This addendum to a Request for Proposal is issued by the Anchor Bay School District in Michigan for an Energy Savings Performance Contract involving Building Automation System (BAS) and Direct Digital Control (DDC) upgrades. The addendum, dated July 28, 2026, modifies and clarifies the original bidding documents issued July 17, 2026, and provides detailed specifications for control device additions across multiple air handling unit types, including VAV units, single-zone constant volume units, roof-mounted units, fan coil units, blower coil units, zone duct booster coils, VAV boxes with reheat coils, and vertical unit ventilators. Bids must be received at the district's Administrative Office no later than 1:00 PM local time on July 31, 2026. All bidders are required to acknowledge receipt of this addendum on their bid forms, with failure to do so potentially resulting in bid rejection.
The addendum specifies which control sensors and measurements are to be included in the base bid versus provided as add-alternate pricing options. Base bid items include CO2 sensors in return and outside air (one per school), outdoor airflow measurements where applicable, room temperature sensors for zone tempering coils, full fan speed modulation for fan coil units, condensate overflow switches, fan motor status sensors, freeze protection sensors, and warmer/cooler adjustment capabilities for room sensors. Add-alternate pricing is required for return air humidity sensors, filter air pressure drop sensors, and discharge air temperature sensors, all designated for alarming purposes only rather than unit control. Additionally, the addendum replaces the original sequence of operations for vertical unit ventilators with a new Exhibit D effective July 28, 2026, establishing new operational parameters for those devices.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Anchor Bay School District – Energy Savings Performance Contract
BAS/DDC Controls Upgrades - Request for Proposal – Addendum No. 1
Centrix Energy 792 Lois Dr Sun Prairie, WI 53590
(817) 506-8303
July 28, 2026
TABLE OF CONTENTS
ADDENDUM NO. 1
OVERVIEW
MODIFICATIONS AND CLARIFICATIONS
ATTACHMENTS
Exhibit D. Sequence of Operations – Vertical Unit Ventilators – dated 7/28/2026
ADDENDUM NO. 1
Project: Anchor Bay School District – Energy Savings Performance Contract
BAS/DDC Controls Upgrades – Addendum 1
TO: All Prospective Bidders/Contractors
DATE: July 28, 2026
RE: Addendum No. 1 – Clarifications and Modifications
OVERVIEW
This Addendum No. 1 is incorporated into the original Bidding Documents dated July 17, 2026, for the above-referenced project. The purpose of this addendum is to clarify, revise, and/or supplement the bidding documents as noted below. As stated in the original RFP, bids are to be received at the district’s Administrative Office, no later than 1:00PM (local time) on July 31, 2026.
All bidders shall acknowledge receipt of this Addendum No. 1 in the space provided on the Bid Form. Failure to acknowledge receipt of this addendum may result in rejection of the bid.
Where any item in this addendum conflicts with the original Request for Proposal (RFP) bidding documents, the requirements of this addendum shall govern and take precedence.
MODIFICATIONS AND CLARIFICATIONS
1. Scope clarification for control devices to be added, as originally described in Exhibit C (Sequence of Operations)
a. VAV Air Handling Units:
i. Return Air Humidity Sensor
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
ii. CO2 (return air)
1. Required where the AHU’s have outside air and mixed air damper actuators – to be added in Base Bid
iii. C02 (outside air)
1. Sensor required for each school, not for each unit – to be added in Base Bid
iv. Filter air pressure drop
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
b. Single Zone Constant Volume Air Handling Units:
i. Outdoor Airflow Measurement
1. Required where the AHU’s have outside air and mixed air damper actuators – to be added in Base Bid
ii. Return Air Humidity Sensor
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
iii. CO2 (return air)
1. Required where the AHU’s have outside air and mixed air damper actuators – to be added in Base Bid
iv. C02 (outside air)
1. Sensor required for each school, not for each unit – to be added in Base Bid
v. Filter air pressure drop
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
vi. Room temperature sensor if zone tempering coils are used
1. Yes, required sensor - to be added in Base Bid
c. Constant Volume Roof Mounted Units:
i. Outdoor Airflow Measurement
1. Required where the AHU’s have outside air and mixed air damper actuators – to be added in Base Bid
ii. Return Air Humidity Sensor
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
iii. CO2 (return air)
1. Required where the AHU’s have outside air and mixed air damper actuators – to be added in Base Bid
iv. C02 (outside air)
1. Sensor required for each school, not for each unit – to be added in Base Bid
v. Filter air pressure drop
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
d. Fan Coil Units: (these devices originally operated under factory controls)
i. Full fan speed modulation
1. Replace existing functionality – to be added in Base Bid
ii. Return Air Humidity sensor
1. Provide ADD ALTERNATE - this will be for alarming only, not for control of unit)
iii. Discharge air temperature
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
iv. Condensate overflow switch
1. Yes, required sensor - to be added in Base Bid
v. Fan motor status
1. Yes, required sensor - to be added in Base Bid
vi. Filter air pressure drop
1. Provide ADD ALTERNATE price - this will be for alarming only, not for control of unit
vii. Freeze protection
1. Yes, required sensor – to be added in Base Bid
e. Single Zone Blower Coil Units:
i. Room sensor
1. Yes, required sensor – to be added in Base Bid
ii. RA Humidity sensor
1. Provide ADD ALTERNATE - this will be for alarming only, not for control of unit
iii. Filter air pressure drop sensor
1. Provide ADD ALTERNATE - this will be for alarming only, not for control of unit
f. Zone Duct Booster Coil:
i. Discharge air temp sensor
1. Provide ADD ALTERNATE - this will be for alarming only, not for control of unit
ii. Is warmer/cooler adjust desired for room sensor?
1. Yes, required – to be added in Base Bid
g. VAV Boxes with reheat coil:
i. Discharge air temp sensor
1. Provide ADD ALTERNATE - this will be for alarming only, not for control of unit
ii. Is warmer/cooler adjust desired for room sensor?
1. Yes, required – to be added in Base Bid
h. Vertical Unit Ventilators:
i. Replace existing sequence of operation reflected in Exhibit C with new Exhibit D (Sequence of Operations – Vertical Unit Ventilators) – dated 7/28/2026
ACKNOWLEDGEMENT – ADDENDUM NO. 1
All bidders must acknowledge receipt of this Addendum No. 1 by signing and returning this form with their bid submission, or by noting receipt of this addendum in the space provided on the Bid Form.
Company Name: _____________________________________________________________
Authorized Signature: __________________________________________________________
Printed Name: ________________________________________________________________
Date: ________________________________________________________________________
END OF ADDENDUM NO. 1
File details come from the government source that posted it. Updated .