U.S. DEPARTMENT OF THE INTERIOR – BUREAU OF LAND MANAGEMENT

RADIO FACILITY TECHNICAL PACKAGE 1 – NEVADA

Virginia Peak 01 11 00 - 56 Bid Schedule

10/19/2020

PART 5: VIRGINIA PEAK – BID SCHEDULE

BID ITEM SOW REF

Unit of

Measure

UNITS MATERIALS LABOR TOTAL

2.3 DESIGN DRAWINGS (A&E)

Civil Improvement Plans 2.3 each 1 $ $ $

Third Party Inspection Services 3.6 each 1 $ $ $

2.3 DESIGN SERVICES $ $ $

3.5.1 PHOTOVOLTAIC POWER AND BATTERY BACKUP SYSTEM

Remove and Reinstall Solar Panels 3.5.1 each 2 $ $ $

3.5.1 Photovoltaic and Battery System - SUBTOTAL $ $ $

3.7 COMMUNICATIONS EQUIPMENT SHELTER INSTALLATION

Relocate and Install Existing Pepro Cabinet with 20-foot articulating mast 3.7 Lump Sum 1 $ $ $

3.7 Shelter - SUBTOTAL $ - $ - $ -

3.11 EXTERNAL RF CABLE & WAVEGUIDE INSTALLATION

Remove and Reinstall RF Cable 3.11 each 1 $ $ $

Test RF Cable and Antenna 3.11 each 1 $ $ $

3.11 External Cable Installation - SUBTOTAL $ $ $

3.12 ANTENNA SYSTEMS INSTALLATION

Remove and Reinstall Antenna 3.12 each 1 $ $ $

3.12 Antenna Systems - SUBTOTAL $ $ $

3.14 COMMON EXTERNAL GROUNDING SYSTEM

Trenching for Grounding System 3.14 per lineal foot 130 $ $ $

Virginia Peak 01 11 00 - 57 Bid Schedule

BID ITEM SOW REF

Unit of

Measure

UNITS MATERIALS LABOR TOTAL

Provide and Install Ground Rods: (3/4" diameter, 10-foot long) 3.14 each 10 $ $ $

Provide and Install External Grounding Conductor: # 2 AWG, bare, solid, tinned, copper for Grounding System

3.14 per lineal foot 150 $ $ $

Backfilling for Grounding System (Includes Grounding Enhancement Material for High Soil Resistivity Sites)

3.14 per lineal foot 150 $ $ $

Bond Existing Tower Ground Bus Bar (TGB) to Ground Ring - Remote Facilities 3.14 each 1 $ $ $

Concrete Encased Electrodes in Shelter Foundation Connected to the Shelter Ground Ring 3.14 each 4 $ $ $

Ground Each Grounding Tab on the Cabinet (x3) to the Grounding System 3.14 each 3 $ $ $

Solar Panel and Framework Grounding 3.14 each 2 $ $ $

RF Cables Grounded at Base of Pipe Mast 3.14 each 1 $ $ $

Ground RF Cable to Entry Port using Stainless Steel Strap Provided by Pepro 3.14 each 1 $ $ $

RF Cable Surge Protection 3.14 each 1 $ $ $

3.14 External Grounding - SUBTOTAL $ $ $

3.16 EQUIPMENT RACKS AND CABINETS

Ground Rack-Mounted Equipment (per device to be grounded) 3.16 each 3 $ $ $

3.16 Equipment Racks and Cabinets - SUBTOTAL $ $ $

COST SUMMARY MATERIALS LABOR TOTAL

LABOR AND MATERIALS - SUBTOTAL $ $ $

MATERIAL HANDLING AND DELIVERY $ $ $

MOBILIZATION FEES $ $ $

OTHER DIRECT COSTS $ $ $

BOND $ $ $

Virginia Peak 01 11 00 - 58 Bid Schedule

PROJECT MANAGEMENT FEES $ $ $

OVERHEAD $ $ $

PROFIT $ $ $

TOTAL ESTIMATED COST $ $ $