This Addendum #1 is issued by the Kansas Department of Transportation (KDOT) Bureau of Construction and Materials to prime contractor bid holders regarding the June 17, 2026 letting for project I070-031 KA 7706-01, an electric lighting system installation project at the I-70/K-177 junction in Geary County. The project requires contractors to furnish and install a complete electric lighting system including high mast light towers (100', 110', and 120' heights), light poles (40' and 55' mounting heights with LED luminaires), concrete bases, conduit systems, cable, ground rods, transformers, and associated hardware. Key quantities include 470 linear feet of boring, 88 expansion joints, multiple high mast towers, LED luminaires, conduit in various sizes and schedules, and numerous electrical components detailed in the Summary of Electric Lighting System Quantities table. Contractors must acknowledge receipt of this addendum and sign and email confirmation to Joshua Matyi at Joshua.Matyi@ks.gov. The completed unit cost spreadsheet must be submitted to the Letting Engineer no later than noon on Friday following the letting day, with the spreadsheet template available on KDOT's website.
The revised required special provision 11-15-17-R02 establishes that although the bid item is structured as a lump sum price, the contractor must provide unit costs for each individual electric lighting item. The contract price will be adjusted based on any variance between the quantities in the Summary of Quantities and actual quantities required, with the sum of unit costs multiplied by all items not exceeding the lump sum bid amount. The Secretary may reject any proposal if the contractor fails to complete the unit cost submittal before the Friday noon deadline. Furnished items must comply with either KDOT's List of Prequalified Roadway Lighting Systems and Equipment or the contract specifications as approved by the engineer. Contractors are responsible for updating their EBS files through Bid Express at http://www.bidx.com and reviewing the Bid Express "Questions and Answers" section for any additional project clarifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Notice-Lighting - I-70 I-70 K-177 Junction in Geary County.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Promptly sign and date on the line below, then EMAIL IT BACK TO KDOT at Joshua.Matyi@ks.gov
EVEN IF NOT BIDDING. Any instructions not followed will result in your bid being declared irregular.
If these changes affect any of your subcontractors or suppliers, IT IS YOUR RESPONSIBILITY to inform them. These changes are part of the contract for this project(s). Please call me at (785) 296-7141, if there are questions. Thank you for your cooperation.
(Company Name) (Signature) (Date)
C: District 2 & Junction City Construction Office
4BKansas Department of Transportation
3BBureau of Construction and Materials
0BEstimating Section
To: Prime Contractor Bid Holders
2BFrom: Josh Matyi - Estimating Engineer Associate
5BDate: May 27, 2026 Proposal/Contract No.: 526066212
Subject: Project Notice for the June 17, 2026 Letting
I070-031 KA 7706-01 – Geary County – Lighting
Revised required special provisions:
11-15-17-R02 – ELECTRIC LIGHTING SYSTEM
A revised sheet is included in this addendum.
To view this project’s documents, choose “Addendum #1” from KDOT’s website:
https://kdotapp.ksdot.org/Proposal/Proposal.aspx.
The Contractor is responsible for ensuring the EBS file that the Contractor uses to prepare its Proposal and submits to KDOT contains any amendments. You must update your EBS file by going to the Bid Express website: http://www.bidx.com, choose the correct Letting, locate and select the Proposal number to download 526066212.001X.
We also recommend that you check the Bid Express “Questions and Answers” (https://www.bidx.com/ks/lettings) to review any questions that may have been posted for this project.
REQUIRED CONTRACT PROVISION - 11-15-17-R02 (Rev. 03/26)
ELECTRIC LIGHTING SYSTEM UNIT COST
Prior to award, the contractor shall submit a spreadsheet for the Unit Costs. A spreadsheet template is available on KDOT’s website - https://www.ksdot.gov/doing-business/highway-contractors/contractor-resources - under Other Resources. The completed spreadsheet shall be submitted to the Letting Engineer no later than noon on the Friday after letting day. Once approved, the spreadsheet will be placed on KDOT’s Exploratory Site and incorporated into the contract by reference.
The Contractor shall comply with Section 814 of the Standard Specifications when providing and installing elements of the Electric Lighting System. Add the following at the end of Section 814.4 Measurement and Payment.
The Contractor will submit a unit cost for each individual Electric Lighting item the contract requires. Even though the bid item is a lump sum price, the Engineer will adjust the lump sum price by any increase or decrease in the quantities indicated in the Summary of Quantities shown in the plans. To calculate the adjustment, the Engineer will determine the overrun or underrun quantity for each Electric Lighting System item listed in the contract. The Engineer will multiply any overrun or underrun quantity by the unit cost the Contractor provided. The Engineer will increase the lump sum price by the cost of any overruns and decrease the lump sum price by the cost of any underruns. The sum of the unit costs multiplied by the items listed in the *Summary of Quantities for each site or the entire project must be less than or equal to the lump sum bid, or the unit cost submittal will be rejected. Contractor will then be required to resubmit unit costs that meet this requirement for the bid to be accepted. The Engineer will only negotiate or receive new prices on Electric Lighting System items if they were not identified in the original Summary of Quantities.
Furnished items shall comply with either the List of Prequalified Roadway Lighting Systems and Equipment, or the specifications in the contract document or otherwise approved by the Engineer.
The Secretary may reject this Proposal if the Contractor fails to complete this Required Contract Provision before noon on Friday after letting day.
CONTRACTOR MUST ACKNOWLEDGE Yes
*Refer to the Plans for the ID #
1810202670-31 KA-7706-01
Lin FtTrench and Backfill
L.S. Lump SumElectric Lighting System
2" Schedule 80 Conduit
3" Schedule 80 Conduit
High Mast Light Tower (100')
High Mast Light Tower (110')
High Mast Light Tower (120')
Expansion Joint
Item Unit Quantity
BID ITEM
Item Unit Quantity
Item Unit Quantity
EachSolid State Photo Cell
Cable Support Grip
Each
Each
Each
Each
Each
2" Conduit Clamps w/ Clamp Backs
Each
Each
Each
Each
2" Schedule 40 Conduit
3" Metallic Conduit
2" Metallic Conduit
1" Metallic Conduit
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Lin Ft
Removal of Concrete Base Each
Lin Ft
Each
Each
Each
Each
Each
Each
Each
(HARDWARE)
SYSTEM QUANTITIES
SUMMARY OF ELECTRIC LIGHTING
(MISCELLANEOUS ITEMS)
SYSTEM QUANTITIES
SUMMARY OF ELECTRIC LIGHTING
" X 3" Wedge Type Anchor Bolts8
" X 20'4
Ground Rods with Clamps
Each
Step Down Transformer
Each
Each
Each
(TOWER)
SYSTEM QUANTITIES
SUMMARY OF ELECTRIC LIGHTING
" Heavy Duty Reversible Drill2
Ground Wire ___ AWG
600 Volt 1/C Secondary Cable with
Groundwire, #6 AWG Solid Bare Copper
Lowering Device Controller
NO
ID
1" 90 Degree Sch 40 PVC Conduit Bends 24" Radius
600 Volt 1/C Secondary Cable #10 AWG
Ground Wire (CIC) #6 AWG
600 Volt 2/C Secondary Cable with
Ground Wire (CIC) #10 AWG
600 Volt 2/C Secondary Cable with
Ground Wire (CIC) #8 AWG
600 Volt 2/C Secondary Cable with
Ground Wire (CIC) #4 AWG
600 Volt 2/C Secondary Cable with
Breakaway Connectors
Lin Ft
NO
ID
QuantityUnitItem
Maximum Wattage
Distribution Type
Maximum Wattage
Distribution Type
GEOLOGY (for footing lengths).
c. FOOTING DETAILS AND ENGINEERING
b. UNDERDECK LIGHTING DETAIL.
LIGHTING.
REQUIREMENTS AND QUANTITIES FOR SIGN
a. CONSTRUCTION AND MATERIAL sheets, as applicable:
For additional construction quantities, see the following 4.
items.
Items not specifically called out are subsidiary to other bid 3.
complete the work.
persons, tools, equipment and new hardware necessary to
The bid item “High Mast Light Tower" includes all work 2.
specifically mentioned or not.
operation of the Electric Lighting System whether shown on the plans. To insure complete and satisfactory necessary for the complete installation within the limits supports, interconnections, ground rods, and all incidentals luminaires, lamps, wiring, conduit, conduit fittings, including towers, concrete bases for towers, anchor bolts, furnish and install all lighting equipment necessary, information only. The contractor shall conduct all work, Linear quantities are approximate and included for 1.
NOTES:
(ADDITIONAL CRITERIA)
BASIS OF DESIGN
Other
Other
NO
ID
LED Luminaire (See Basis of Design)
Designed Lumens
Designed Lumens
Junction Box
Item Unit Quantity
Each
Each
Each
(LIGHT POLES)
SYSTEM QUANTITIES
SUMMARY OF ELECTRIC LIGHTING
30" Concrete Base (40' Pole)
NO
ID
40' LED Luminaire (See Basis of Design)
Each
Each
55' LED Luminaire (See Basis of Design) Each
82751
Symmetrical
33988
Type 3
3" 90 Degree Sch 40 PVC Conduit Bends 24" Radius
36" Concrete Base (55' Pole) and Frangible Base
55' Mounting Height Light Pole with 15' Luminaire Arm and Frangible Base
40' Mounting Height Light Pole with XX' Luminaire Arm
High Mast Light Tower (100')(48" Concrete Base)
High Mast Light Tower (110')(48" Concrete Base)
High Mast Light Tower (120')(48" Concrete Base)
ELECTRIC LIGHTING SYSTEMS
CONSTRUCTION QUANTITIES
FHWA APPROVAL
DESIGNED
TE209
STATE
KANSAS
YEARPROJECT NO.
SHEETS
TOTAL
SHEET NO.
DATE REVISIONS APP'DNO.
KANSAS DEPARTMENT OF TRANSPORTATION
04-28-20 Add 55' pole/change footing size C.P.A.01
BY
J.A.P.
03-17-21 High mast footing to 48"/ground rod C.P.A.02 J.A.P.
05-25-23 Added boring S.M.P.03 J.A.P.
-0
K
A -7
-0 l s s .d g n
F il e
P lo tt e d b y K y le .M c C a ll k s .g o v
-M
A Y -2
:1
07-07-23
J.A.P. DETAILED
DESIGN CK. DETAIL CK.S.M.P. S.M.P.
J.A.P.
APP'D. Sara M. Peters
QUANTITIES
QUAN.CK.
TRACED
TRACE CK.
Sh. No.
Lin FtBoring 470 15
K D
O T G ra p h ic s C e rt if ie d
KDOT Graphics Certified 05-27-2026
NEW SHEET - Released by addendum
DATE
VOID PREVIOUS ISSUE
May 27, 2026
New Sheet - Released by Addendum Date: 5/27/26