A10_1-12970224R0018-Att1-FillableSOI.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Santa Fe National Forest HPCC Capulin Fencing
Solicitation number
12970224R0018
Issued by

About this file

This document is a Schedule of Items (SOI) for the Santa Fe National Forest HPCC Capulin Fencing solicitation. The SOI provides a detailed breakdown of the items required for the fencing installation project, including mobilization, installation materials and labor, existing fence removal, and hazard tree removal. The estimated quantities are provided, and the vendor is required to input pricing for each line item. The total set-aside is for small businesses located in specified counties in New Mexico. The solicitation seeks proposals for construction services to install boundary and recreational fencing, including removal of existing fencing and hazard tree felling, with an estimated project value between $1,000,000 and $5,000,000. A mandatory pre-proposal site visit is scheduled for April 19, 2024, and the contract will be awarded to a single vendor.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

PART I - THE SCHEDULE

B.1 SCHEDULE OF ITEMS

Santa Fe National Forest HPCC Capulin Fencing
Santa Fe National Forest
VENDORS PLEASE NOTE: BEFORE PREPARING QUOTE, CAREFULLY READ THE CONTENTS OF THIS SOLICITATION.
ITEM NO.DESCRIPTIONQNTYUNITUNIT PRICEAMOUNT
0001Capulin Allotment Exterior Fence Installation1LSQ
1Mobilization1LSQ
2Installation Material23LM
3Installation Labor23LM
4Existing Fence Removal23LM
5Hazard Tree Removal1LSQ
Subtotal
Bonding
TOTAL

VENDOR NAME: BUSINESS EMAIL:

SAM UEI #: BUSINESS PHONE:

AUTHORIZED TO SIGN: (NAME & TITLE)

SIGNATURE: DATE:

SOI NOTES:
1VENDOR INPUT REQUIRED
2LSQ - LUMP SUM QUANTITY
3LM - LINEAR MILE
4ANY AWARD WILL BE TO ONE QUOTER
5THE REFERENCED QUANTITIES ARE ESTIMATES ONLY. NO GUARANTEES ARE MADE AS TO THE PRECISE QUANTITIES. IN THIS CASE OF A FIRM-FIXED-PRICE CONTRACT, THE AGENCY SHALL NOT BE HELD LIABLE FOR REASONABLE VARIATIONS IN THESE ESTIMATED QUANITITES, NOT CONSTITUTING A SUBSTANTIVE CHANGE IN REQUIREMENT SCOPE

File details come from the government source that posted it. Updated .