Lump Sum
1.2
Deep patch 3 inch and replace with recycling asphalt concrete 19mm @ 330 lbs/sy including bitum material (locations to be provided by County but includes the paved shoulder) 1,800 Tons
1.3
Recycled asphalt concrete 12.5 mm @ 165 lbs/sy including bitum material 6,000 Tons
1.4
Recycled asphalt concrete leveling, 55 lbs/sy of 9.5 mm Type 1 including bitum material 1,700 Tons
1.5 Mill butt joints (bridge) 4 Each
1.6 Traffic Stripe (thermoplastic) 1
1.7 Rumble Strips (thermoplastic) 3 Each
TOTAL BID
DAYS TO COMPLETE
IFB #495-26 Roadway Rehabilitations and Culvert Replacements 22
TASK 2 – Emma Terrace
Description Estimated Quantity
Unit Unit Cost Total Estimated Cost
2.1 Traffic control, shoulders, signage and mobilization 1
2.2
Mill 6 inch depth and replace with Recycling asphalt concrete 25 mm @440 lbs/sy including bitum material (locations to be provided by County) 900 Tons
2.3 Recycled asphalt concrete 12.5 mm @ 220 lbs/sy including bitum material 350 Tons
2.4 Traffic Stripe (thermoplastic) 1
TASK 3A – Cowart Road
Description Estimated Quantity
Unit Unit Cost Total Estimated Cost
3A.1 Traffic control, shoulders, signage and mobilization 1
3A.2 Permanent Grassing – shoulders 1 sum
3A.3
10” Cement Reclaimed Base (includes temp raised lane markers) 24 foot wide 34,000 Sq yd
3A.4 Portland Cement – 75 lb/sy 1,300 Tons
3A.5
B-MOD Asphalt Binder 2” depth, 24 foot wide including bitum material 4,000 Tons
3A.6
12.5 mm 165 lbs/sy TP 1/H Mix SP Asphalt Topping 24 foot wide including bitum material 3,000 Tons
3A.7 Rumble Strips (thermoplastic) 6 Each
3A.8 Traffic Stripe (thermoplastic) including stop bars 1
IFB #495-26 Roadway Rehabilitations and Culvert Replacements 23
TASK 3B – Cowart Road Culverts
Description Estimated Quantity
Unit Unit Cost Total Estimated Cost
3B.1 Traffic control, shoulders, signage and mobilization 1
3B.2 Storm Drain Pipe 18” reinforced concrete pipe 50 LF
3B.3 Storm Drain Pipe 24” reinforced concrete pipe 80 LF
3B.4 Storm Drain Pipe 30” reinforced concrete pipe 160 LF
3B.5
Concrete Headwall Straight Endwall with downstream storm drain outlet protection 8 Each
3B.6 Field Fence incl posts 40 LF
TOTAL ESTIMATED COSTS
FOR ALL TASKS:
START DATE:
WARRANTY:
(Circle each if compliant)
2-year warranty for all asphalt work 3-year warranty for Full Depth Reclamation 1-year warranty on Task 3B
WARRANTY IF NOT
COMPLIANT:
IFB #495-26 Roadway Rehabilitations and Culvert Replacements 24
Vendor’s Price Proposal Form (Sheet B)
Point of Contact Information:
Name:
E-Mail:
Number:
Authorized Representative Signature Date
Print Name Title
All costs for Dawson County are to be included in the line items above. Additional documents may accompany this form.