About this file

This Addendum #1 document clarifies questions from a non-mandatory pre-proposal meeting held on January 24, 2025, for Rogue Community College's Construction Management/General Contractor (CMGC) Services Request for Proposal No. P17926-2025-02-13 for Transportation Technology Buildings. The RFP seeks qualified architects and contractors simultaneously to design and construct two identical 14,000-square-foot transportation training facilities—one at the Redwood Campus (RWC) and one at the Table Rock Campus (TRC)—to deliver the same program experience regardless of location. The project includes demolition of the upper section of an existing S building at RWC, with specific modifications to be determined during the design phase. The RFP closing date is February 13, 2025, at 2:00 PM local time, with proposals submitted to Rogue Community College's Contract and Procurement Director. The anticipated project schedule is detailed on page 8 of the primary RFP document, with selection timeline and subsequent phases outlined therein.

The addendum addresses operational and environmental considerations for the project, including confirmation that no lengthy permit process is anticipated except for conditional use permitting at the RWC location. Space allocation between service bays and vehicle work areas will be determined during the program review and design phase. Environmental feasibility studies and requirements will be addressed in accordance with specifications contained in Addendum 1 of the related Architect RFQ. The document confirms that both design and construction services are being procured in a single solicitation, streamlining the delivery approach for both campus locations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum #1 P17926-2025-02-13 CMGC Transportation Technology

Addendum #1

Construction Management/ General Contractor Services

Transportation Technology Buildings Pre-Proposal Meeting Questions

January 24, 2025, 2:00 PM

Redwood Campus and Table Rock Campus

REQUEST FOR PROPOSAL (RFP)

NO. P17926-2025-02-13

RFP CLOSING (DUE) DATE: February 13, 2025, 2:00 PM Local Time

NO LATE RESPONSES WILL BE ACCEPTED

SUBMIT TO:

Rogue Community College

Attn: Contract and Procurement Director 3345 Redwood Highway, JO Bldg., Rm 12

Grants Pass, Oregon 97527

Addendum #1 P17926-2025-02-13 CMGC Transportation Technology

This addendum is prepared to provide clarifications and answer the following questions posed at the January 24, 2025, Pre-Proposal meeting:

Clarifications:

1. Are we seeking the Architects and the Contractors at the same time?

Correct

2. Will the building at TRC be the same 14,000 square footage as the one at RWC?

Correct, the intent is to create the same program experience, regardless of which campus students attend.

3. Is a lengthy permit process expected?

No, with the exception of additional time for conditional use permitting at the RWC project.

4. Will most of the space be dedicated to service bays/vehicle work?

These details will be determined during the program review and design phase of the project.

5. How soon will a selection be made?

Please reference the anticipated project schedule located in the RFP document, page 8.

6. What part of S bldg. will be demolished?

(Greg showed them) The building is at two elevations. The upper section of the building is planned for demolition. Exact locations and details for demolition will be determined during the design phase of the RWC project.

7. What modifications will be needed to S bldg.?

Details will be determined during the design phase of the RWC project.

8. Has an environmental feasibility study been done, or will one be required for the new construction?

Please reference question 11 issued in addendum 1 of the Architect RFQ.