This Addendum No. 2, issued November 7, 2025, by Century A&E modifies the original bidding documents for the State of Michigan Department of Transportation and Mackinac (DTMB) Department of Natural Resources project for Mears State Park Modern Campground Electrical Upgrades in Pentwater, Michigan (Project No. MIS044, DTMB File No. 751/25207.HJD). The addendum forms part of the contract documents and must be initialed and submitted with the bidder's bid package; failure to acknowledge receipt in the bid form may result in bidder disqualification. The original bidding documents were dated October 15, 2025, and all work covered under this addendum remains subject to the previously provided Plans and Specifications.
The sole change contained in Addendum No. 2 is the deletion of Item 1 from Addendum 1, which had provided a clarification regarding the construction commencement date of October 3, 2022, as stated in Section 00800, Appendix I, item 7.2. No pricing terms, set-asides, funding sources, or other financial information is included in this addendum document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 2
November 7, 2025
RE: State of Michigan DTMB Department of Natural Resources Mears State Park Modern Campground - Electrical Upgrades Pentwater, Michigan Century A&E Project No. MIS044 DTMB File No. 751/25207.HJD
TO: PROSPECTIVE BIDDERS
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated October 15, 2025. This addendum is to be initialed and submitted as part of Bidder's bid package; failure to do so may subject Bidder to disqualification.
This Addendum consists of:
One (1) typed page
INSTRUCTIONS
1. All work covered in this addendum shall be subject to the Plans and Specifications previously provided.
2. The Contractor must acknowledge receipt of this addendum in the bid form(s).
CHANGES AND/OR ADDITIONS
1. Delete Item 1. issued in Addendum 1 under Changes and/or Additions: "As a clarification, the date to commence construction onsite is October 3, 2022, as stated in section 00800, Appendix I, item 7.2."
END OF ADDENDUM NO. 2
Respectfully submitted, Century A&E
Matthew A. Tipping PSC Project Manager
Distribution: All Bidders & Project Team