This document provides a code and criteria review for a federal contract opportunity to repair BE Admin and Shops buildings 4210 and 4211 for the Florida Air National Guard. The review identifies no required changes to previously submitted civil, structural, architectural, mechanical, plumbing, telecommunications, or electrical engineering documents. For fire protection engineering, the review recommends updating the reference to UFC 3-600-01 on sheet F-003 to reflect the current change. For electrical engineering, changes to lighting requirements and controls in some areas would be needed to comply with updated ASHRAE 90.1 and UFC 3-530-01.
The related federal contract opportunity is a solicitation set aside for small businesses to award a firm fixed price contract for repair services. The North American Industry Classification System code is 236220. The pre-bid conference will take place on January 26, 2024 and site visits will follow. The contract duration is 300 calendar days after notice to proceed and the magnitude of construction is estimated between $5,000,000 to $10,000,000.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Air National Guard
Camp Blanding Joint Training
Center 202 Red Horse Squadron
Repair BE Admin & Shops
Bldgs 4210 & 4211 Project Number: CYQL152003
Contract Number: W50S6Y-23-0004
12 December 2023
Code and Criteria Review Submittal
Prepared by:
Tetra Tech Project No.: 213-38546-24001
M&H Project No.: 4363500-171034.01
Code and Criteria Review
Project Number: CYQL152003 Repair BE Admin & Shops Bldg 4210 & 4211, Florida ANG
Code and Criteria Review Contract Number: W911YN-19-F-0059
The following Code and Criteria Review has been completed within conformance with the ANG Design
Objectives and Procedures (Tab C) dated April 16, 2010 for effort performed under work order
W911YN18F0019, dated 13 September 2018.
This review is the result of the research of ANG Engineering Technical Letters, Unified Facility Criteria, and building codes for updates and revisions relating to the project criteria and design project requirements since the competition of the Type B-3 Submittal, dated November 19, 2021.
The following codes and criteria were utilized in the development of the Type B-3 Submittal documents.
Those found to have experienced updates have been noted below at each occurrence:
DoD Design Requirements
Uniform Facility Requirements (UFC)
UFC 1-200-01 DoD Building Code (General Building Requirements); 01 December 2020 updated
Change 2, 01 July 2022
UFC 1-200-02 High Performance and Sustainable Building Requirements; 01 December 2020 Updated
Change 2, 01 June 2022
UFC 3-101-01 Architecture: 16 December 2020 Updated Change 2, 02 October 2023
UFC 3-110-03 Roofing; Change 5, 12 June 2020
UFC 3-120-01 Design: Sign Standards; Change 3, 12 December 2017 Updated Change 4, 01 February
UFC 3-120-10 Interior Design: 16 May 2018 Updated Change 2,15 June 2021
UFC 3-301-01 Structural Engineering: 1 October 2019 Updated Change 2 October 2023
UFC 3-400-02 Design: Engineering Weather Data; 20 September 2018
UFC 3-401-01 Mechanical Engineering; Change 1, 01 October 2015
UFC 3-420-01 Plumbing Systems: Change 11, 01 November 2019 updated 01 April 2021
UFC 3-501-01 Electrical Engineering; 01 November 2019
UFC 3-520-01 Interior Electrical Systems; 06 October 2015
UFC 3-530-01 Interior and Exterior Lighting Systems and Controls; Change 3, 01 June 2016 Updated 09
February 2023
UFC 3-550-01 Exterior Electrical Power Distribution: 01 September 2016 Updated Change 3, 01
November 2019
UFC 3-560-01 Electrical Safety, O&M; Change 5, 14 April 2015 Updated Change 3, 15 May 2023
UFC 3-580-01 Telecommunications Interior Infrastructure Planning and Design.
Change 1, 01 June 2016
UFC 3-600-01 Fire Protection Engineering for Facilities; Change 1, 28 November 2016, Change 4, 7
February 2020 updated Change 6, published 6 May 2021
UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings; Change 1, 19 August 2020 Updated
Change 2, 30 July 2022
Code and Criteria Review
Project Number: CYQL152003 Repair BE Admin & Shops
Public Law
Public Law 1095-58 Energy Policy Act (EPAct) of 2005; 08 August 2005
Accessibility for DoD Facilities
ABA ABA Accessibility Standard for Department of Defense Facilities; 31 October 2008
Air National Guard Requirements
Air National Guard Handbooks (ANGH)
ANGH 32-1084 Air National Guard Handbook, Facility Space Standards; 20 December 2015 updated 30 March 2022
ANGETL 15-01 Air National Guard Design Policy; 01 May 2015
Public Codes
International Code Council (ICC)
IBC International Building Code; 2018
IPC International Plumbing Code; 2018
IMC International Mechanical Code; 2018
IEC International Electrical Code; 2018
American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)
ASHRAE Standard 55 Thermal Environmental Conditions for Human Occupancy; 2013 2020
ASHRAE Standard 62.1 Ventilation for Acceptable Indoor Air Quality; 2010 updated 2016
ASHRAE Standard 90.1 Energy Standard for Buildings Except Low-Rise Residential Buildings (IP);
2013 2022
National Fire Protection Association (NFPA)
NFPA 13 Standard for the Installation of Sprinkler Systems; 2013 2022
NFPA 25 Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems; 2014 2023
NFPA 70 National Electrical Code; 2014 2023
NFPA 72 National Fire Alarm Code and Signaling Code; 2013 2022
NFPA 75 Standard for the Fire Protection of Information Technology Equipment; 2013
NFPA 90A Standard for the Installation of Air-Conditioning Ventilating Systems; 2015
NFPA 101 Life Safety Code; 2015 2024
NFPA 170 Standard for Fire Safety and Emergency Symbols; 2015 2024
NFPA 241 Standard for Safeguarding Construction, Alteration and Demolition
Operations; 2013 2022
NFPA 780 Standard for the Installation of Lightning Protection Systems; 2014 2023
Code and Criteria Review
Project Number: CYQL152003 Repair BE Admin & Shops
Civil Engineering Summary
We find there are no significant changes to the applicable current code and criteria requiring modifications to the Civil Engineering documents within the Type B-3 Submittal. The project is designed as compliant with current code and criteria.
Structural Engineering Summary
We find there are no significant changes to the applicable current code and criteria requiring modifications to the Structural Engineering documents within the Type B-3 Submittal. The project is designed as compliant with current code and criteria.
Architectural Summary
We find there are no significant changes to the applicable current code and criteria requiring modifications to the Architectural documents within the Type B-3 Submittal. The project is designed as compliant with current code and criteria.
Mechanical and Plumbing Engineering Summary
We find there are no significant changes to the applicable current code and criteria requiring modifications to the Mechanical and Plumbing Engineering documents within the Type B-3 Submittal. The project is designed as compliant with current code and criteria.
Fire Protection Engineering Summary
The following summarizes the Code and Criteria changes for Fire Protection Engineering:
UFC 3-600-01 Fire Protection Engineering for Facilities; Change 6, 6 May 2021.
Most changes are revisions in UFC 3-600-01 that address the authority over some fire protection features, scoping regarding branch-specific guidelines, and expanding definitions. UFC 3-600-01 Change
6 scopes in the latest editions of the NFPA standards. A notable change in NFPA 13 Chapter 19 moved away from the use of density/area curves for the standard occupancy classes to a single-point density option for new systems.
Per UFC 3-600-01, Change 6, the following list outlines the changes as they relate to the project:
• Included a new section 10-7 for Accessible Means of Egress
• Section 1-4.2.2 changes the authority over features in excess of the requirements in UFC from the “Authority Having Jurisdiction (AHJ)” to a Component Fire Protection Engineer (CFPE)” along with an expanded definition of a CFPE in Section 2-1.4.
• Section 1-4.2.5 notes that the Air Force issues specific technical guidelines (Air Force Guidance
Manual (AFGM)) that expand the requirements of the UFC.
• Section 2-1.2 provides the definition of “Ammunitions and Explosives.”
• Section 9-7.6.3 states that the Air Force permits the use of CPVC and other listed plastic sprinkler pipe in any occupancy in which an approved listing exists when installed in strict accordance with the approved listing.
Code and Criteria Review
Project Number: CYQL152003 Repair BE Admin & Shops
• Section 10-7 is a new section regarding the Accessible Means of egress – all exits of both buildings are considered accessible as they open to grade and the building is a single story. Both buildings are compliant.
The Type B-3 Submitted Code Sheet F-003 lists the project as complying with UFC 3-600-01 (Change 4, 7 February 2020). This standard has since been updated with to Change 6, published 6 May 2021. We recommend this reference be updated on this sheet. Other than this sheet, we find there are no significant changes in the building codes and NFPA standards requiring modifications to the Fire
Protection documents within the Type B-3 Submittal. The project is designed as compliant with current code and criteria.
Electrical Engineering Summary
The following summarizes the Code and Criteria changes for Electrical Engineering:
ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise Residential Buildings (IP) 2022
UFC 3-530-01 Interior and Exterior Lighting Systems and Controls; Change 09 February 2023
The changes and updates to ASHRAE 90.1 & and UFC 3-530-01 do affect lighting requirements within the scope of this project. To be in compliance, lighting fixtures in some areas will require change. The lighting layout as designed would require reanalyzing. Lighting controls in some areas require change to provide additional AUTO&MANUAL-ON/AUTO&MANUAL-OFF controls.
Telecommunications Engineering Summary
We find there are no significant changes to the applicable current code and criteria requiring modifications to the Telecommunications documents within the Type B-3 Submittal. The project is designed as compliant with current code and criteria.
END OF REPORT.