ADDENDUM #1 ARFQ DEP2100000055.pdf
PDF 21 MB Posted
- Solicitation number
- ARFQ 0313 DEP2100000055 2
- Issued by
- Taylor County, West Virginia
About this file
This addendum modifies an agency solicitation (ARFQ DEP2100000055) issued by the West Virginia Department of Environmental Protection for the DLM Coal Company Plant Hollow Treatment Facility construction project located in Upshur County, West Virginia. The project involves comprehensive construction of acid mine drainage treatment infrastructure, including a treatment building, clarifier, lime silo system, finishing pond, three lift stations (Plant Hollow, Panther Fork, and Cutright), new sludge cells, conveyance lines, electrical systems, and associated support facilities across multiple sites. The solicitation encompasses extensive bid items totaling approximately 950 linear feet of new road construction, 1 lump sum control and pump building, 1 lump sum clarifier, 1 lump sum lime silo system, 5,500 cubic yards of pond sludge removal, and numerous piping, electrical, and site preparation items. A pre-bid conference was conducted on May 11, 2021; interested parties may schedule additional site visits by contacting Chester Wright at (304) 918-7709. The contract performance period and contract term have been established at 15 months from the Notice to Proceed. The engineer's estimate for the project is $8,294,968, though this figure does not reflect pandemic-related price increases.
The addendum addresses 77 questions posed at the pre-bid conference and incorporates revised specifications, revised bid schedules, revised drawings, and clarifications regarding project scope, materials, equipment specifications, and construction sequencing. No price increases are permitted within the contract; however, delays caused by weather conditions or material shortages may justify contract time extensions through change orders. Materials may be ordered early and stored on-site at the contractor's discretion upon submittal approval. The project is subject to an Administrative Order and must maintain minimal treatment of acid mine drainage during construction. Contractors are responsible for construction staking, obtaining borrow and disposal area approvals from WVDEP, managing unsuitable material disposal, and arranging their own water supply. Specific technical specifications have been updated regarding butterfly valves with electric actuators, plug valves with electric actuators, electrical installation requirements, conduit systems, wiring standards, pH sensors, and flocculator mixers. Two revised specifications documents establish new bid items for electrical conduit and wiring upgrades at the Existing DLM Shop location only.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AGENCY SOLICITATION NUMBER – ARFQ DEP2100000055
Addendum Number: __1__
The Purpose of this addendum is to modify the solicitation identified as (“Agency Solicitation”) to reflect the change(s) identified and described below.
Applicable Addendum Category:
[] Modify bid opening date and time
[X] Modify specification of product or service being sought
[X] Attachment of vendor questions and responses
[X] Attachment of pre-bid sign-in sheet
[] Correction of error
[X] Other
Description of Modification to Solicitation:
This Addendum issued to publish and distribute the attached documentation to the vendor community.
1. Questions & Answers 2. Clarifications, Notes, & Changes
3. Revised Bid Schedule 4. Revised Specifications
5. Revised Drawings 6. Pre-bid Sign-In Sheets
Additional Documentation: Documentation related to this Addendum (if any) has been included herewith as Attachment A and is specifically incorporated herein by reference.
Terms and Conditions:
1. All provision of the Agency Solicitation and other addenda not modified herein shall remain in full force and effect.
2. Vendor should acknowledge receipt of all addenda issued for this Agency Solicitation by completing an Addendum Acknowledgement, a copy of which is included herewith. Failure to acknowledge addenda may result in bid disqualification. The addendum acknowledgement should be submitted with the bid to expedite document processing.
Addendum #1
DLM COAL COMPANY
Permit # 138-74, 135-78, 58-77, 23-76
PLANT HOLLOW TREATMENT FACILITY
The following are questions that were identified at the Pre-Bid Conference (PBC) conducted on-site on May 11, 2021, Questions provided to WVDEP Procurement, Project Clarifications, Project Notes, Project Changes, Technical Specification Changes, and Project Plan Changes. The answers and clarifications provided herein take precedence over verbal answers at the PBC and previously provided specifications and descriptions provided in the Solicitation should there be any conflicts between the two.
Q1: When dewatering existing Pond 2, Dugout A and B where does the water discharge to?
A1: The water will go into Existing Pond 1 and discharge into the existing stream.
Q2: When dewatering existing Pond 1 where does the water discharge to?
A2: The water from Pond 1 shall be discharged off the side of the bank into the existing stream.
Q3: Where does the sludge from Pond 1, Dugout A and B get moved to?
A3: The sludge from those ponds shall be disposed of in the existing sludge cell near New
Sludge Cells 1 and 2.
Q4: Where is Cutright Lift Station to be built in relationship to the pond?
A4: See Sheet 76 for location.
Q5: What happens to the caustic tanks after the tanks are no longer used for treatment and flushed?
A5: The tanks shall be moved to the DLM shop area. All valves must be removed and saved and caustic lines must be checked by WVDEP before being disposed of. The tanks will then be scraped once we receive permission to do so.
Q6: Is the 24 inch ball valve in Manhole 1 stainless steel? If so, what if there is a long lead time to receive the ball valve due to recent supply shortages?
A6: Yes, the valve is stainless steel. If there is a long lead time to receive this valve then the 24 inch conveyance line from the equalization basin can be plugged until the valve arrives which will require Pond 2 be drained twice, once for initial pipe installation and again once the valve arrives.
Q7: Is Pond 1 an existing pond?
A7: Yes, Pond 1 is an existing pond to be used for temporary treatment while the Plant Hollow
Facility is being constructed. Once the facility is up and running then existing Pond 1 can be bypassed and the new construction for the Final Pond to replace existing Pond 1 can begin as seen on Sheet 40. BEFORE existing Pond 1 can be bypassed the conveyance line from the Control Tee to Manholes 3 and 4 must be installed.
Q8: Will the WVDEP take care of power setup to the site thru Mon Power?
A8: Yes, we have that setup with the power company to have two drops: one at the Panther
Fork Lift Station and one at the main Plant Hollow Facility.
Q9: Where does power come from for the Cutright Lift Station?
A9: Power will be ran out of the MCC at the Control and Pump Building.
Q10: Is all the electrical conduit at the Plant Hollow Facility paid under the Electrical bid item?
A10: Yes.
Q11: Where are the fiber optic splice boxes located?
A11: Locations are as follows: Control and Pump Building, Cutright Lift Station building, Panther Fork Lift Station Building, Existing DLM Shop, on the power pole running to the Plant Hollow Treatment Facility, and on the power pole for the Panther Fork Lift Station.
The two splice boxes that are on power poles will be mounted on two (2) treated 4 x 4 posts with plywood across the middle. This shall be included under bid item Fiber Optic Armored Cable.
Q12: Is the 24 inch HDPE pipe around the Control and Pump Building and Clarifier dual wall culvert pipe?
A12: Yes, dual wall culvert pipe can be used where and option of either HPDE or C-900 is called out. C-900 must be used in locations where only C-900 pipe is explicitly listed.
Q13: Are all pipes around the Plant Hollow Treatment Facility incidental to the plant area?
A13: No, we have line items for all individual piping in the plant area which are paid by linear footage. The 8 inch underdrain pipe around the Clarifier is incidental to the Clarifier. The 8 inch underdrain pipe around the Control and Pump Building is incidental to the Control and Pump Building.
Q14: What is the engineer’s estimate for the project?
A14: The estimate is $8,294,968. This does not reflect the price increases due to pandemic shortages.
Q15: Is there any extra performance time and/or price increase that can be granted after the project is awarded to accommodate for possible delays in material arrivals and shortage price escalations?
A15: There are no provisions for a price increase within the contract. All prices that are bid remain the same throughout the life of the contract. However, delay for weather condition and material shortage/delays can be considered adequate justification for a project time extension.
Q16: Due to price increases on materials because of current market shortages, if materials are ordered earlier on in the project in order to insure delivery, supply, and to take pricing increases into account could received materials be stored on-site?
A16: The Contractor can purchase materials as soon as a submittal is approved. Storage is at the discretion of the Contractor.
Q17: What is the performance period and contract term of the project?
A17: The performance period is 15 months and the contract term is 15 months. See updated
Special Provisions Section 0-0 Project Information.
Q18: Can you check the elevation on the influent lines on the lift stations?
A18: See revised Sheets 64R,66R,71R,73R,78R,80R.
Q19: For Panther Fork Lift Station, where does the 6inch HDPE piping switch to being paid by the liner foot?
A19: Outside the fenced area. Everything inside the fence is paid under Panther Fork Lift Station as a lump sum. See note on Sheet 69. The chain link fence has a separate bid item of Chain Link Fence and Gates per linear foot.
Q20: What is included with the new caustic tanks?
A20: This includes the new caustic tank, gravel pad, new caustic lines, and metal T post and valves. The length of the lines is estimated.
Q21: Where is the waste material from the excavation of the new sludge cells disposed of?
A21: The material will be used to build the berm around the new sludge cells and to build up the back side as needed. If we need to waste the material, there is room on site at a WVDEP designated location.
Q22: What amount needs to be input into Oasis for the non-bid item of Utilities?
A22: Zero.
Q23: Can we come back and look at the site again?
A23: Yes, please contact Chester Wright at (304) 918-7709 to setup a site visit.
Q24: Will the WVDEP stake out the limits of construction or is the Contractor responsible?
A24: The Contractor is responsible. There is a Construction Layout bid item for this.
Q25: Is the Clarifier to be constructed where Dugout A is currently located?
A25: Yes.
Q26: What do we do with unsuitable material that is excavated from the site?
A26: The unsuitable material can be disposed of in the existing sludge cell. See Sheet 29R for designated borrow areas for good, useable material.
Q27: Is the existing ground where both the Clarifier and Lime Silo are to be constructed suitable for such construction?
A27: Yes, see Technical Specification Section 14-1 Geological Technical Report.
Q28: What is the depth of the mud mat for the Lime Silo?
A28: The depth of the mud mat is 24 feet with 3 feet of AASHTO #3 above on which the 3 feet of Lime Silo foundation sits. See Sheet 63 for details.
Q29: How is the brush generated at the Plant Hollow Site disposed of?
A29: The bigger trees on the northwest side of the Pond 1 must be set aside for the landowner to use as firewood. The trees on the northeast side of the Pond 1 can either be windrowed or stacked out of the way at a WVDEP designated site location. This includes the tops of trees as well. And yes, the trees can also be burned on site.
Q30: Are the depths of Pond 1, Dugout A and Dugout B at the Plant Hollow location known for sludge removal?
A30: No, there is a bid item of Pond Sludge Removal for this purpose. Once all are dewatered each must be surveyed BEFORE sludge removal, the sludge then removed, and each surveyed AFTER to compute volumes removed. See Technical Specification 13-7 Section
3.2 Pond Sludge Removal.
Q31: What is expected for road upkeep?
A31: There is a bid item of Road Maintenance for this which covers all labor for the upkeep and stone placement on existing and newly constructed roads while the project is under construction. The actual stone used on these roads shall be paid under bid item Limestone Incidental Stone.
Q32: When clearing for pipeline installations, is there a certain distance that must be cleared on either side of the line?
A32: Yes, a total of twenty feet (10 feet on either side of the line) shall be cleared. All cleared trees can be windrowed.
Q33: Does the Panther Fork pond need to be drained and cleaned?
A33: Yes.
Q34: What type of metal building is located on Haulroad 3 to be relocated to the Alton site?
Does the building have a concrete floor?
A34: The building is tubular steel and has a gravel floor.
Q35: If it becomes cost prohibitive to move the metal building from Haulroad 3 to the Alton site can the building be left and a new building constructed at Alton?
A35: No, the building is not on WVDEP property and the landowner would like the building removed. The WVDEP would like to repurpose this building since it is in useable condition.
Q36: The entrance/exit gate that must be used off of CR-11/Alexander Helvetia Rd. must be unlocked and opened for each delivery truck to pass then closed at relocked? The gate cannot be left open for the day for multiple, spaced out deliveries?
A36: Yes, the gate must be locked at all times when not in use.
Q37: Where should the Project Sign be located?
A37: Near the Existing DLM Shop.
Q38: For the 24” C-900 tee connection in the Rapid Mix Tank as shown on Sheet 55: PVC pipe is not rigid enough to be stable at the bottom and ductile iron pipe is too heavy.
What type of pipe should be used?
A38: Use gasketed C-900 pipe with stainless steel straps to anchor the pipe to the wall.
Q39: Will you provide a list of plan holders for this job?
A39: The sign-in sheet will be included in this Addendum.
Q40: Is the approximate 6 feet of stone under the Clarifier (as shown on Sheet 51) to be paid for under bid item 14 Limestone Incidental Stone or is this to be incidental to the Clarifier and included in bid item 18 Clarifier?
A40: Yes, the stone is incidental to the Clarifier and therefore will be paid under bid item 18 Clarifier.
Q41: What are the water elevations of existing Pond 1, Pond 2, Dugout A, and Dugout B at the Plant Hollow site (Sheet 18)?
A41: Sheet 07 Existing Conditions-Plant Hollow Section 1 has these elevations labeled.
Q42: What is the slab and wall thickness and resteel layout of the Control and Pump Building on Sheets 46 and 47?
A42: The slab and wall thickness are 1 foot. See revised Sheets 46R and 47R for resteel details.
Q43: Can you review the cut and fill numbers found on Sheet 56?
A43: See revised Sheet 56R.
Q44: Can you provide a resteel detail for the Pond 13 Caustic Tank Building seen on Sheets 99 and 100?
A44: See revised Sheet 100R.
Q45: Can you provide a scale for Sheets 18, 21, and 22?
A45: See revised Sheets 18R, 21R, and 22R.
Q46: Where is the Cementitious Crystalline Concrete Additive indicated in Technical Specification 9-3 required to be used?
A46: This additive must be used in the Clarifier, Rapid Mix Tank, Panther Fork Lift Station, Cutright Lift Station, Plant Hollow Lift Station, Septic Tank, all manholes, Sludge Valve
Boxes, the sump boxes in the bottom of the Final Treatment Pond, the Distribution Trough, Collection Vault, Control Tee Vault and Control Trough.
Q47: Can the bid due date be extended by two weeks?
A47: Currently there is no time extension as this site is under an Administrative Order.
Q48: What size and type of valves are the Electric Actuator Valves on Sheet 46?
A48: See revised Sheet 46R.
Q49: Is the required seeding for New Sludge Cells 1 and 2 and the berm around the Existing Sludge Cell paid under bid item 8 Type I Revegetation or are each incidental to bid item 32 New Sludge Cell 1, bid item 33 New Sludge Cell 2, and bid item 35 Existing Sludge Cell Rehabilitation?
A49: All are paid under bit item 8 Type I Revegatation.
Q50: Are the new access roads to Panther Fork Lift Station and Cutright Lift Station to be paid under bid item 11 New Road Construction Base Layer and bid item 12 New Road Construction Final Layer or are each incidental to the respective lift stations?
A50: Both are paid under bid item 11 New Road Construction Base Layer and bid item 12 New Road Construction Final Layer.
Q51: Is the Final Treatment Pond access road shown on Sheet 30 incidental to bid item 36 Final Treatment Pond or is this to be paid for under bid item 11 New Road Construction Base Layer and bid item 12 New Road Construction Final Layer?
A51: This is paid under bit item 36 Final Treatment Pond.
Q52: How many sump pumps are required under Technical Specification 12-11 Sump Pumps?
A52: Two, one to be installed in the Control and Treatment Building and one to be used as a spare pump.
Q53: How many generators are required for this project?
A53: Two, see Sheet 28 System Schematic and Technical Specification 11-32 Standby Electric Generator for details.
Q54: What type and in what quantity of level indicator instruments are required at the three lift stations?
A54: See Sheets 64R, 65, 66R, 67, 71R, 72, 73R, 74, 78R, 79, 80R and 81 for details.
Magmeters are to be used for flow with three total, one at each lift station. Ultrasonic level transmitters are to be used to measure the water level in the lift stations with three total, one at each lift station.
Q55: Per Technical Specification 12-23 Double Wall Tank, how many tanks are required total?
What fittings and accessories in what sizes and quantities are required?
A55: A total of ten tanks are required: seven to be paid under bid item 65, 1000 Gallon Dual Wall Caustic Tank with Gravel Pad for those at Plant Hollow, Alton, Haulroad 2, Haulroad 3, and Little Woody sites, three to be paid under bid item 66 Pond 13 Caustic Tank Building. See Technical Specification 13-7 Sections 2.18 and 2.19 for required valves and gauges. An approximate length of half inch PEX line is indicated on Sheets 95-98 and 101 for all sites except Plant Hollow. The approximate length of line needed for the Plant Hollow site can be found on Sheet 34 in the Piping and Conduit Schedule, Conduit or Piping Numbers P17A and P17B.
Q56: Are the slurry pumps as indicated in Technical Specification 12-38 Peristaltic Lime Slurry Pump furnished as part of the Lime Silo package or are the pumps to be purchased separately? What size is the spare pump that is required?
A56: The pumps are paid under bid item 17 Lime Silo System but are not automatically furnished by the Lime Silo Manufacturer. The Contractor may choose to request that the Lime Silo Manufacturer provide the slurry pumps as part of the Lime Silo System or the Contractor may choose to order the slurry pumps separately from a third party vendor.
The spare slurry pump must be a Dura 25.
Q57: Technical Specification 12-40 Flocculator Mixer currently requires six mixers, two per clarifier. How many Flocculator Mixers are required and how are the mixers to be paid?
A57: See revised Technical Specification 12-40 Flocculator Mixer. Two Flocculator Mixers are required and are to be paid under bid item 18 Clarifier.
Q58: Sheet 36 Site Profile 1 shows a Concrete Trough with details to be found on Sheet 42, but there are no such details. Can these details be provided?
A58: This detail has been added to revised Sheet 55R.
Q59: The Clarifier stone subgrade appears to be shown at 1922.42’ on Sheet 51 under the entire 80 foot diameter clarifier. This would mean that the stone thickness varies between 1 foot and 5.75 feet thick. Is this correct or should the stone be a uniform thickness under the Clarifier?
A59: Yes, the stone thickness varies under the clarifier.
Q60: Does the Chainlink Fence get 3 strands of barbwire? Or is it to be 6 feet high without barbwire per the detail on Sheet 91?
A60: The Chainlink Fence does not have barbwire and is per the “Chainlink Fence, Typical” detail on Sheet 91.
Q61: Existing Sludge Cell note on Sheet 29 says to add a 3 foot earthen berm around the perimeter of the sludge cell. There is an existing woven wire farm fence around this sludge cell that will have to be removed and reinstalled in order to add the earthen berm. Is this the removal and reinstallation of this farm fence to be paid for under bid item 56 Farm Fence and Gates or is this incidental to bid item 35 Existing Sludge Cell Rehabilitation?
A61: This is to be incidental to bid item 35 Existing Sludge Cell Rehabilitation.
Q62: Is there geotechnical data on the New Sludge Cells 1 and 2 area?
A62: No.
Q63: Due to the size of this project and the current excessive lead times on all materials, this project will not be able to be constructed within the 365 days allowed for substantial completion. Can the performance period be increased to at least 540 days?
A63: No. The performance period has been increased to 15 months. However, as construction begins if it becomes apparent that there will be material shortage/delays this could be considered adequate justification for a project time extension.
Q64: Sheet 30 states that there is a detail for bid item 52 Distribution Trough on Sheet 42 however, no such detail exists. Can you please provide this detail?
A64: See revised Sheet 42R.
Q65: What bid item are the cuts and fills for the Plant Hollow site to be paid under?
A65: Site Preparation.
Q66: For the Fiber Optic Armored Cable, is new cable to be installed to existing poles or are new pole installations required?
A66: The cable will be installed on existing poles at the level that the currently existing telephone wire is located.
Q67: Where is the power pole for the Plant Hollow service located? Is this at the same point as that for the Panther Fork Lift Station?
A67: See new Sheet 29A for Plant Hollow and revised Sheet 68R for Panther Fork.
Q68: Are the generator ATS’s to be outside, service rated, and rated Nema 3R?
A68: All generators will be located outside and must meet all these requirements.
Q69: Is there any HVAC required at the Pond 13 Caustic Tank Building?
A69: No.
Q70: Can details be provided for the new underground HDPE tank at the Existing DLM Shop?
A70: A new 2,000 gallon tank is to be installed at the same location and depth as the existing underground cistern. Roof gutter drains will then be ran into this tank for runoff collection. An overflow pipe will be installed near the top of the tank that will exit to a gravel pad.
Q71: Can details be provided for the new natural gas heater in the bathroom at the Existing DLM Shop?
A71: A natural gas heating unit must be installed capable of providing 5,000 BTU to the 125 square foot bathroom.
Q72: Can note #17 for upgrading the electrical wiring and panels as needed be further clarified for the Existing DLM Shop?
A72: A new panel box will need to be installed with appropriate breakers in order to accommodate both the existing equipment and all new equipment to be installed. New bid items 70 Conduit and 71 Wiring will be added to the bid schedule to account for these installations at ONLY the Existing DLM Shop.
Q73: Is the sludge only to be removed from Pond 1 and Dugouts A and B?
A73: No, sludge does need to be removed from all of these but also from the Panther Fork
Pond. See revised Sheet 21R.
Q74: What are the correct dimensions of the Control Tee Vault shown on Sheet 42?
A74: See revised Sheet 42R. The interior dimensions are 5.0 ft X 7.0 ft. The exterior dimensions are 6.0 ft X 8.0 ft. The dimensions for the aluminum grating are 4.25 ft X
6.25 ft.
Q75: The Control Tee Vault detail on Sheet 42 shows slide gate details. How many slide gates are required and where should the slide gates be located?
A75: Yes, there are slide gates required in the Control Tee Vault. Two slide gates must be installed as shown on the detail on revised Sheet 42R.
Q76: Can Dutchland Inc. be included as a base bid option for the circular clarifier tanks?
A76: No, not at this point in time. However, once the project is under construction Dutchland, Inc. may be provided as a submittal and may be approved as an Engineer Approved Equal per Special Provisions 0-13 Engineer Approved Equal.
Q77: Is the 8” PVC Clarifier underdrain as seen on Sheet 51 to be paid for under bid item 46, 8 Inch SDR-35 Gravity Line or is this incidental to the Clarifier?
A77: This is incidental to the Clarifier bid item 18.
CLARIFICATIONS, NOTES, AND CHANGES
1. BEFORE any excavation is performed for this project all natural gas companies must be contacted to mark line locations.
2. Performance period extensions may be addressed if need arises as project construction progresses though a change order.
3. Bid items 70 Conduit and 71 Wiring have been added to the project and are ONLY for electrical upgrades at the Existing DLM Shop. These bid items shall not be used as payment for any other project locations.
REVISED SPECIFICATIONS
1. Special Provisions 0-0 Project Information: Section 2.0 Contract Period has been updated to 15 months. Section 3.0 Contract Term has been updated to 15 months.
2. Technical Specification 10-2 Butterfly Valve with Electric Actuator: Specification added.
3. Technical Specification 10-6 Plug Valve with Electric Actuator: Section 2.2.B.1., motor details updated, Section 2.4 added.
4. Technical Specification 11-1 Electrical Installation Requirements: Section 1.4.Y and 1.4.Z added.
5. Technical Specification 11-6 Conduits: added pay item “Conduit”.
6. Technical Specification 11-7 Wire and Cable (600V and Below): added pay item “Wiring”.
7. Technical Specification 12-40 Flocculator Mixer: Section 1.1.A., quantity of flocculator mixers was updated to two (2).
REVISED BID SHEET
1. Bid item 11 New Road Construction Base Layer footage was increased.
2. Bid item 12 New Road Construction Final Layer footage was increased.
3. Bid item 19 Rapid Mix Tank was increased to include the construction of the Concrete Trough.
4. Bid item 69 Pond Sludge Removal cubic yardage was increased.
5. Bid item 70 Conduit has been added to pay for electrical upgrades at ONLY the Existing DLM Shop.
6. Bid item 71 Wiring has been added to pay for electrical upgrades at ONLY the Existing DLM Shop.
REVISED DRAWINGS
1. SHEET 03R-SUMMARY OF QUANTITIES: increased linear footage of NEW ROAD CONSTRUCTION BASE LAYER and NEW ROAD CONSTRUCTION FINAL LAYER, added bid items CONDUIT and WIRING.
2. SHEET 18R-DEMOLITION-PLANT HOLLOW SECTION 1: added scale to drawing.
3. SHEET 21R-DEMOLITION-PANTHER FORK: added scale to drawing, updated “Panther Fork Pond Note”.
4. SHEET 22R-DEMOLITION-CUTRIGHT: added scale to drawing.
5. SHEET 28R-SYSTEM SCHEMATIC: added second pH probe to the Clarifier, updated “Available Power” to 800 AMP.
6. SHEET 29A-PLANT HOLLOW TREATMENT FACILITY POWER POLE
LOCATION: new sheet added.
7. SHEET 29R-PROJECT PLAN OVERVIEW PLANT HOLLOW TREATMENT
FACILITY: updated drawing to show borrow areas.
8. SHEET 34R-PIPING AND CONDUIT OVERVIEW SCHEDULE: updated Conduit or Piping Number P28 Piping Size to 8 inches.
9. SHEET 36R-PLANT HOLLOW TREATMENT FACILITY SITE PROFILES 1 AND 2:
updated Sheet reference numbers for Manhole 1, Palmer Bowlus Flume, Concrete Trough, and Distribution Trough details.
10. SHEET 41R-MANHOLE DETAILS: updated “Manhole 1” detail.
11. SHEET 42R-PALMER BOWLUS FLUME, CONTROL TEE VAULT, COLLECTION
VAULT, AND DISTRIBUTION TROUGH DETAILS: updated “24 Inch Palmer Bowlus Flume with Fiberglass Manhole” detail, “Control Tee Vault” detail, and “Note(s)”; added “Distribution Trough” detail.
12. SHEET 46R-CONTROL AND PUMP BUILDING PLAN VIEW: added “Building Floor Resteel Detail”.
13. SHEET 47R-CONTROL AND PUMP BUILDING PUMP PIT SECTIONS: added “Pump Pit Resteel Detail”.
14. SHEET 48R-CONTROL AND PUMP BUILDING PLAN VIEW ELECTRICAL:
updated actuator valve label.
15. SHEET 50R-CLARIFIER PLAN VIEW: updated label to show 2 pH probes.
16. SHEET 55R-RAPID MIX TANK AND CONCRETE TROUGH: updated “Rapid Mix Tank” details and “Note(s)”; added “Concrete Trough” detail.
17. SHEET 56R-PLANT HOLLOW TREATMENT FACILITY CUT AND FILL
OVERVIEW: updated cut and fill quantities.
18. SHEET 61R-LIME SILO ELEVATION AND INTERNAL VIEWS: updated “Elevation View” detail.
19. SHEET 62R-LIME SILO ROOF AND FLOOR PLANS: updated “Floor Plan” detail.
20. SHEET 64R-PLANT HOLLOW LIFT STATION: updated items 21 and 72.
21. SHEET 66R-PLANT HOLLOW LIFT STATION PROFILE VIEW: updated “Wet Well” detail elevations.
22. SHEET 71R-PANTHER FORK LIFT STATION: updated items 21, 24, and 72.
23. SHEET 73R-PANTHER FORK LIFT STATION PROFILE VIEW: updated “Wet Well” detail elevations.
24. SHEET 78R-CUTRIGHT FORK LIFT STATION: updated items 21, 24, and 72.
25. SHEET 80R-CUTRIGHT FORK LIFT STATION PROFILE VIEW: updated “Wet Well” detail elevations.
26. SHEET 85R-NEW SLUDGE CELLS 1 AND 2: updated cut quantity for “New Sludge Cell 1”.
27. SHEET 100R-POND 13 CAUSTIC TANK BUILDING EXTERIOR ELEVATION
VIEW AND CONCRETE SLAB DETAILS: added “Concrete Slab” detail; updated “Note”.
28. SHEET 104R-ELECTICAL ONE LINE: updated to remove generator from existing DLM shop.
28. SHEET 108R-CONDUIT ONE LINE: updated electrical.
29. SHEET 109R-PANTHER FORK LIFT STATION CONDUIT ONE LINE: updated electrical.
30. SHEET 110R-CUTRIGHT LIFT STATION CONDUIT ONE LINE: updated electrical.
31. SHEET 111R-CONDUIT SCHEDULE: updated Conduit Numbers C94-C109.
32. SHEET 121A-DLM SITE ENTRANCE POINT AND ROAD: added to show location of gate to be used as project site entrance/exit point and path to Existing DLM Shop.
26. SHEET 85R-NEW SLUDGE CELLS 1 AND 2: updated cut quantity for “New Sludge Cell 1”.
27. SHEET 100R-POND 13 CAUSTIC TANK BUILDING EXTERIOR ELEVATION
VIEW AND CONCRETE SLAB DETAILS: added “Concrete Slab” detail; updated “Note”.
28. SHEET 108R-CONDUIT ONE LINE: updated electrical.
29. SHEET 109R-PANTHER FORK LIFT STATION CONDUIT ONE LINE: updated electrical.
30. SHEET 110R-CUTRIGHT LIFT STATION CONDUIT ONE LINE: updated electrical.
31. SHEET 111R-CONDUIT SCHEDULE: updated Conduit Numbers C94-C109.
32. SHEET 121A-DLM SITE ENTRANCE POINT AND ROAD: added to show location of gate to be used as project site entrance/exit point and path to Existing DLM Shop.
0-0 (1)
0-0 PROJECT INFORMATION
1.0 LOCATION / SITE DESCRIPTION
The DLM Coal Company Plant Hollow Treatment Facility Permit # 138-74, 135-78, 58-77, 23-76 is located near French Creek (Upshur County) West Virginia.
The project will involve but is not limited to the construction of a treatment building, clarifier, lime silo system, finishing pond, lift stations, sludge cells, and conveyance lines.
DIRECTIONS TO THE SITE:
From I-79 N near Weston, WV take Exit 99 onto US-119 N/US-33 E toward Buckhannon. Travel 13.9 miles and take the exit toward Country Rd. 12/Main Street. Turn right onto Old Weston Road then continue onto W Main Street. Make a right onto S Locust St. and continue onto WV-20 S/S Kanawha St. for 7.8 miles.
Turn left onto Alton Rd./Evergreen Alton and proceed 4.2 miles and take a left onto Alton Rd./Evergreen Alton/Strawberry Drive. Continue 1.8 miles then take a right onto Evergreen Alton/French Creek Panther Fork/Slab Camp. Travel 1.1 miles and turn right onto Alton Ridge Rd./Evergreen/French Creek Panther Fork/Panther Fork/Slab Camp; drive 0.8 miles and turn a sharp left to stay on Alton Ridge Rd./Evergreen/French Creek Panther Fork/Panther Fork/Slab Camp for another 1.9 miles and turn left; proceed to driveway on right to DLM Shop. (Latitude 38°48’47.16”N and Longitude - 80°11’35.52”W).
2.0 WORK PERFORMANCE PERIOD
The “Contract Period” for the project is 15 months commencing on the date as defined in the Notice to Proceed letter. This period is defined as the amount of contract time allowed by the WVDEP for substantial completion of the project.
The “Contract Period” shall comply with Standard Specifications Section 14 Determination and Extension of Contract Time.
3.0 CONTRACT TERM
The “Contract Term” for the project is 15 months commencing on the date as defined in the Notice to Proceed letter. The Contract Term defines the beginning and end dates of the contract.
4.0 REFERENCE SPECIFICATIONS / DEFINITIONS
All references to "Owner" in these Specifications shall mean West Virginia Department of Environmental Protection, Office of Special Reclamation (WVDEP).
E022284 Highlight 15 months
E022284 Highlight
0-0 (2)
All references to "Engineer" in these Specifications shall mean the WVDEP's Engineer or authorized representative.
All references to "ASTM" shall mean the American Society of Testing and Material Specifications, Latest Edition unless otherwise noted.
All references to "AASHTO Specifications" shall mean the Standard Specifications for Transportation Materials and Methods of Sampling and Testing by the American Association of State Highway and Transportation Officials, latest edition, and all subsequent addenda thereto.
All references to "WVDOH Standard Specifications" shall mean State of West Virginia Department of Transportation, Division of Highways Standard Specifications for Roads and Bridges, adopted 2010, and all-subsequent addenda thereto.
All references to the "Contractor" shall be understood to mean the successful bidder and or firm or corporation undertaking the execution of the work under the terms of these Specifications.
All references to "OSHA" shall be understood to mean The Occupational Safety and Health Administration and the standards set in the Occupational Safety and Health Act of 1970.
All references to “AMD” shall be understood to mean all acid mine drainage discharges from the project site.
5.0 SCOPE OF WORK
The Contractor shall perform all operations necessary for:
clearing and grubbing at the site;
construction and installation of support areas and access roads to the site and coordination of work activities with landowner and complying with WVDOH rules and regulations;
regrading and excavation of the project site as approximated by the lines and grades shown on the Project Plans for the construction of the treatment plant and the construction and/or upgrading of treatment/sedimentation ponds and new sludge cells, and the moving of all unsuitable or excess material to a Contractor-locate and/or WVDEP permitted waste disposal area;
construction of new conveyance lines, lift stations and ditches;
upgrade existing caustic tanks;
0-0 (3) erosion and sediment control with best management practices;
revegetation of disturbed areas to also include erosion control matting in select areas.
The Contractor shall also be responsible for surveying, including establishing construction baseline, measuring, and developing all completed quantities on the job, and for ordering, purchase and delivery of all materials required for construction or required for development of support areas. The Contractor shall perform all other operations as incidental to the program as specified herein.
6.0 SCHEDULE OF WORK
Before commencing work on this project, the Contractor shall prepare and submit a schedule of construction activities for approval by the WVDEP. The WVDEP requires that minimal treatment of the acid mine drainage continue during the construction of the facility. The sequence of construction is listed in Sub-Section 7.0 of this Specification. The Contractor will be required to maintain access at all times to the facility, and upon completion of the project the access road condition shall be equal to or better than existed upon mobilization activities.
The Contractor shall provide adequate supervision, labor, tools, equipment, and materials to prosecute the work energetically and complete the work within the time specified. The Contractor shall demonstrate to the Engineer that sufficient sized and quantity of equipment shall be mobilized to ensure this Project is completed within specified time frames or sooner. The required Schedule to be submitted (mentioned above) shall include a list of said properly sized and quantity of equipment, along with projected earth moving and excavation capabilities as well as hauling, and grading rates to complete the tasks herein specified within stated time frames.
The WVDEP has no intention to delay the work for the checking of lines or grades, but if necessary, working operations shall be suspended for such reasonable time as the Engineer may require for the purpose. No special compensation shall be paid for the cost to the Contractor for any of the work or delay occasioned by checking lines and grades, by making other necessary measurements, or by inspection.
7.0 SEQUENCE OF CONSTRUCTION
1. Install treatment bypass line from existing Pond 2 to Pond 1.
2. Regrade part of existing access road and construct new section of access road and Treatment Facility pad area.
3. Construct Control and Pump Building, Clarifier, Lime Silo System, Non-
Potable Water System and Finishing Pond.
4. Install conveyance lines and ditches to Treatment Facility.
0-0 (4)
5. Construct Lift Stations.
6. Construct New Sludge Cells 1 and 2.
7. Existing Shop Upgrades.
8. Decommission existing caustic tanks and install new tank upgrades.
8.0 BORROW (DISPOSAL) AREAS
All borrow (disposal) areas must be approved by WVDEP. Should the Contractor decide to obtain and utilize any borrow areas outside of construction limits, or move material from one property owner to another (unless designated), the Contractor shall be responsible to obtain (from the property owner(s) of the borrow areas) all necessary rights of entry, including rights of entry for WVDEP and OSMRE for inspection purposes. The said rights of entry agreement must state that the property owner(s) indemnify and hold harmless the WVDEP for Contractor’s action for any injury or damages whatsoever resulting from the use of the property.
The Contractor also shall submit borrow or waste area reclamation plans for prior approval by WVDEP. The Contractor shall observe the following NEPA compliance schedule relative to selecting and utilizing any off site borrow areas and or any waste disposal areas.
A. No borrow (disposal) site operations will affect a site listed in, eligible or proposed to be listed in the National Register of Historic Places.
B. No borrow (disposal) operations will be located within one-quarter mile of any federally listed established or prospective component of the National Wild and Scenic River System under 16 USC 1274 and 1276.
C. Borrow (disposal) site operations will not cause a significant encroachment within the base floodplain (CE.O. 11988: Floodplain Management).
D. Borrow (disposal) site operations will not be located in or affect a critical habitat of a Federally listed endangered or threatened species under 16 USC 1531, et. seq.
E. No borrow (disposal) operations will occur in wetland areas which are designated by appropriate agencies.
F. Borrow (disposal) site operations will be consistent with any approved plans governing ambient air quality.
G. Adherence to these mitigation measures does not relieve the Contractor of the obligation or responsibility to obtain any other Federal, State, or local approvals required to use borrow (disposal) areas and conduct such activities.
0-0 (5)
H. Documentation: Copies of borrow (disposal) site approvals and concurrences will be submitted to the WVDEP prior to the commencement of reclamation activities.
I. Site Monitoring: Borrow (disposal) activities will be monitored by the State to ensure compliance with contractual requirements, applicable Federal, State, and local laws, and any permit conditions.
9.0 DISPOSAL OF UNSUITABLE MATERIAL
All disposal areas shall be obtained in accordance with Sub-Section 8.0 of this Specification. All unsuitable materials (wood, trash, debris, and garbage) as determined by the Engineer, shall be wasted by the Contractor, at the Contractor’s expense, outside the limits of work conforming to the requirements of the applicable listed items in Sub-Section 8.0 of this Specification. Wood may be burned in designated areas in conformity with Technical Specifications Section 5-1 Site Preparation. Coal, coal refuse, black or dark gray shales, and exposed coal seams and other similar potentially toxic (acidic) materials shall be soil covered on-site and in accordance with these Specifications.
The Contractor shall observe the NEPA compliance schedule relative to selecting and utilizing any off-site disposal areas in accordance with Sub-Section 8.0 of this Specification.
10.0 WATER SUPPLY
There is no potable water available at the site. Arrangements for water supply shall be made by the Contractor, and all costs for such arrangements shall be borne by the Contractor at no additional cost to the department.
11.0 UTILITIES AND OTHER OBSTRUCTIONS
The name, address, and phone number of the WVMISS Utility location service and of the utility companies are as follows:
WV 811 Formerly WV Miss Utility 811 or 1-800-245-4848
FirstEnergy David Tennant 4431 US Highway 33E
Weston, WV 26452
(304) 269-6895
12.0 CITATION OF OTHER SPECIFICATIONS
0-0 (6)
Whenever the Specifications for this Contract refer to the specifications of any society, institute, association or government organization, then such specifications cited shall become a part of this Contract as if written in full. Commonly used abbreviations have the following meanings:
ASTM - American Society for Testing Materials
ASA - American Standards Association
AWWA - American Water Works Association
AASHTO - American Association of State Highway and Transportation Officials
ACI - American Concrete Institute
USFHWA – United States Federal Highway Administration
Where reference is made to a specification, it shall be the latest revision at the time called for bids, except as noted on the Project Plans or elsewhere herein.
END OF SECTION
10-2 (1)
10-2 BUTTERFLY VALVE WITH ELECTRIC ACTUATOR
1.0 GENERAL
1.1 DESCRIPTION
A. Furnish labor, materials, equipment and incidentals necessary to install butterfly valves with actuator. Related work specified elsewhere.
1. Special Provisions Section 0-11 Submittals.
1.2 QUALITY ASSURANCE
A. Butterfly Valve with electric actuator
1. Valves shall comply with all applicable provisions of AWWA, including performance tests, leakage test and hydrostatic tests.
1.3 SUBMITTALS
A. Submit the following in accordance with Special Provisions Section 0-11 Submittals.
1. Manufacturer's literature for all types of valves to be used.
2. Certificates of compliance and testing results.
1.4 BASIS OF DESIGN
A. The BASIS OF DESIGN for the Butterfly Valve with Electric Actuator is by Crispin-Kflo (Series 500 for three (3) inch to twenty (20) inch and Series 47 for twenty-four (24) inch and larger) and Auma Actuator Model SQ12.2/IMCO1.1 Quarter turn electric actuator, having been deemed to represent the minimum level of quality, performance and service acceptable for this equipment. Equal equipment submittals will be in accordance with Special Provisions Section 0-13 Engineer Approved Equal.
2.0 PRODUCTS
2.1 BUTTERFLY VALVE
A. All butterfly valves shall be of the tight-closing, rubber-seated type, con-forming to the design standards of ANSI/AWWA C504 latest revision, except where noted herein. Valves shall be bubble-tight at the rated pressure in either direction and shall be suitable for throttling service
10-2 (2) and/or operation after long periods of inactivity. Maximum operating non-shock shut-off pressure and maximum operating non-shock line pressure is 150 psi. Each valve shall be performance and leak tested as specified in
AWWA C504 revised as follows: In addition to the testing requirements of
AWWA C504, each butterfly valve shall be thoroughly cleaned and opened at least three (3) times prior to testing.
B. All items shall have the name or symbol of the maker, the nominal size, date of manufacture, and the working pressure for which the items are designed, cast, stamped, or permanently marked on the body.
C. Butterfly valves shall be Class 150B, unless otherwise indicated and of the flanged short body design. The valve bodies shall be constructed of cast iron ASTM A-126, Class B or ductile iron in accordance with ASTM A-536 with ANSI B16.1 flange drilling or for mechanical joint ends shall conform to ANSI/AWWA C111/A21.11 standard. Flanges shall conform to AWWA
Class D standards.
D. Discs for valve sizes three (3) inch to twenty (20) inch shall be of the concentric design. Valve discs shall be constructed of 316 stainless steel for sizes three (3) inch to eight (8) inch and epoxy coated ductile iron
ASTM A-536 for sizes ten (10) inch to twenty (20) inch. Discs for valve sizes twenty-four (24) inch and larger shall be of the offset design to provide a full 360 degree seating surface and shall be constructed from epoxy coated ductile iron ASTM A-536. Valve disc shall have a 316 stainless steel seating edge. Valve disc shall seat at 90 degrees to the access of the pipe and shall require no torque to hold the valve disc in the closed position.
E. Valves three (3) inch to twenty (20) inch shall have a one piece through shaft constructed of stainless steel ASTM A-276, grade 304, corresponding to the requirements of AWWA C504, latest revision. The shaft shall be fastened to the disc by means of a threaded disc pin providing a positive leak proof connection of the shaft to the disc. Valves twenty-four (24) inch and larger shall have stub shafts of stainless steel
ASTM A-276, grade 304, corresponding to the design requirements of
AWWA C504, latest revision. The shafts shall be fastened to the disc by straight pins that provide a .005 interference fit. The use of taper pins for the shaft/disc connection is not acceptable.
F. The resilient seat shall be Buna-N for valves three (3) inch to twenty (20) inch and shall be simultaneously bonded and vulcanized to body of the valve. All interior surfaces in contact with water, excluding stainless steel and disc, shall be completely rubber lined. Seats for valves three (3) inch to twenty (20) inch shall be designed so that the seats will require no
10-2 (3) internal adjustment or maintenance to seat against a pressure differential of one hundred and fifty (150) psi on either side of the valve. The resilient seat shall be Buna-N for valves twenty-four (24) inch and larger and shall be mechanically retained in the body by means of 316 stainless steel attachment hardware. The seat shall be fully adjustable and replaceable in the field with the use of a standard wrench. No special tools shall be required. Valve seat designs in the body that require the use of epoxy to retain the seat or fillers to increase seat compression are not considered mechanically retained, field replaceable, or adjustable, and will not be accepted. Valves with seat designs that are located on the disc will not be acceptable.
G. All bearings shall be of the self-lubricating, corrosion-resistant, sleeve type. Bearings shall be designed for horizontal and/or vertical shaft loading. The valve assembly shall be furnished with a factory set two-way thrust bearing designed to center the valve disc in the valve seat at all times.
H. Shaft packing shall be of the V-type, self-adjusting type and suitable for pressure and vacuum service. Valves twenty-four (24) inch and larger shall be designed with pull down packing which shall be fully adjustable and replaceable without removing the actuator. The packing shall be
PTFE, interlocking braid, self-compensating type. Stuffing boxes for pull down packing shall have a depth sufficient to accept at least four (4) rings of self-compensating type packing specifically selected for the operating pressure to be encountered.
I. The Manufacturer shall certify that the butterfly valves are capable of operating in continuous duty service under the specified pressures and flow conditions.
J. The interior of valves three (3) inch to twenty (20) inch shall be completely rubber lined. The valve disc shall either be entirely 316 stainless steel or be ductile iron with epoxy coating from an AWWA NSF-61 coating system.
The use of liquid epoxy on body interior surfaces shall not be allowed.
Valves twenty-four (24) inch and larger: the interior of the valve body and the exterior of the valve disc shall be cleaned and sandblasted and lining shall be applied as per the Manufacturer’s instructions. The lining material shall be in compliance with ANSI/NSF Standard 61, for contact with potable water. The lining material shall be “Pota -Pox” as manufactured by
Tnemec, or equal. The interior lining shall be applied in a minimum of two
(2) coats, at four (4) to five (5) mils per coat; the total dry thickness shall be eight (8) – ten (10) mils.
K. The exterior surfaces shall be cleaned and sandblasted and coating shall
10-2 (4) be applied in accordance with the Manufacturer’s instructions. Surface face cleanliness shall be inspected and any contaminants on the surface shall be removed prior to the coating operations. The coating material shall be “Pota- Pox” as manufactured by Tnemec, or equal. The coating material shall be applied in a minimum of two coats, at four (4) to five (5) mils per coat; the total dry thick- ness shall be eight (8) – ten (10) mils.
2.2 ELECTRIC ACTUATOR FOR MOTORIZED VALVES
A. General
1. Actuators shall be designed for valve operation to ensure proper function in accordance to EN 15714-2:2010 electric actuators for industrial valves - basic requirements. Depending on application actuators shall be designed for ON-OFF, short-time duty (S2-15min) respectively Class A and B according to EN 15714-2 or MODULATING, intermittent duty (S4-25%) respectively Class C with up to 1.200 starts per hour; no. of starts depending on actuator size and output speed.
2. Actuator shall have a design life of ten (10) OPEN-CLOSE-OPEN cycles, each consisting of thirty (30) turns per sense of rotation and must be suitable for operating in any mounting position. Actuator design must provide simple setting, testing, maintenance and repair.
3. Actuator settings shall be performed non intrusive via push-buttons at motor control without special tools or instruments (e.g. battery backed setting tool).
4. Electrical connection of actuators to be multi pin plug and socket connector, allowing quick disconnection in case of maintenance or repair. In order to prevent loss of screws during commissioning or maintenance, all covers shall be fixed with captive screws. In order to minimize the amount of spare parts required, parts such as covers, plug and sockets, parts must be interchangeable throughout all model sizes.
5. Torque-transmitting housings must be made of cast iron, except motor housing. No plastic parts of any type shall be used, except for electric / electronic components, operating knobs / levers, indicator mechanism and sealing elements as far as applicable.
6. Depending on valve application, actuators shall be self-locking. Self-locking shall remain active if actuator is switched to hand-operation-mode. For non-self-locking actuators with high output speeds a mechanical anti-back drive device shall be provided attached to the actuator.
7. Valve mounting dimensions shall be according to ISO 5210 with use of a plug sleeve connection adapting to valve shaft. For rising stem applications, actuator design must allow actuator removal from output drive without disturbing the valve function.
10-2 (5)
B. Electric Motors
1. Motors must be suitable for operating at single (1) phase power supply voltage of 120/240Volt AC (+/- 10%) and shall be specifically designed for valve-actuator operation, characterized by high starting torque, low stall torque and low inertia. Motors shall be totally enclosed non-ventilated type (TENV). Motor housings and covers to be made of sea water resistant aluminum. Motor-insulation must be in accordance with IEC 85 Class F (155° C). Motors must be protected by three (3) thermal monitoring devices, which are embedded in motor windings. Motor connections shall be internal by means of plug and socket.
2. Motors must be totally separated from lubricant-filled gearing of actuator, allowing replacement of motor without loss of lubricant regardless of mounting position. Motors shall have a dog coupling as mechanical connection to actuators worm shaft.
3. Actuator motors must develop full torque when power is turned on.
All motors shall be of high starting torque type to facilitate 'unseating' of the valve. Each motor shall have a rating plate marked in accordance with IEC 34.1 as far as applicable.
C. Sizing
1. One actuator size (same outside dimensions) shall be available covering output speeds from four (4) to one hundred and eighty
(180) rpm for a given torque range, to avoid over sizing and unnecessary weight load on valve stem,…