S1904-1_CLEANLINESS_REQUIREMENTS_FOR_HYDRAULIC_PIPING_SYSTEMS.pdf

PDF 52 KB Posted

Attached to
Drydock Repair Services in the Hawaii Region
Solicitation number
AB-133M-17-RQ-0857
Issued by

About this file

Support Document

View the file

Other files

File Type Posted
Combined_Synopsis_Solicitation_V4.pdf PDF
Amendment_0006.pdf PDF
Document_3,_Statement_of_Work_for_Task_Order_0001_Sette_Drydock_V1.pdf PDF
Amendment_0005.pdf PDF
AD-574-001_A-Frame_Strl_Arr_&_Dets_01_Rev_-.DWG DWG drawing
AD-574-001_A-Frame_Strl_Arr_&_Dets_03_Rev_-.DWG DWG drawing
AD-574-002_Deck_Machinery_J-Frame_Arr_&_Dets_02_Rev_-.DWG DWG drawing
HI-574-001_Rev_A_Deck_Machinery_A-Frame_Arrgt_Dtls.pdf PDF
HI-574-002_2.TIF TIF image
AD-574-002_Deck_Machinery_J-Frame_Arr_&_Dets_04_Rev_-.DWG DWG drawing
HI_575_01_Electric_Drive_Oceanographic_Winch.pdf PDF
HI-574-002_4.TIF TIF image
HI-574-002_3.TIF TIF image
AD-574-002_Deck_Machinery_J-Frame_Arr_&_Dets_06_Rev_-.DWG DWG drawing
HI-574-002_5.TIF TIF image
AD-574-002_Deck_Machinery_J-Frame_Arr_&_Dets_03_Rev_-.DWG DWG drawing
AD-574-002_Deck_Machinery_J-Frame_Arr_&_Dets_05_Rev_-.DWG DWG drawing
Amendment_0004.pdf PDF
GU_KA_581_02_MAN_ANCHOR_WINDLASS_AND_CAPSTAN.pdf PDF
HI-574-001_1.TIF TIF image
HI-574-002_Rev_A_Deck_Machinery_J-Frame_Arrgt_Dtls.pdf PDF
AD-574-001_A-Frame_Strl_Arr_&_Dets_02_Rev_-.DWG DWG drawing
AD-574-002_Deck_Machinery_J-Frame_Arr_&_Dets_01_Rev_-.DWG DWG drawing
Part_7_e-July17.pdf PDF
Part_7_Guide_to_Colors.pdf PDF
243-6233870.pdf PDF
OS_556_01_CENTRAL_HYDRAULICS_SYSTEM_INSTALLATION.pdf PDF
OS-163-623356_1.pdf PDF
HI_243_02_Stern_Tube_Bearings_&_Seals.pdf PDF
s2906_VESSEL_ARC_WELDING.pdf PDF
Part_1_Ships_e-Apr17.pdf PDF
OS-528-6233824_4.pdf PDF
S2603A_GROUND_TACKLE.pdf PDF
HI_243_01_Shafting_Details.pdf PDF
Part_7_Corrigenda-July17.pdf PDF
CFR-2005-title46-vol4-chapI-subchapJ.pdf PDF
Part_2_e-Jan17.pdf PDF
SVR_Part_5A&B_e-July17.pdf PDF
Part_1_Ships_Guide_to_Colors.pdf PDF
436-6233675_2.pdf PDF
SVR_Guide_to_Colors.pdf PDF
OS-528-6233824_2.pdf PDF
CFR-2012-title46-vol2-chapI-subchapF.pdf PDF
OS-085-002.pdf PDF
OS-163-6233563_2.pdf PDF
AMC-000-3C_GENERAL_REQUIREMENTS_FOR_SMALL_CONTRACT_SHIP_REPAIRS.pdf PDF
IMPLEMENTATION_AND_CONDUCT_OF_CHECK_POINTS.pdf PDF
635-2_THERMAL_INSULATION_FOR_COMPARTMENTS.pdf PDF
S1402_TERRAZZO_DECK_COVERING_INSTALLATION.pdf PDF
Part_7_Notice_1.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

August, 1994

NOAA Standard Specification - S1904-1

CLEANLINESS REQUIREMENTS FOR HYDRAULIC PIPING SYSTEMS

1. SCOPE

New hydraulic piping systems and repaired or modified existing hydraulic piping systems shall conform to this specification.

2. GENERAL REQUIREMENTS FOR CLEANLINESS

2.1 New Piping: All new pipe and fittings such as welded or brazed elbows and flanges, shall be thoroughly deburred, cleaned and pickled prior to final installation in the system. Cleaning and pickling shall conform to paragraphs (3) and (4) respectively. For "Fit-Up" purposes, new pipe sections may be initially installed without cleaning or pickling, providing that these pipe sections have been deburred on the ends and flushed or blown out to insure that loose particles will not fall into existing installed pipe sections, or other system components. After "Fit-Up" has been completed, the new pipe and fittings shall be removed, cleaned and pickled. Under no condition, shall oil be circulated through new pipe and fittings when installed in the system, until deburring, cleaning and pickling has been completed. After cleaning and pickling has been completed, pipe ends shall be capped until installed in the system. No further burning, cutting or welding will be permitted on cleaned and pickled piping.

2.1.1 In place cleaning and pickling of new system pipe will be authorized on a case basis subject to approval of the government representative. All components subject to damage such as pumps, motors, valves, etc., shall be jumpered prior to circulating cleaning and pickling solutions.

2.2 Existing Piping: All existing piping sections that are to be burned, cut or welded, shall be removed from the system and treated as a "new pipe section", with fit-up, cleaning and pickling requirements as in 2.1 above. All existing piping connections that are opened for removal of equipment, shall be adequately capped to prevent entry of foreign matter, while system components are being repaired.

2.2.1 In place cleaning and pickling of new pipe installed in an existing system will be authorized on a case basis subject to the approval of the government representative. All components subject to damage such as pumps, motors, valves, etc., shall be jumpered prior to circulating, cleaning and pickling solutions.

Cleanliness Requirements for Hydraulic Piping Systems

S1904-1

2.3 Flushing

2.3.1 New Hydraulic System Installations: (i.e., new pipe, fittings, components, tanks, etc.) Flushing shall be as follows:

Piping shall be flushed by installing temporary jumpers around each component. A temporary pump and temporary strainer shall be installed in the system. The strainer shall be of a 10 micron mesh replaceable element type with a pressure drop not to exceed the tolerances of the manufacturer at the flow and temperature for the type fluid used. Hydraulic fluid of the same type to be installed in the system shall be circulated until no appreciable quantity of soil is deposited on the strainers. The filter element shall be checked and replaced whenever the pressure drop reaches the limits specified. The system shall be drained, the jumpers, temporary strainers and pump shall be removed and the piping assembly connected to all components, after flushing is completed.

2.3.2 Modified or Repaired Hydraulic Systems: Flushing shall not normally be required unless specifically called for by the work item or unless there is reasonable evidence to show that the Contractor has not taken precautions to prevent entry of foreign matter into the piping system.

3. CLEANING METHOD

Pipe sections shall be cleaned as follows in preparation for pickling:

a. Wire brush interior and exterior.

b. Submerge in a hot lye or tri-sodium phosphate (or equivalent) solution for approximately 15 minutes, followed by a water rinse. Dry and cap pipe unless pickling follows immediately.

4. PICKLING

Pickling shall be comparable to methods used by commercial electro-plating/pickling companies, and in general, piping pickled by commercial pickling companies is acceptable. The following procedures, or an approved equivalent, are acceptable, when pickling is accomplished by the Contractor:

4.1 Bronze, Copper and Copper-Nickel:

a. Pickle free from scale in solution of the following composition at room temperature:

Sulfuric acid, 66° Baume, sp.gr. 1.83, conforming to Type 1, Class 1 of

0-S-809 . . . . . . . . . . . . . . . 7-14 fl. oz.

Water . . . . . . . . . . . . . . . . 1 gallon

(Caution. The acid shall always be added carefully to the water.)

NOTE: If red stains appear, immerse the work briefly in a solution formulated as above but which contains in addition 2-4 oz. of sodium dichromate (per gallon) conforming to 0-S-595. This solution shall be maintained at a temperature range of 70° to 120°F.

4.2 Monel:

a. Pickle for 20 to 40 minutes in a hot solution (180°

± 10°F) of the following composition:

Hydrochloric acid, 20° Baume, sp. gr. 1.16

(See O-H-765). . . . . . . . . . 1/2 gallon

Cupric Chloride. . . . . . . . . 4 ounces

Water. . . . . . . . . . . . . . 1 gallon

b. Rinse in hot water.

c. Immerse for 5 to 10 minutes in a bath composed as follows (temperature 70° to 100°F).

Sulfuric acid, 66°, Baume, sp.gr. 1.83 conforming to type 1, Class 1 of O-S-809 . . . . . . . 13 fl. oz.

Sodium Dichromate (See O-S-595) . 17 1/2 oz.

Water . . . . . . . . . . . . . . 1 gallon

4.3 Ferrous Steel Other Than CRES:

a. Pickle free from rust and scale in a hot solution (150° ± 10°F) of the following composition:

Sulfuric acid, 66°, Baume, sp.gr. 1.83 conforming to type 1, Class 1 of O-S-809 . . . . . . . 7-14 fl. oz.

Inhibitor (see O-I-501) . . . . . Quantity recommended by manufacturer

4.4 Corrosion Resistant Steel:

a. Immerse work for 10 to 15 minutes in a hot solution (130° ± 10°F) of the following composition:

Nitric Acid (See O-N-350) . . . . 13-20 fl. oz.

Hydrofluoric Acid (60%)

(See O-H-795) . . . . . . . . . 1-2 fl. oz.

b. Rinse in a clean, warm water bath.

c. If hydrostatic test is to be performed with hydraulic oil (see 3.3.14), dry the piping assembly with clean air.

5. TREATMENT FOLLOWING PICKLING

a. Immediately after pickling, rinse in a clean, warm water bath.

b. Neutralize traces of acid from the pickling operation by rinsing the work in an alkaline bath containing four (4) ounces (per gallon of water) of soda ash conforming to O-S-571.

c. Rinse thoroughly in fresh, warm water.

d. Dry and cap.