About this file

This document is an Addendum (No. 1) for a Request for Qualifications (RFQ-8-25-07) issued by Brevard County Purchasing Services for Professional Engineering Continuing Consultant Services focused on Stormwater Master Planning & Analysis and Pollution and Flood Reduction Design Projects. The RFQ has been extended with a new proposal opening date of Friday, January 31, 2025, at 10:00 am, and the final deadline for questions is Tuesday, January 21, 2025, at 5:00 pm. The addendum provides clarifications on submission requirements, including page limits, font specifications, and project documentation guidelines. Respondents can submit up to six projects per service line, with specific formatting instructions for resumes, technical methodology, and project descriptions.

The selection committee includes Bach McClure (Stormwater Program Manager), Rachel Gerena (Engineering Manager), and Billy Prasad (Deputy Director of Planning & Development). Key clarifications include allowing two-page resumes, permitting variations of specified fonts (Arial, Century, Courier, Verdana), and confirming that firms can submit as a prime contractor and also be a subcontractor on another team. The draft contract was revised to specify that only the Board of County Commissioners, County Manager, or designated representative can issue task orders or approve contract modifications. Respondents are required to provide three to six references per service, and the submission must adhere to specific page and formatting guidelines across different tabs of the proposal.

View the file

Other files

File Type Posted
Notice_of_Award.pdf PDF
Selection_Committee_Consolidated_Evaluation_Scoresheet.pdf PDF
Public_Meeting_Notice.pdf PDF
Names_Only_Tab.pdf PDF
Revised_Addendum_4.pdf PDF
Attachment_C_-_FEMA_Contract_Requirements.pdf PDF
Addendum_4.pdf PDF
Addendum_3.pdf PDF
Addendum_2.pdf PDF
Attachment_A_-_Revised_Draft_Contract.pdf PDF
Reference_Form.pdf PDF
Addendum_1.pdf PDF
RFQ-8-25-07_Inv&Specs.pdf PDF
Attachment_A_-_Draft_Contract.pdf PDF
Attachment_B_-_ARPA_Documents.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Purchasing Services 2725 Judge Fran Jamieson Way

Building C, Room 303 Viera, Florida 32940

Professional Engineering Continuing Consultant Services for Stormwater Master Planning & Analysis and Pollution and Flood Reduction Design Projects

RFQ-8-25-07

January 13, 2025

Addendum 1

TO ALL PROSPECTIVE CONTRACTORS

This is an Addendum to and shall be considered as part of the original advertisement package for the above-mentioned Request for Qualifications. Consultants are requested to acknowledge receipt of this Addendum with their submission.

CLARIFICATION TO QUESTIONS ASKED RECEIVED:

1. Question: Will the County reserve answering any questions until after the question cutoff of January

16, and should we expect an addendum soon thereafter?

Response: Addendums will be posted prior to the question cutoff date.

2. Question: The page count in Tab 5 specifies two pages per project but also asks for a one-page list of other projects. Can we assume that the one-page list is in addition to the 12-page total for the six projects?

Response: Yes. List up to six(6) projects (no more than 5 years old) maximum 2 pages per project that best illustrates the Team’s capability to perform similar work required by this RFQ. Also, provide a one-page list of other projects if applicable.

3. Question: Will the County consider extending the proposal opening date to January 31st?Response:

Yes. The RFQ has been extended to January 31.

4. Question: How does the County define "pages"? For example, is one double-sided sheet considered 1-page or 2-pages?

Response: Double-sided pages count as two pages.

5. Question: Can graphics, tables, and resumes have smaller font size than 12-point?

Response: Yes.

6. Question: Can the Headers and Footers of the pages be smaller than 12-point font?

Response: Yes.

Engineering Continuing Consultant Services

RFQ-8-25-07

January 13, 2025 Addendum 1 – Page Two

7. Question: Can the County provide names of selection committee members?

Response: Bach McClure, Stormwater Program Manager, Natural Resources

Rachel Gerena, Engineering Manager, Public Works Billy Prasad, Deputy Director, Planning & Development

8. Question: Tab 2 - Currently the maximum number of pages excluding Org Chart is limited to 2. Would the County expand the page limit to 5?

Response: No. Two pages to describe the team as a whole, 1 page for the Organizational Chart (No font requirement) plus 1 page per each team member Resume.

9. Question: Tab 2 - Due to the size-limitations of 12-point font, would the County consider 2-page resumes?

Response: Two page resumes are allowed.

10. Question: Tab 3 - Currently the maximum number of pages is limited to 2. Due to the expansive list of services requested in this RFQ, would the County expand the page limit to 6 pages to allow respondents to elaborate on the technical methodology for this wide range of services?

Response: The County will allow a total of 4 typed pages. Please note a sheet contains 2 pages is using double sided.

11. Question: Tab 5 - The project information requested under this tab appears more applicable to Stormwater Improvement Projects than it is to Master Planning & Analysis projects. More specifically, Items 4 through 8 only seem relevant to Stormwater Improvement Projects. Should the respondents only provide information for Items 1 and 2 for Master Planning & Analysis Projects that don’t have project aspects that relate to Items 4 through 8?

Response: The respondent needs to provide the information they feel will help them qualify for the service. Items 4 through 8 can apply to Master Planning, since those items will take effect when the project goes from the “Master Plan” phase to the “Construction Phase”. If the Master Plan did not consider items that could make the project not feasible, then the Master Plan, is not a Plan.

12. Question: Tab 5 - If the respondent is pursuing contracts for both service lines, can we provide 6 projects under each of the service lines?

13. Question: Tab 5 - Would the County consider allowing Item 9 (1-page list of other projects) to be printed on 11"x17"?

Response: No.

14. Question: Tab 6 - Is there an expected number of references?

Response: Three (3) to six (6) per service.

15. Question: Tab 6 - How many references are necessary for inclusion in the proposal?

Engineering Continuing Consultant Services

RFQ-8-25-07

January 13, 2025 Addendum 1 – Page Two

Response: Three (3) minimum per service.

16. Question: Tab 6 - If a specific form is not required, could you please clarify whether there is a particular format or specific information that is required?

Response: The Form is attached.

17. Question: The RFQ states that submittals shall be typed using Arial, Century, Courier, or Verdana typeface. Can the County please confirm whether variations of these fonts are acceptable? i.e. Arial Narrow, Arial Nova, Verdana Pro, etc.

18. Question: Do we know the individuals expected to be on the selection committee?

Response: Bach McClure, Stormwater Program Manager, Natural Resources

Rachel Gerena, Engineering Manager, Public Works Billy Prasad, Deputy Director, Planning & Development

19. Question: If a firm submits as prime, can the firm also be a sub on another team?

Clarification:

The Draft Contract is revised on page 6, Section 5 – Authorized Representative and Notices.

The Parties understand and agree that only the Board of County Commissioners, County Manager or designated representative shall have the authority to issue Task Orders or approve changes or modifications to this Contract or a Task Order.

Attachment to be included in Addendum:

Reference Form Attachment A – Revised Draft Contract

ADDITIONAL INFORMATION:

The deadline for Final Questions has changed to Tuesday, January 21, 2025 at 5:00 pm. No further questions considered after this date and time.

Please note that the proposal opening date and time has changed to Friday, January 31, 2025 @ 10:00 am.

All other terms and conditions remain unchanged.

Sincerely, Mary Bowers Purchasing Manager

END OF ADDENDUM NO. 1

Professional Engineering Continuing Consultant Services for Stormwater Master Planning & Analysis and Pollution and Flood Reduction Design Projects
RFQ-8-25-07
January 13, 2025
Addendum 1
TO ALL PROSPECTIVE CONTRACTORS